New Mexico / Bernalillo County
EV Charger Permit in Bernalillo County, New Mexico
It depends
Sometimes, depending on the project
Before installing a hardwired charger or a new 240-volt circuit or receptacle for an electric vehicle.
Quick answer
Bernalillo County publishes no EV charger rule, so the electrical permit rule decides it. Its ordinance exempts only portable equipment energized by a cord with an attachment plug connected to an approved receptacle, and reinstalling plug receptacles but not the outlets for them. Plugging a portable charger into an existing receptacle needs no permit; a new circuit, a new 240-volt receptacle or a hardwired charger needs a county electrical permit.
- Issued by
- Bernalillo County Planning & Development Services, Building Section
- Phone
- (505) 314-0350
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
A licensed electrician typically pulls the electrical permit as part of the install. If you have not picked one yet, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
What an EV charger permit costs in Bernalillo County
- Fee schedule in force
- Official scheduleRead .
- No EV charger line item.
- Resolution 25-2009 Table 3-B: administrative charge $23.50 each;
- "Outlet: 30 amp or over including panels" $4.00 each;
- "Residential Fixed Appliances (30 amps or over)" $4.00 each.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in Bernalillo County
General guide, not specific to this office
What an EV charger permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an EV charger permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Bernalillo County Planning & Development Services, Building Section
- 415 Silver Ave. SW, 2nd Floor, Albuquerque, NM 87102
- Phone: (505) 314-0350
- Email: permits@bernco.gov
EV Charger Permit in Bernalillo County compared with nearby New Mexico localities
| Locality | Permit needed? | Threshold | What each New Mexico schedule says | Verified |
|---|---|---|---|---|
| Bernalillo County | It depends | Before installing a hardwired charger or a new 240-volt circuit or receptacle for an... | See schedule | |
| Albuquerque | Permit required | Any size | Electrical permit under "TABLE 112-B ELECTRICAL PERMIT FEES": $47.00 administrative charge plus line items (the schedule has no EV-specific line) |
Your EV Charger Permit checklist for Bernalillo County
- Confirm the requirement. Sometimes, depending on the project. Read the rule where we read it: bernco.gov: building services.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Bernalillo County permit portal.
- Keep the office details handy. Bernalillo County Planning & Development Services, Building Section. Phone: (505) 314-0350. Email: permits@bernco.gov. Address: 415 Silver Ave. SW, 2nd Floor, Albuquerque, NM 87102.
Compiled from the official sources on this page. Last checked .
Permitting activity in Bernalillo County
In 2025, Bernalillo County authorized permits for 1,560 new residential housing units (668 single-family, 892 in multi-family buildings), valued at $314M, up from 1,316 the year before. That works out to about 2.3 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 667,601.
What else needs a permit in Bernalillo County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before moving or adding plumbing fixtures, adding circuits, or making structural changes | See schedule |
| Deck Permit | It depends | height of a platform above grade; also not over a basement or story below and not part of an accessible route | Building permit fees are valuation-based under Administrative Resolution 25-2009 (effective May 1, 2009); the schedule has the rest |
| Electrical Permit | It depends | Before adding or altering wiring, circuits, outlets, panels or services | See schedule |
| Fence Permit | It depends | height of a fence or freestanding masonry wall above grade, measured on the lowest side; open-style fences such as chain-link any height as determined by the building official | See schedule |
| HVAC Permit | It depends | Before installing or replacing a furnace, air conditioner, heat pump, boiler... | See schedule |
| Patio Permit | Permit required | Any size | Building permit fees are valuation-based under Administrative Resolution 25-2009 (effective May 1, 2009); the schedule has the rest |
| Plumbing Permit | It depends | Before installing, altering or relocating plumbing or gas piping, fixtures, sewer or... | See schedule |
| Pool Permit | It depends | prefabricated pool accessory to a Group R-3 dwelling, installed entirely above ground, capacity not over 5,000 gallons | Building permit fees are valuation-based under Administrative Resolution 25-2009 (effective May 1, 2009); the schedule has the rest |
| Roof Replacement Permit | Permit required | Any size | Building permit fees are valuation-based under Administrative Resolution 25-2009 (effective May 1, 2009); the schedule has the rest |
| Shed Permit | It depends | one-story detached accessory building used as a tool or storage shed, playhouse or similar use | Building permit fees are valuation-based under Administrative Resolution 25-2009 (effective May 1, 2009); the schedule has the rest |
| Solar Permit | Permit required | Any size | See schedule |
| Water Heater Permit | Permit required | Any size | Plumbing (Table 3-D) and mechanical (Table 3-C) each carry a $23.50 administrative charge |
Frequently asked questions
- Do you need an EV charger permit in Bernalillo County?
- Sometimes: before installing a hardwired charger or a new 240-volt circuit or receptacle for an electric vehicle. If you are unsure how that applies to your project, call the Bernalillo County Planning & Development Services, Building Section at (505) 314-0350 before you start.
- How much does an EV charger permit cost in Bernalillo County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 23 Oct 2026. For the figure on your own project, call the Bernalillo County Planning & Development Services, Building Section at (505) 314-0350.
- How long does an EV charger permit take in Bernalillo County?
- The county says it will make every effort to process trade permit submittals received by 3:00 p.m. on the same day (Apply for Trade Permits page). Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for an EV charger permit in Bernalillo County?
- You can apply through the Bernalillo County permit portal or contact the Bernalillo County Planning & Development Services, Building Section directly. The links are listed on this page.
- Can a homeowner pull an EV charger permit themselves in Bernalillo County?
- Under New Mexico law (NMSA 1978, 60-13-3(D)(10), (11); 14.5.2.8(B) NMAC; 14.5.2.18 NMAC): Yes, with tight limits. CILA exempts from the contractor definition an individual who, alone or with wage-paid help, builds or makes installations, alterations or repairs to a single-family dwelling he owns and occupies or will occupy (60-13-3(D)(10)), and a person building or improving a single-family residence for personal use (60-13-3(D)(11)). The work must still meet all state codes, and CID's homeowner permit (14.5.2.18 NMAC) applies only to the owner's primary residence and its garages, carports and sheds, never to rental, other owned or commercial property. The homeowner must perform the major portion of the work by dollar amount and file a signed, notarized responsibility sheet. A homeowner electrical permit requires passing a CID homeowner electrical exam (75% to pass), a plumbing permit requires a competency showing that may include a written exam, and no homeowner permit is issued for HVAC, natural gas or LP gas work. The project may not be put on the market while under construction (doing so voids the permit and can bring unlicensed contracting charges), and only one single-family homeowner permit may be issued to the same owner in any 12-month period. Confirm how Bernalillo County applies this before you apply.
From the Library
EV Charger Permit in other New Mexico localities
Everything above, sourced
How this EV charger permit page for Bernalillo County was verified. 2 official sources: bernco.gov, bernco.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Bernalillo County Planning & Development Services, Building Section. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page