Bathroom Remodel Permit in Albuquerque, New Mexico
It depends
Sometimes, depending on the project
Before moving or adding plumbing, adding circuits or outlets, or altering walls or layout.
Issued byCity of Albuquerque Planning Department, Building Safety Division
By Mario Bailey, verified against official sources
Quick answer
Painting, papering, tiling, cabinets, counter tops and similar finish work need no building permit, and replacing fixtures with the same type of configuration needs no plumbing permit. Installing or altering bathroom piping needs a plumbing/mechanical permit, new wiring or devices need an electrical permit, and changing the layout or structure needs a building permit; small jobs may qualify for a "Minor Alteration and Repair" permit.
Typical threshold: Finish work and same-configuration fixture swaps are exempt; altered piping, new wiring or structural changes need permits.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Remodel contractors usually handle the permits as part of the job. Comparing a few bids before you commit is the useful next step.
Compare bathroom remodel quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before moving or adding plumbing, adding circuits or outlets, or altering walls or layout.
What a bathroom remodel permit costs in Albuquerque
How to apply in Albuquerque
In Albuquerque, a bathroom remodel that creates a new bathroom or touches its plumbing, wiring, or walls needs a building permit application, typically filed as separate building, electrical, mechanical, and plumbing permits submitted together and backed by a floor plan showing the fixture layout. A simple like-for-like fixture swap with no other work is often exempt.
What most bathroom remodel permit applications include:
- Creating a new bathroom or toilet room, or altering, moving, or replacing a plumbing, electrical, gas, or mechanical system as part of the remodel, is regulated work that requires a permit before work starts, usually filed as separate building, electrical, mechanical, and plumbing permit applications submitted together (IRC R105.1).
- For Albuquerque, the permit application itself must identify and describe the work, describe the site, state the intended use, be accompanied by construction documents, state the valuation of the work, and be signed by the applicant or their agent (IRC R105.3).
- Those construction documents have to show the location, nature, and extent of the proposed work, which in practice means a scaled existing and proposed floor plan showing every fixture, outlet, switch, and vent fan, including the code-mandated clearances around fixtures such as the water closet (IRC R106.1.1; R307.1 fixture clearances).
- For Albuquerque, a bathroom needs ventilation: mechanical exhaust ducted to the outside where the required openable window is absent, sized in the range of 50 cubic feet per minute intermittent (IRC R303.3; M1505).
- New or relocated bathroom receptacles must be ground-fault circuit-interrupter protected (IRC E3902.1 / NEC 210.8(A)(1)).
- Tub and shower walls have to be finished with a nonabsorbent, waterproof surface extending to a minimum height above the floor (IRC R307.2).
- Routine maintenance items such as towel bars, mirrors, paint, or floor coverings done alone are commonly permit-exempt, but that exemption ends once the work relocates fixtures or opens up wiring, piping, or walls, so a like-for-like fixture swap should be checked against the local exemption list rather than assumed (IRC R105.2).
General submittal guidance from International Residential Code (IRC), 2021 edition, Sections R105, R106, R303.3, R307, and E3902. Source. City of Albuquerque Planning Department, Building Safety Division sets the exact checklist for Albuquerque.
Where to apply in Albuquerque:
City of Albuquerque Planning Department, Building Safety Division
- Plaza del Sol Building, 600 Second NW, Albuquerque, NM 87102
- Phone: (505) 924-3320
- Email: planningdepartment@cabq.gov
Bathroom Remodel Permit in Albuquerque compared with nearby New Mexico localities
| Locality | Permit needed? | Threshold | What each New Mexico schedule says | Verified |
|---|---|---|---|---|
| Albuquerque | It depends | Finish work and same-configuration fixture swaps are exempt; altered piping, new wiring or structural changes need permits | Building permit (if structural or layout work) by valuation under "TABLE 112-A BUILDING... | |
| Bernalillo County | It depends | Before moving or adding plumbing fixtures, adding circuits, or making structural changes | Building work is valuation-based under Resolution 25-2009 Table 3-A ("$30.00 plus $4.00... |
Inspections and closing out your permit
In Albuquerque, once the permit is issued, the work stays subject to inspection at each stage, and the plumbing, mechanical, and electrical rough-in must be inspected and approved before the walls are closed up. A final inspection, made after everything required by the permit is done, closes out the job.
