New Mexico / Albuquerque

Shed Permit in Albuquerque, New Mexico

It depends

Sometimes, depending on the project

Before building a detached accessory building larger than 120 sq ft, or one of any size with more than one story.

Confirmed on official page Verified

Issued byCity of Albuquerque Planning Department, Building Safety Division

By Mario Bailey, verified against official sources

Quick answer

A one-story detached accessory building used as a tool or storage shed, playhouse or similar use needs no building permit if its building area does not exceed 120 square feet; anything larger needs a building permit with plans. Electrical, plumbing or mechanical work in an exempt shed still needs its own trade permit.

Typical threshold: Building area of a one-story detached accessory building used as a tool or storage shed, playhouse or similar use.

Diagram of the 120 sq ft footprint area threshold for a shed permit in Albuquerque, New Mexico
Threshold illustrated: 120 sq ft. Whether Albuquerque requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-10-23.

Who is pulling this permit?

Hire it out

Sponsored

If a contractor builds or places your shed, they usually handle any required permit. Compare a few bids before you commit.

Compare contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before building a detached accessory building larger than 120 sq ft, or one of any size with more than one story.

What a shed permit costs in Albuquerque

Line item
shed permitBy formulaBuilding permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to $500.00": $23.50; "$2,001.00 to $25,000.00": "$69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof"), multiplied by the Albuquerque Regional Modifier of (.50) for one- and two-family dwellings, minimum fee $23.50; plan review fee is 65 percent of the building permit fee, paid at submittal. City of Albuquerque 2024 Uniform Administrative Code (UAC), Section 112 and Tables 112-A through 112-G, cover date effective January 1, 2025.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Albuquerque compares in New Mexico

Closest shed permit thresholds outside New Mexico

Jurisdictions we cover whose limit sits nearest Albuquerque's 120 sq ft.

How to apply in Albuquerque

In Albuquerque, a residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • For Albuquerque, a written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • For Albuquerque, a scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. City of Albuquerque Planning Department, Building Safety Division sets the exact checklist for Albuquerque.

Where to apply in Albuquerque:

City of Albuquerque Planning Department, Building Safety Division

Shed Permit in Albuquerque compared with nearby New Mexico localities

LocalityPermit needed?ThresholdWhat each New Mexico schedule saysVerified
AlbuquerqueIt dependsBuilding area of a one-story detached accessory building used as a tool or storage shed, playhouse or similar use...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to...
Bernalillo CountyIt dependsone-story detached accessory building used as a tool or storage shed, playhouse or similar use...under Administrative Resolution 25-2009 (effective May 1, 2009), Table 3-A: "$30.00...

Inspections and closing out your permit

In Albuquerque, a permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection in Albuquerque: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection in Albuquerque: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection in Albuquerque: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. In Albuquerque: for a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Albuquerque permit portal or by phone at (505) 924-3320.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Albuquerque

In 2025, Albuquerque authorized permits for 1,417 new residential housing units (525 single-family, 892 in multi-family buildings), valued at $219M, up from 1,099 the year before. That works out to about 2.5 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 562,540.

Frequently asked questions

Do you need a shed permit in Albuquerque?
A one-story detached accessory building used as a tool or storage shed, playhouse or similar use needs no building permit if its building area does not exceed 120 square feet; anything larger needs a building permit with plans. Electrical, plumbing or mechanical work in an exempt shed still needs its own trade permit. Building area of a one-story detached accessory building used as a tool or storage shed, playhouse or similar use. Always confirm with the office before starting.
How much does a shed permit cost in Albuquerque?
Building permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to $500.00": $23.50; "$2,001.00 to $25,000.00": "$69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof"), multiplied by the Albuquerque Regional Modifier of (.50) for one- and two-family dwellings, minimum fee $23.50; plan review fee is 65 percent of the building permit fee, paid at submittal. City of Albuquerque 2024 Uniform Administrative Code (UAC), Section 112 and Tables 112-A through 112-G, cover date effective January 1, 2025. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Albuquerque?
You can apply through the Albuquerque permit portal or contact the City of Albuquerque Planning Department, Building Safety Division directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Albuquerque?
Under New Mexico law (NMSA 1978, 60-13-3(D)(10), (11); 14.5.2.8(B) NMAC; 14.5.2.18 NMAC): Yes, with tight limits. CILA exempts from the contractor definition an individual who, alone or with wage-paid help, builds or makes installations, alterations or repairs to a single-family dwelling he owns and occupies or will occupy (60-13-3(D)(10)), and a person building or improving a single-family residence for personal use (60-13-3(D)(11)). The work must still meet all state codes, and CID's homeowner permit (14.5.2.18 NMAC) applies only to the owner's primary residence and its garages, carports and sheds, never to rental, other owned or commercial property. The homeowner must perform the major portion of the work by dollar amount and file a signed, notarized responsibility sheet. A homeowner electrical permit requires passing a CID homeowner electrical exam (75% to pass), a plumbing permit requires a competency showing that may include a written exam, and no homeowner permit is issued for HVAC, natural gas or LP gas work. The project may not be put on the market while under construction (doing so voids the permit and can bring unlicensed contracting charges), and only one single-family homeowner permit may be issued to the same owner in any 12-month period. Confirm how Albuquerque applies this before you apply.

From the Library

What else needs a permit in Albuquerque

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsFinish work and same-configuration fixture swaps are exempt; altered piping, new wiring or structural changes need permitsBuilding permit (if structural or layout work) by valuation under "TABLE 112-A BUILDING...
Deck PermitIt dependsPlatforms not over a story or basement below and not part of an accessible route...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to...
Electrical PermitIt dependsLike-for-like repair or replacement of receptacles, switch parts and fixed listed appliances is exempt; new or altered wiring, devices and equipment needs a permit...charge applicable to all applications and additions to permits" $47.00...
EV Charger PermitPermit requiredAny sizeElectrical permit under "TABLE 112-B ELECTRICAL PERMIT FEES": $47.00 administrative...
Fence PermitPermit requiredAny size...Construction Cost Guide Per Lineal Foot" (for example "Wood Fence (Cedar)" $23.30...
HVAC PermitPermit requiredAny size...charge applicable to all applications and additions to permit" $47.00...
Patio PermitIt dependsCovered versus uncovered: a patio cover or porch needs a building permit; an uncovered at-grade slab falls under the exemption for platforms and walks...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to...
Plumbing PermitIt dependsStopping leaks, clearing stoppages and replacing fixtures with the same type of configuration are exempt; new or altered piping needs a permit...charge applicable to all applications and additions to permit" $47.00...
Pool PermitIt dependsPrefabricated pools installed entirely above ground, not exceeding 5,000 gallons, accessory to a building under the International Residential Code...FEES" with the (.50) residential modifier, plus "Swimming pool (Private)" $60.00...
Roof Replacement PermitPermit requiredAny size...PERMIT FEES", "Residential (R-3 Occupancies Only)": Administrative Fee $30.00 +...
Solar PermitPermit requiredAny size...the (.50) residential modifier, plus an electrical permit under Table 112-B ($47.00...
Water Heater PermitPermit requiredAny sizePlumbing/mechanical permit with the $47.00 administrative charge (Tables 112-C and 112-D)

Shed Permit in other New Mexico localities

Everything above, sourced

cabq.gov: permitsread

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Albuquerque documents; the office above sets the local rules.

How this shed permit page for Albuquerque was verified. 2 official sources: cabq.gov, cabq.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Albuquerque Planning Department, Building Safety Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Shed Permit requirements across New Mexico localities

Shed permit rules nationwide

Look up an existing Albuquerque permit record

It depends
Get quotes