Massachusetts / Boston

Shed Permit in Boston, Massachusetts

It depends

We could not confirm this

For sheds with a floor area exceeding 120 sq ft

Based on building code Verified

Issued byInspectional Services Department

By Mario Bailey, verified against official sources

Typical job value
$8,700
declared valuation

Quick answer

Under Massachusetts 780 CMR, one-story detached accessory structures used as tool or storage sheds are exempt from the building permit requirement when the floor area is 120 square feet or less. Sheds exceeding 120 square feet require a building permit from Boston ISD. Zoning requirements still apply regardless of size.

Typical threshold: one-story detached accessory sheds used for tools or storage are exempt if floor area does not exceed 120 sq ft.

Diagram of the 120 sq ft footprint area threshold for a shed permit in Boston, Massachusetts
Threshold illustrated: 120 sq ft. Whether Boston requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-06-18.

Who is pulling this permit?

Hire it out

Sponsored

If a contractor builds or places your shed, they usually handle any required permit. Compare a few bids before you commit.

Compare contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

For sheds with a floor area exceeding 120 sq ft

What a shed permit costs in Boston

Line item
shed permitBy formulaSheds need a Use of Premises Permit at a $50 primary fee, named alongside pools on the city's Use of Premises page, per the ISD fee schedule effective 5/15/2023.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Boston compares in Massachusetts

Closest shed permit thresholds outside Massachusetts

Jurisdictions we cover whose limit sits nearest Boston's 120 sq ft.

  • Alameda County, California, Floor area of a one-story detached tool or storage shed accessory to a house, at which the building permit exemption stops
  • Aurora, Colorado, shed floor area at which a building permit is required
  • Baltimore County, Maryland, accessory structure floor area
  • Chandler, Arizona, One-story detached accessory structures (storage sheds, open-air ramadas) with floor area of 120 sq ft or less and height of 7 ft or less (up to 9 ft with 2 additional feet of setback per additional foot of height) are exempt if not connected to any electrical, gas, or water utility; exceeding either limit or connecting a utility requires a building permit.

How to apply in Boston

In Boston, a residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • For Boston, a written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • For Boston, a scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Inspectional Services Department sets the exact checklist for Boston.

Where to apply in Boston:

Inspectional Services Department

  • 1010 Massachusetts Avenue, 5th Floor, Boston, MA 02118
  • Phone: (617) 635-5300
  • Email: isd@boston.gov

Shed Permit in Boston compared with nearby Massachusetts localities

LocalityPermit needed?ThresholdWhat each Massachusetts schedule saysVerified
BostonIt dependsone-story detached accessory sheds used for tools or storage are exempt if floor area does not exceed 120 sq ftSheds need a Use of Premises Permit at a $50 primary fee, named alongside pools on the...
WorcesterIt dependsfloor area of a one-story detached storage shedNo shed line item.

Inspections and closing out your permit

In Boston, a permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection in Boston: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection in Boston: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection in Boston: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. In Boston: for a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Boston permit portal or by phone at (617) 635-5300.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Boston

In 2024, Boston authorized permits for 1,789 new residential housing units (72 single-family, 1,717 in multi-family buildings), valued at $812M, down from 2,051 the year before. That works out to about 2.6 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 691,531.

About Boston

Boston has about 307,840 housing units. The median home is valued at $710,400, against a median household income of $94,755. About 35% of homes are owner-occupied, and the typical home was built around 1947.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a shed permit in Boston?
Under Massachusetts 780 CMR, one-story detached accessory structures used as tool or storage sheds are exempt from the building permit requirement when the floor area is 120 square feet or less. Sheds exceeding 120 square feet require a building permit from Boston ISD. Zoning requirements still apply regardless of size. One-story detached accessory sheds used for tools or storage are exempt if floor area does not exceed 120 sq ft. Always confirm with the office before starting.
How much does a shed permit cost in Boston?
Sheds need a Use of Premises Permit at a $50 primary fee, named alongside pools on the city's Use of Premises page, per the ISD fee schedule effective 5/15/2023. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Boston?
You can apply through the Boston permit portal or contact the Inspectional Services Department directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Boston?
Under Massachusetts law (780 CMR R105.3; 780 CMR 110.R5.1.3.1 (10th ed.); M.G.L. c. 142, s. 3; M.G.L. c. 141, s. 1A): Yes for the building permit itself: 780 CMR R105.3 says 'the owner or authorized agent shall file a permit application.' The construction supervisor license (CSL) rules contain an explicit homeowner exemption at 780 CMR 110.R5.1.3.1: 'Any homeowner performing work for which a building permit is required shall be exempt from the licensing provisions of 780 CMR 110.R5, provided that if a homeowner engages a person(s) for hire to do such work, then such homeowner shall act as supervisor.' 'Homeowner' is defined as a person who owns a parcel on which he or she resides or intends to reside with a one- or two-family dwelling; a person who constructs more than one home in a two-year period does not qualify. The exemption does not extend to the trades: plumbing and gas work requires licensure under M.G.L. c. 142, s. 3, which contains no homeowner exemption, and the electrician licensing exemptions in M.G.L. c. 141, s. 1A likewise do not include homeowners. Confirm how Boston applies this before you apply.

From the Library

What else needs a permit in Boston

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsNot specifiedNon-structural bathroom work uses the Short-Form building permit at $20 primary plus $10...
Deck PermitIt dependsdetached decks not more than 30 inches above grade and under 200 sq ft that do not serve an exit door may be exemptBilled as building work: Short-Form at $20 primary plus $10 per $1,000 of estimated cost...
Electrical PermitPermit requiredNot specified$20 application fee plus $0.25 per amp for service upgrades or $1 per fixture for other...
EV Charger PermitPermit requiredNot specifiedAn Electrical Permit is required per Boston's EVSE installation guide, billed under the...
Fence PermitIt dependspermit required for fences over 6 feet in height per Massachusetts 780 CMRNot published
HVAC PermitPermit requiredNot specifiedNo single HVAC line
Plumbing PermitPermit requiredNot specified$20 application fee plus $5 per fixture such as toilets and sinks
Pool PermitPermit requiredNot specifiedPools need a Use of Premises Permit at a $50 primary fee per the ISD fee schedule...
Roof Replacement PermitPermit requiredNot specifiedRoof replacement with no structural change uses the Short-Form building permit at $20...
Solar PermitPermit requiredNot specifiedSystems under 20 kWh on 1-2 family homes qualify for Short-Form at $20 primary plus $10...
Water Heater PermitPermit requiredNot specifiedWater heater or boiler swaps with no other work use a Plumbing Permit at $20 primary...

Shed Permit in other Massachusetts localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Boston documents; the office above sets the local rules.

How this shed permit page for Boston was verified. 1 official source: boston.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Inspectional Services Department. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page