New Mexico / Bernalillo County

Electrical Permit in Bernalillo County, New Mexico

It depends

Sometimes, depending on the project

Before adding or altering wiring, circuits, outlets, panels or services.

Confirmed on official page Verified

Issued byBernalillo County Planning & Development Services, Building Section

By Mario Bailey, verified against official sources

Quick answer

Bernalillo County, not the state, issues residential electrical permits (Accela type ELRE) in the unincorporated area; licensed contractors apply online through Accela Citizen Access, and homeowners may pull an electrical permit for their own home after passing the county's $25 homeowner electrical exam. The ordinance exempts like-for-like repair or replacement of fixed appliances, motors, switch parts and overcurrent devices in the same location, cord-and-plug portable equipment, temporary decorative lighting and removal of wiring. New circuits, outlets, services and panels need a permit.

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before adding or altering wiring, circuits, outlets, panels or services.

What an electrical permit costs in Bernalillo County

Line item
electrical permitBy formulaResolution 25-2009 Table 3-B Electrical Permit Fees: administrative charge $23.50 each; meter loop $20.00 each; outlets first 20 $0.75 each, all over 20 $0.45 each; "Outlet: 30 amp or over including panels" $4.00 each; "Residential Fixed Appliances (30 amps or over)" $4.00 each; prefinal $20.00 each.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Bernalillo County

In Bernalillo County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • For Bernalillo County, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • For Bernalillo County, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Bernalillo County Planning & Development Services, Building Section sets the exact checklist for Bernalillo County.

Where to apply in Bernalillo County:

Bernalillo County Planning & Development Services, Building Section

  • 415 Silver Ave. SW, 2nd Floor, Albuquerque, NM 87102
  • Phone: (505) 314-0350
  • Email: permits@bernco.gov

Electrical Permit in Bernalillo County compared with nearby New Mexico localities

LocalityPermit needed?ThresholdWhat each New Mexico schedule saysVerified
Bernalillo CountyIt dependsBefore adding or altering wiring, circuits, outlets, panels or servicesResolution 25-2009 Table 3-B Electrical Permit Fees: administrative charge $23.50 each
AlbuquerqueIt dependsLike-for-like repair or replacement of receptacles, switch parts and fixed listed appliances is exempt; new or altered wiring, devices and equipment needs a permit...charge applicable to all applications and additions to permits" $47.00...

Inspections and closing out your permit

In Bernalillo County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. In Bernalillo County: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. In Bernalillo County: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. In Bernalillo County: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. In Bernalillo County: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. In Bernalillo County: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. In Bernalillo County: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. In Bernalillo County: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Bernalillo County permit portal or by phone at (505) 314-0350.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Bernalillo County

In 2025, Bernalillo County authorized permits for 1,560 new residential housing units (668 single-family, 892 in multi-family buildings), valued at $314M, up from 1,316 the year before. That works out to about 2.3 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 667,601.

