Arizona / Phoenix

Shed Permit in Phoenix, Arizona

By Mario Bailey Last checked 2026-06-18 · 2 official sources

Verified against official sources From an official source

It depends

Quick answer

Detached sheds without utilities that are 200 sq ft or smaller are exempt from a building permit in Phoenix. Any detached structure exceeding 200 sq ft, or any structure with electrical, plumbing, or mechanical connections, requires a permit. Applications are submitted through the SHAPE PHX portal.

Typical threshold: detached structures without utilities at or under 200 sq ft are exempt; structures over 200 sq ft or with utilities require a permit.

200 sq ftfootprint
Threshold illustrated: 200 sq ft. Whether Phoenix requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-06-18.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Phoenix, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

For any shed or detached accessory structure over 200 sq ft or with electrical plumbing or mechanical work

What shed permit costs in Phoenix

Shed permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026.

Official fee schedule

How Phoenix compares in Arizona

Across the Arizona jurisdictions we have verified, the same threshold runs from 120 to 200, so a project that is exempt here may still need a permit one county over.

JurisdictionPermit needed?Threshold
ChandlerIt dependsOne-story detached accessory structures (storage sheds, open-air ramadas) with floor area of 120 sq ft or less and height of 7 ft or less (up to 9 ft with 2 additional feet of setback per additional foot of height) are exempt if not connected to any electrical, gas, or water utility; exceeding either limit or connecting a utility requires a building permit.
GilbertIt dependsStructures less than 200 square feet do not require a permit; a permit is required at 200 square feet or larger, or if the shed has electrical or plumbing utilities or is connected to the house or another structure.
Maricopa CountyIt dependsstructures under 200 sq ft with no electrical plumbing or mechanical are exempt from a building permit; all others require a permit
MesaIt dependsdetached structures under 200 sq ft without utilities are exempt; structures 200 sq ft or larger or those with utilities require a permit
PeoriaIt dependsOne-story detached accessory structures used as tool and storage sheds, playhouses and similar uses are exempt from a building permit when the floor area is not greater than 200 square feet.
Phoenixthis pageIt dependsdetached structures without utilities at or under 200 sq ft are exempt; structures over 200 sq ft or with utilities require a permit
Pima CountyIt dependsOne-story detached tool and storage sheds, playhouses, and similar non-habitable accessory structures are the category Pima County's own adopted code amendments refer to as "structures exempted from permits"; the standard exemption size carried in the adopted IRC for this category is 200 sq ft with no electrical, plumbing, or mechanical connections, though Pima's own published guidance pages do not restate that figure directly.

Closest shed permit thresholds outside Arizona

Jurisdictions we cover whose limit sits nearest Phoenix's 200 sq ft.

  • Austin, Texas, one-story detached accessory structures used as tool or storage sheds with floor area no greater than 200 sq ft and no more than 15 ft in height and no plumbing and not in a floodplain are exempt
  • Bellevue, Washington, detached storage sheds playhouses or gazebos with a floor area of 200 square feet or less do not require a building permit; structures over 200 square feet require a permit
  • Clark County, Nevada, sheds over 200 sq ft require a building permit; storage sheds 200 sq ft or under may be exempt under Building Administrative Code Section 22.02.190
  • Clark County, Washington, Sheds over 200 square feet require a building permit; sheds of 200 square feet or less are exempt if they meet setbacks and easements, but any size shed in a mobile home park or multi-family zone requires a permit.

How to apply in Phoenix

A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. City of Phoenix Planning and Development Department sets the exact checklist for Phoenix.

Where to apply in Phoenix:

City of Phoenix Planning and Development Department

Inspections and closing out your permit

A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Phoenix permit portal or by phone at 602-262-7811.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Phoenix

In 2024, Phoenix authorized permits for 8,997 new residential housing units (4,062 single-family, 4,935 in multi-family buildings), valued at $1.4B, down from14,468 the year before. That works out to about 5.3 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 1,708,127.

About Phoenix

Phoenix has about 642,867 housing units. The median home is valued at $381,900, against a median household income of $77,041. About 57% of homes are owner-occupied, and the typical home was built around 1984.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a shed permit in Phoenix?
Detached sheds without utilities that are 200 sq ft or smaller are exempt from a building permit in Phoenix. Any detached structure exceeding 200 sq ft, or any structure with electrical, plumbing, or mechanical connections, requires a permit. Applications are submitted through the SHAPE PHX portal. Detached structures without utilities at or under 200 sq ft are exempt; structures over 200 sq ft or with utilities require a permit. Always confirm with the office before starting.
How much does a shed permit cost in Phoenix?
Shed permits have no dedicated fee line, they are valuation-based building permits under Table A, minimum $195 base fee for valuation up to $1,000 then a rising per-$1,000 rate per the PDD Fee Schedule effective 1/20/2026. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Phoenix?
You can apply through the Phoenix permit portal or contact the City of Phoenix Planning and Development Department directly. The links are listed on this page.

From the Library

What else needs a permit in Phoenix

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsplatforms or decks not more than 30 inches above grade do not require a permit; elevated or attached decks do require a permitDeck permits have no dedicated fee line, they are valuation-based building permits unde...
Electrical PermitPermit requiredNot specifiedElectrical permits have no dedicated fee line, they are valuation-based building permit...
Fence PermitIt dependsfences and walls over 3 feet tall require a permit; fences under 3 feet tall are exemptResidential fences carry a $98 minimum permit fee for project valuations of $1 to $1,00...
HVAC PermitPermit requiredNot specifiedHVAC (mechanical) permits have no dedicated fee line, they are valuation-based building...
Patio PermitPermit requiredNot specifiedPatio permits have no dedicated fee line, they are valuation-based building permits und...
Plumbing PermitPermit requiredNot specifiedPlumbing permits have no dedicated fee line (water heaters get the $98 minimum tier), g...
Pool PermitPermit requiredNot specifiedResidential pool and spa permits carry a minimum $234 permit fee plus a $30 aquatics pr...
Roof Replacement PermitIt dependsre-roofing with same material as original is exempt; more than two layers of asphalt shingles over existing asphalt or structural changes require a permitRoof replacement permits have no dedicated fee line, they are valuation-based building...
Solar PermitPermit requiredNot specifiedResidential solar photovoltaic permits use fixed-fee options from $780 with plan review...

Shed Permit in other Arizona localities

Official sources

Verified by a person against the sources above on 2026-06-18, not confirmed with City of Phoenix Planning and Development Department. Rules change; confirm before you build. How we verify.

Last checked: 2026-06-18Report an error on this page

Compare Shed Permit requirements across Arizona localities