Washington / Snohomish County

Electrical Permit in Snohomish County, Washington

By Mario Bailey Last checked 2026-07-06 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

Snohomish County Planning and Development Services does not administer electrical permits in unincorporated Snohomish County. Residential electrical work, including wiring installation, modification, or design, requires a permit from the Washington State Department of Labor and Industries (L&I), purchased online through L&I's Electronic Permit/Inspection System or in person at L&I's Everett field office. This applies to unincorporated Snohomish County; cities within the county such as Everett, Marysville, Lynnwood, and Mountlake Terrace run their own electrical permit programs within their own city limits.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Snohomish County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

For any residential electrical wiring, panel, or fixture work in unincorporated Snohomish County

What electrical permit costs in Snohomish County

No county fee; electrical permitting and inspection in unincorporated Snohomish County is handled statewide by the Washington State Department of Labor and Industries, so fees follow the L&I schedule.

How Snohomish County compares in Washington

No Washington jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
BellevuePermit requiredElectrical permit fee by valuation per Table 6 of Ordinance 6879, $79 inspect...
Clark CountyPermit requiredNo county fee;
King CountyPermit requiredSet by state L&I, not King County, under WAC 296-46B-906 (effective 7/1/2026)...
Pierce CountyPermit requiredNo county fee;
SeattlePermit requiredItemized per Fee Subtitle Table D-15: minimum $105.12 for a standard online s...
Snohomish Countythis pagePermit requiredNo county fee;
TacomaPermit requiredNo Planning and Development Services fee;

How to apply in Snohomish County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Washington State Department of Labor and Industries sets the exact checklist for Snohomish County.

Where to apply in Snohomish County:

Washington State Department of Labor and Industries

  • 729 100th St. SE, Everett, WA 98208-3727
  • Phone: 425-290-1309

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Snohomish County permit portal or by phone at 425-290-1309.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a electrical permit in Snohomish County?
Snohomish County Planning and Development Services does not administer electrical permits in unincorporated Snohomish County. Residential electrical work, including wiring installation, modification, or design, requires a permit from the Washington State Department of Labor and Industries (L&I), purchased online through L&I's Electronic Permit/Inspection System or in person at L&I's Everett field office. This applies to unincorporated Snohomish County; cities within the county such as Everett, Marysville, Lynnwood, and Mountlake Terrace run their own electrical permit programs within their own city limits. Always confirm with the Washington State Department of Labor and Industries before starting.
How much does a electrical permit cost in Snohomish County?
No county fee; electrical permitting and inspection in unincorporated Snohomish County is handled statewide by the Washington State Department of Labor and Industries, so fees follow the L&I schedule. Contact the office for current amounts.
Where do you apply for a electrical permit in Snohomish County?
You can apply through the Snohomish County permit portal or contact the Washington State Department of Labor and Industries directly. The links are listed on this page.

From the Library

What else needs a permit in Snohomish County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsuncovered decks, deck steps, and uncovered porches for residential buildings exempt if 30 inches or less above adjacent grade at any point, not over a basement or story below, and not part of a required accessible route; covered or taller decks require a permitBase application fee $150 per application plus 3% technology surcharge and $6.50 Washin...
Fence PermitIt dependsfences 8 feet or less in height exempt, provided they have no masonry or concrete elements above 6 feet (wire strands atop an 8-foot fence are excluded from the height measurement); taller fences, or fences with masonry/concrete above 6 feet, require a permitBase application fee $150 per application plus 3% technology surcharge and $6.50 Washin...
HVAC PermitPermit requiredNot specifiedFiled as a Mech/Plbg residential trade permit priced from the PDS valuation table start...
Patio PermitIt dependsopen at-grade patios are treated as exempt sidewalks and driveways under SCC 30.50.103(1)(e) with no size limit; freestanding patio covers (roofed, not attached to another structure) are exempt only if 200 sq ft or less inside the UGA or 400 sq ft or less outside the UGA; larger or attached patio covers require a permitPriced from the PDS valuation table starting at a $45 permit fee plus $29.25 plan check...
Plumbing PermitPermit requiredNot specifiedFiled as a Mech/Plbg residential trade permit priced from the PDS valuation table start...
Pool PermitIt dependsprefabricated swimming pools regulated under the IRC (one- and two-family dwellings) exempt if less than 24 inches deep, with no gallon-volume cap; in-ground pools or pools 24 inches deep or more require a building permitPriced from the PDS valuation table starting at a $45 permit fee plus $29.25 plan check...
Roof Replacement PermitIt dependsre-roof overlay or tear-off-and-replace of a residential roof exempt if limited to 2 total layers of roofing material, uses the same type of roofing material as the existing roof, and the roof sheathing is not removed or replaced; adding a layer beyond 2, changing material type, or replacing sheathing requires a permitA like-for-like reroof limited to 2 layers with no sheathing removal needs no permit;
Shed PermitIt dependsone-story detached accessory structure not used for human habitation (tool/storage shed, playhouse) exempt if floor area is 200 sq ft or less and sidewalls 9 ft or less inside the Urban Growth Area (UGA), or 400 sq ft or less and sidewalls 11 ft or less outside the UGA; larger structures require a building permitBase application fee $150 per application plus 3% technology surcharge and $6.50 Washin...
Solar PermitIt dependsground-mounted residential solar PV systems never need a building or mechanical permit; roof-mounted residential PV on a detached single-family house is exempt from a building/mechanical permit only if total dead load is 3.5 lbs per sq ft or less (up to 4.5 lbs per sq ft for frameless panels on a 3:12 or steeper slope, or 5 lbs per sq ft for frameless panels on a 5:12 or steeper slope), panels are mounted 18 inches or less above the roof surface, and an electrical permit has already been issued; a separate electrical permit through WA L&I is always required regardlessGround-mounted and qualifying roof-mounted residential solar PV need no county building...

Electrical Permit in other Washington localities

Official sources

Verified by a person against the sources above on 2026-07-06, not confirmed with Washington State Department of Labor and Industries. Rules change; confirm before you build. How we verify.

Last checked: 2026-07-06Report an error on this page