- In Albuquerque: any construction or work covered by the permit stays subject to inspection and must remain accessible and exposed until the building official approves it (IRC R109.1).
- In Albuquerque: the plumbing, mechanical, and electrical rough-in has to be inspected and approved before it is covered or concealed, before fixtures or appliances are installed, and before the framing inspection, so the trade work behind the walls is signed off before drywall closes them up (IRC R109.1.2, R109.1.4).
- In Albuquerque: work cannot proceed past the point covered by the last approved inspection without the building official's sign-off (IRC R109.4).
- Scheduling is on the permit holder in Albuquerque: it is their duty to notify the building official when work is ready and to provide access for each inspection (IRC R109.3).
- In Albuquerque: a final inspection, covering everything required by the permit including items such as GFCI protection, closes out the job once all the permitted work is complete (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Albuquerque permit portal or by phone at (505) 924-3320.
Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Bathroom Remodel Permit checklist for Albuquerque
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: Finish work and same-configuration fixture swaps are exempt; altered piping, new wiring or structural changes need permits. Usually needed: Before moving or adding plumbing, adding circuits or outlets, or altering walls or layout.
- Budget the fee. Building permit (if structural or layout work) by valuation under "TABLE 112-A BUILDING PERMIT FEES" with the (.50) residential modifier; plumbing fixtures "Plumbing fixture includes drain and vent" $10.00 each plus the $47.00 administrative charge (Table 112-D); electrical items under Table 112-B. City of Albuquerque 2024 Uniform Administrative Code (UAC), Section 112 and Tables 112-A through 112-G, cover date effective January 1, 2025. Official fee schedule.
- Apply. In Albuquerque, a bathroom remodel that creates a new bathroom or touches its plumbing, wiring, or walls needs a building permit application, typically filed as separate building, electrical, mechanical, and plumbing permits submitted together and backed by a floor plan showing the fixture layout. A simple like-for-like fixture swap with no other work is often exempt. Start at the Albuquerque permit portal.
- Keep the office details handy. City of Albuquerque Planning Department, Building Safety Division. Phone: (505) 924-3320. Address: Plaza del Sol Building, 600 Second NW, Albuquerque, NM 87102.
- Plan for inspections. In Albuquerque, once the permit is issued, the work stays subject to inspection at each stage, and the plumbing, mechanical, and electrical rough-in must be inspected and approved before the walls are closed up. A final inspection, made after everything required by the permit is done, closes out the job.
Compiled from the official sources on this page. Last checked .
Permitting activity in Albuquerque
In 2025, Albuquerque authorized permits for 1,417 new residential housing units (525 single-family, 892 in multi-family buildings), valued at $219M, up from 1,099 the year before. That works out to about 2.5 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 562,540.
Frequently asked questions
- Do you need a bathroom remodel permit in Albuquerque?
- Painting, papering, tiling, cabinets, counter tops and similar finish work need no building permit, and replacing fixtures with the same type of configuration needs no plumbing permit. Installing or altering bathroom piping needs a plumbing/mechanical permit, new wiring or devices need an electrical permit, and changing the layout or structure needs a building permit; small jobs may qualify for a "Minor Alteration and Repair" permit. Finish work and same-configuration fixture swaps are exempt; altered piping, new wiring or structural changes need permits. Always confirm with the office before starting.
- How much does a bathroom remodel permit cost in Albuquerque?
- Building permit (if structural or layout work) by valuation under "TABLE 112-A BUILDING PERMIT FEES" with the (.50) residential modifier; plumbing fixtures "Plumbing fixture includes drain and vent" $10.00 each plus the $47.00 administrative charge (Table 112-D); electrical items under Table 112-B. City of Albuquerque 2024 Uniform Administrative Code (UAC), Section 112 and Tables 112-A through 112-G, cover date effective January 1, 2025. See the official fee schedule for current amounts.
