EV Charger Permit in Albuquerque, New Mexico
Permit required
Yes, a permit is required
Before installing a hardwired charger or a new circuit or receptacle for one.
Issued byCity of Albuquerque Planning Department, Building Safety Division
By Mario Bailey, verified against official sources
Quick answer
Albuquerque publishes nothing EV-specific; installing a charger is installation of equipment or wiring, which needs a City electrical permit. A homeowner must pass the City's electrical exam to pull it; otherwise a licensed electrical contractor applies.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
A licensed electrician typically pulls the electrical permit as part of the install. If you have not picked one yet, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before installing a hardwired charger or a new circuit or receptacle for one.
What an EV charger permit costs in Albuquerque
How to apply in Albuquerque
In Albuquerque, in most of the US, installing a Level 2 (240 volt) home EV charger is handled as an electrical permit built around a load calculation and a single line diagram showing the new dedicated circuit. A Level 1 charger that simply plugs into an existing 120 volt outlet typically needs no permit unless new wiring is added.
What most EV charger permit applications include:
- For Albuquerque, a Level 2 charger needs its own dedicated 240 volt circuit and requires an electrical permit with inspection, since each outlet installed for EV charging must be fed by an individual branch circuit with no other outlets on it (NEC 625.40).
- For Albuquerque, the application includes an electrical load calculation showing the existing service panel has enough spare capacity for the added EVSE demand, worked out using the standard dwelling load calculation method (NEC 220.83).
- For Albuquerque, the breaker or other overcurrent device feeding the charger must be sized for continuous duty, rated at not less than 125 percent of the equipment's maximum load (NEC 625.41).
- Plan submittal typically includes a single line diagram showing conductor size, breaker size, conduit, and panel rating, plus the charger's manufacturer specifications, since the EVSE itself must be a listed product (NEC 625.5).
- For charging equipment rated over 60 amps or over 150 volts to ground, the application has to show a disconnecting means installed in a readily accessible location and capable of being locked open (NEC 625.43).
- For Albuquerque, the charger must be shown connected and fastened in place according to the manufacturer's installation instructions, whether it is hardwired or a plug in unit on a dedicated receptacle (NEC 625.44).
General submittal guidance from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System and Article 220 Load Calculations, 2017 to 2023 editions. Source. City of Albuquerque Planning Department, Building Safety Division sets the exact checklist for Albuquerque.
Where to apply in Albuquerque:
City of Albuquerque Planning Department, Building Safety Division
- Plaza del Sol Building, 600 Second NW, Albuquerque, NM 87102
- Phone: (505) 924-3320
- Email: planningdepartment@cabq.gov
EV Charger Permit in Albuquerque compared with nearby New Mexico localities
| Locality | Permit needed? | Threshold | What each New Mexico schedule says | Verified |
|---|---|---|---|---|
| Albuquerque | Permit required | Any size | Electrical permit under "TABLE 112-B ELECTRICAL PERMIT FEES": $47.00 administrative... | |
| Bernalillo County | It depends | Before installing a hardwired charger or a new 240-volt circuit or receptacle for an... | Resolution 25-2009 Table 3-B: administrative charge $23.50 each |
Inspections and closing out your permit
In Albuquerque, a Level 2 EV charger installation gets a rough wiring inspection if any new conductors will be hidden inside walls, ceilings, or run underground, then a final inspection that checks the dedicated circuit, breaker sizing, any required GFCI protection, the disconnect, and the charger's listing before the permit closes.
- In Albuquerque: if new EVSE conductors will be concealed in a wall or ceiling, or run underground, they must pass a rough wiring inspection before being covered, since that inspection confirms the dedicated branch circuit required for the charger (NEC 625.40).
- In Albuquerque: at final inspection, the breaker or other overcurrent device serving the charger is checked to confirm it is properly rated for the continuous EV charging load (NEC 625.41).
- In Albuquerque: any receptacle installed for EV charging, as opposed to a hardwired connection, has to be checked for ground fault circuit interrupter protection (NEC 625.54).
- In Albuquerque: where the EVSE is rated over 60 amps or 150 volts to ground, the inspector confirms a lockable, readily accessible disconnecting means was installed (NEC 625.43).
- In Albuquerque: the inspector verifies the charger, along with its fittings and associated equipment, carries a nationally recognized testing laboratory listing (NEC 625.5).
- In Albuquerque: mounting height is checked against the manufacturer's instructions, with the coupling means generally required to sit at least 18 inches above an indoor floor or 24 inches above outdoor grade unless the equipment is listed otherwise (NEC 625.50).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Albuquerque permit portal or by phone at (505) 924-3320.
Inspection sequence from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System, 2017 to 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your EV Charger Permit checklist for Albuquerque
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing a hardwired charger or a new circuit or receptacle for one.
- Budget the fee. Electrical permit under "TABLE 112-B ELECTRICAL PERMIT FEES": $47.00 administrative charge plus line items (the schedule has no EV-specific line); plan review is 25 percent of the total trade permit fee. City of Albuquerque 2024 Uniform Administrative Code (UAC), Section 112 and Tables 112-A through 112-G, cover date effective January 1, 2025. Official fee schedule.
- Apply. In Albuquerque, in most of the US, installing a Level 2 (240 volt) home EV charger is handled as an electrical permit built around a load calculation and a single line diagram showing the new dedicated circuit. A Level 1 charger that simply plugs into an existing 120 volt outlet typically needs no permit unless new wiring is added. Start at the Albuquerque permit portal.