Frequently asked questions

Do you need an electrical permit in Bernalillo County?
Bernalillo County, not the state, issues residential electrical permits (Accela type ELRE) in the unincorporated area; licensed contractors apply online through Accela Citizen Access, and homeowners may pull an electrical permit for their own home after passing the county's $25 homeowner electrical exam. The ordinance exempts like-for-like repair or replacement of fixed appliances, motors, switch parts and overcurrent devices in the same location, cord-and-plug portable equipment, temporary decorative lighting and removal of wiring. New circuits, outlets, services and panels need a permit. Always confirm with the Bernalillo County Planning & Development Services, Building Section before starting.
How much does an electrical permit cost in Bernalillo County?
Resolution 25-2009 Table 3-B Electrical Permit Fees: administrative charge $23.50 each; meter loop $20.00 each; outlets first 20 $0.75 each, all over 20 $0.45 each; "Outlet: 30 amp or over including panels" $4.00 each; "Residential Fixed Appliances (30 amps or over)" $4.00 each; prefinal $20.00 each. See the official fee schedule for current amounts.
How long does an electrical permit take in Bernalillo County?
The county says it will make every effort to process trade permit submittals received by 3:00 p.m. on the same day (Apply for Trade Permits page). Times can vary by workload and project scope, so confirm with the office.
Where do you apply for an electrical permit in Bernalillo County?
You can apply through the Bernalillo County permit portal or contact the Bernalillo County Planning & Development Services, Building Section directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Bernalillo County?
Under New Mexico law (NMSA 1978, 60-13-3(D)(10), (11); 14.5.2.8(B) NMAC; 14.5.2.18 NMAC): Yes, with tight limits. CILA exempts from the contractor definition an individual who, alone or with wage-paid help, builds or makes installations, alterations or repairs to a single-family dwelling he owns and occupies or will occupy (60-13-3(D)(10)), and a person building or improving a single-family residence for personal use (60-13-3(D)(11)). The work must still meet all state codes, and CID's homeowner permit (14.5.2.18 NMAC) applies only to the owner's primary residence and its garages, carports and sheds, never to rental, other owned or commercial property. The homeowner must perform the major portion of the work by dollar amount and file a signed, notarized responsibility sheet. A homeowner electrical permit requires passing a CID homeowner electrical exam (75% to pass), a plumbing permit requires a competency showing that may include a written exam, and no homeowner permit is issued for HVAC, natural gas or LP gas work. The project may not be put on the market while under construction (doing so voids the permit and can bring unlicensed contracting charges), and only one single-family homeowner permit may be issued to the same owner in any 12-month period. Confirm how Bernalillo County applies this before you apply.

From the Library

What else needs a permit in Bernalillo County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsBefore moving or adding plumbing fixtures, adding circuits, or making structural changesBuilding work is valuation-based under Resolution 25-2009 Table 3-A ("$30.00 plus $4.00...
Deck PermitIt dependsheight of a platform above grade; also not over a basement or story below and not part of an accessible route...under Administrative Resolution 25-2009 (effective May 1, 2009), Table 3-A: "$30.00...
EV Charger PermitIt dependsBefore installing a hardwired charger or a new 240-volt circuit or receptacle for an...Resolution 25-2009 Table 3-B: administrative charge $23.50 each
Fence PermitIt dependsheight of a fence or freestanding masonry wall above grade, measured on the lowest side; open-style fences such as chain-link any height as determined by the building official...footage of the wall." Otherwise building permits are valuation-based: "$30.00 plus...
HVAC PermitIt dependsBefore installing or replacing a furnace, air conditioner, heat pump, boiler...Resolution 25-2009 Table 3-C Mechanical Permit Fees: administrative charge $23.50 each
Patio PermitPermit requiredAny size...under Administrative Resolution 25-2009 (effective May 1, 2009), Table 3-A: "$30.00...
Plumbing PermitIt dependsBefore installing, altering or relocating plumbing or gas piping, fixtures, sewer or...Resolution 25-2009 Table 3-D Plumbing Permit Fees: administrative charge $23.50 each
Pool PermitIt dependsprefabricated pool accessory to a Group R-3 dwelling, installed entirely above ground, capacity not over 5,000 gallons...under Administrative Resolution 25-2009 (effective May 1, 2009), Table 3-A: "$30.00...
Roof Replacement PermitPermit requiredAny size...under Administrative Resolution 25-2009 (effective May 1, 2009), Table 3-A: "$30.00...
Shed PermitIt dependsone-story detached accessory building used as a tool or storage shed, playhouse or similar use...under Administrative Resolution 25-2009 (effective May 1, 2009), Table 3-A: "$30.00...
Solar PermitPermit requiredAny size...building permit (BRSP), valuation-based under Resolution 25-2009 Table 3-A ("$30.00...
Water Heater PermitPermit requiredAny sizePlumbing (Table 3-D) and mechanical (Table 3-C) each carry a $23.50 administrative charge

Electrical Permit in other New Mexico localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Bernalillo County documents; the office above sets the local rules.

How this electrical permit page for Bernalillo County was verified. 2 official sources: bernco.gov, bernco.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Bernalillo County Planning & Development Services, Building Section. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across New Mexico localities

Electrical permit rules nationwide

Look up an existing Bernalillo County permit record

It depends
Get quotes