- Where do you apply for a bathroom remodel permit in Albuquerque?
- You can apply through the Albuquerque permit portal or contact the City of Albuquerque Planning Department, Building Safety Division directly. The links are listed on this page.
- Can a homeowner pull a bathroom remodel permit themselves in Albuquerque?
- Under New Mexico law (NMSA 1978, 60-13-3(D)(10), (11); 14.5.2.8(B) NMAC; 14.5.2.18 NMAC): Yes, with tight limits. CILA exempts from the contractor definition an individual who, alone or with wage-paid help, builds or makes installations, alterations or repairs to a single-family dwelling he owns and occupies or will occupy (60-13-3(D)(10)), and a person building or improving a single-family residence for personal use (60-13-3(D)(11)). The work must still meet all state codes, and CID's homeowner permit (14.5.2.18 NMAC) applies only to the owner's primary residence and its garages, carports and sheds, never to rental, other owned or commercial property. The homeowner must perform the major portion of the work by dollar amount and file a signed, notarized responsibility sheet. A homeowner electrical permit requires passing a CID homeowner electrical exam (75% to pass), a plumbing permit requires a competency showing that may include a written exam, and no homeowner permit is issued for HVAC, natural gas or LP gas work. The project may not be put on the market while under construction (doing so voids the permit and can bring unlicensed contracting charges), and only one single-family homeowner permit may be issued to the same owner in any 12-month period. Confirm how Albuquerque applies this before you apply.
From the Library
What else needs a permit in Albuquerque
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | Platforms not over a story or basement below and not part of an accessible route | ...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to... |
| Electrical Permit | It depends | Like-for-like repair or replacement of receptacles, switch parts and fixed listed appliances is exempt; new or altered wiring, devices and equipment needs a permit | ...charge applicable to all applications and additions to permits" $47.00... |
| EV Charger Permit | Permit required | Any size | Electrical permit under "TABLE 112-B ELECTRICAL PERMIT FEES": $47.00 administrative... |
| Fence Permit | Permit required | Any size | ...Construction Cost Guide Per Lineal Foot" (for example "Wood Fence (Cedar)" $23.30... |
| HVAC Permit | Permit required | Any size | ...charge applicable to all applications and additions to permit" $47.00... |
| Patio Permit | It depends | Covered versus uncovered: a patio cover or porch needs a building permit; an uncovered at-grade slab falls under the exemption for platforms and walks | ...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to... |
| Plumbing Permit | It depends | Stopping leaks, clearing stoppages and replacing fixtures with the same type of configuration are exempt; new or altered piping needs a permit | ...charge applicable to all applications and additions to permit" $47.00... |
| Pool Permit | It depends | Prefabricated pools installed entirely above ground, not exceeding 5,000 gallons, accessory to a building under the International Residential Code | ...FEES" with the (.50) residential modifier, plus "Swimming pool (Private)" $60.00... |
| Roof Replacement Permit | Permit required | Any size | ...PERMIT FEES", "Residential (R-3 Occupancies Only)": Administrative Fee $30.00 +... |
| Shed Permit | It depends | Building area of a one-story detached accessory building used as a tool or storage shed, playhouse or similar use | ...permit fee from "TABLE 112-A BUILDING PERMIT FEES" by total valuation ("$1.00 to... |
| Solar Permit | Permit required | Any size | ...the (.50) residential modifier, plus an electrical permit under Table 112-B ($47.00... |
| Water Heater Permit | Permit required | Any size | Plumbing/mechanical permit with the $47.00 administrative charge (Tables 112-C and 112-D) |
Bathroom Remodel Permit in other New Mexico localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Albuquerque documents; the office above sets the local rules.
How this bathroom remodel permit page for Albuquerque was verified. 2 official sources: cabq.gov, cabq.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Albuquerque Planning Department, Building Safety Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Bathroom Remodel Permit requirements across New Mexico localities