- Keep the office details handy. City of Albuquerque Planning Department, Building Safety Division. Phone: (505) 924-3320. Address: Plaza del Sol Building, 600 Second NW, Albuquerque, NM 87102.
- Plan for inspections. In Albuquerque, a Level 2 EV charger installation gets a rough wiring inspection if any new conductors will be hidden inside walls, ceilings, or run underground, then a final inspection that checks the dedicated circuit, breaker sizing, any required GFCI protection, the disconnect, and the charger's listing before the permit closes.
Compiled from the official sources on this page. Last checked .
Permitting activity in Albuquerque
In 2025, Albuquerque authorized permits for 1,417 new residential housing units (525 single-family, 892 in multi-family buildings), valued at $219M, up from 1,099 the year before. That works out to about 2.5 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 562,540.
Frequently asked questions
- Do you need an EV charger permit in Albuquerque?
- Albuquerque publishes nothing EV-specific; installing a charger is installation of equipment or wiring, which needs a City electrical permit. A homeowner must pass the City's electrical exam to pull it; otherwise a licensed electrical contractor applies. Always confirm with the City of Albuquerque Planning Department, Building Safety Division before starting.
- How much does an EV charger permit cost in Albuquerque?
- Electrical permit under "TABLE 112-B ELECTRICAL PERMIT FEES": $47.00 administrative charge plus line items (the schedule has no EV-specific line); plan review is 25 percent of the total trade permit fee. City of Albuquerque 2024 Uniform Administrative Code (UAC), Section 112 and Tables 112-A through 112-G, cover date effective January 1, 2025. See the official fee schedule for current amounts.
- How long does an EV charger permit take in Albuquerque?
- In Albuquerque, an EV charger permit typically takes 1 day for electrical permits (Building Safety dashboard, last updated October 20, 2026). Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for an EV charger permit in Albuquerque?
- You can apply through the Albuquerque permit portal or contact the City of Albuquerque Planning Department, Building Safety Division directly. The links are listed on this page.
- Can a homeowner pull an EV charger permit themselves in Albuquerque?
- Under New Mexico law (NMSA 1978, 60-13-3(D)(10), (11); 14.5.2.8(B) NMAC; 14.5.2.18 NMAC): Yes, with tight limits. CILA exempts from the contractor definition an individual who, alone or with wage-paid help, builds or makes installations, alterations or repairs to a single-family dwelling he owns and occupies or will occupy (60-13-3(D)(10)), and a person building or improving a single-family residence for personal use (60-13-3(D)(11)). The work must still meet all state codes, and CID's homeowner permit (14.5.2.18 NMAC) applies only to the owner's primary residence and its garages, carports and sheds, never to rental, other owned or commercial property. The homeowner must perform the major portion of the work by dollar amount and file a signed, notarized responsibility sheet. A homeowner electrical permit requires passing a CID homeowner electrical exam (75% to pass), a plumbing permit requires a competency showing that may include a written exam, and no homeowner permit is issued for HVAC, natural gas or LP gas work. The project may not be put on the market while under construction (doing so voids the permit and can bring unlicensed contracting charges), and only one single-family homeowner permit may be issued to the same owner in any 12-month period. Confirm how Albuquerque applies this before you apply.
From the Library
What else needs a permit in Albuquerque
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Finish work and same-configuration fixture swaps are exempt; altered piping, new wiring or structural changes need permits | Building permit (if structural or layout work) by valuation under "TABLE 112-A BUILDING... |
| Deck Permit | It depends | Platforms not over a story or basement below and not part of an accessible route | ...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to... |
| Electrical Permit | It depends | Like-for-like repair or replacement of receptacles, switch parts and fixed listed appliances is exempt; new or altered wiring, devices and equipment needs a permit | ...charge applicable to all applications and additions to permits" $47.00... |
| Fence Permit | Permit required | Any size | ...Construction Cost Guide Per Lineal Foot" (for example "Wood Fence (Cedar)" $23.30... |
| HVAC Permit | Permit required | Any size | ...charge applicable to all applications and additions to permit" $47.00... |
| Patio Permit | It depends | Covered versus uncovered: a patio cover or porch needs a building permit; an uncovered at-grade slab falls under the exemption for platforms and walks | ...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to... |
| Plumbing Permit | It depends | Stopping leaks, clearing stoppages and replacing fixtures with the same type of configuration are exempt; new or altered piping needs a permit | ...charge applicable to all applications and additions to permit" $47.00... |
| Pool Permit | It depends | Prefabricated pools installed entirely above ground, not exceeding 5,000 gallons, accessory to a building under the International Residential Code | ...FEES" with the (.50) residential modifier, plus "Swimming pool (Private)" $60.00... |
| Roof Replacement Permit | Permit required | Any size | ...PERMIT FEES", "Residential (R-3 Occupancies Only)": Administrative Fee $30.00 +... |
| Shed Permit | It depends | Building area of a one-story detached accessory building used as a tool or storage shed, playhouse or similar use | ...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to... |
| Solar Permit | Permit required | Any size | ...the (.50) residential modifier, plus an electrical permit under Table 112-B ($47.00... |
| Water Heater Permit | Permit required | Any size | Plumbing/mechanical permit with the $47.00 administrative charge (Tables 112-C and 112-D) |
EV Charger Permit in other New Mexico localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Albuquerque documents; the office above sets the local rules.
How this EV charger permit page for Albuquerque was verified. 1 official source: cabq.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Albuquerque Planning Department, Building Safety Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare EV Charger Permit requirements across New Mexico localities