Patio Permit in Peoria, Arizona

By Mario Bailey Last checked 2026-07-19 · 5 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

Handout 502 states a building permit is required for the construction, repair or enclosure of a patio cover or carport, and a footing and final inspection must pass before the work is complete. Patio covers are limited to one story not exceeding 12 feet and recreational outdoor living use. Attached patio covers qualify for over the counter plan review by appointment, and plans are submitted online at devservices.peoriaaz.gov.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Peoria, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Construction, repair or enclosure of any patio cover or carport

What patio permit costs in Peoria

Valuation-based building permit fee, minimum 87 dollars; patio covers are valued at 13 dollars per square foot and enclosed patios at 19.50 dollars per square foot in the Building Valuation Table (Development Fee Schedule Rev 9/2025).

Official fee schedule

How Peoria compares in Arizona

JurisdictionPermit needed?Threshold
ChandlerIt dependsAn open, unattached patio slab no more than 200 sq ft in area and not more than 30 inches above grade falls under the same code exemption as an unattached deck and does not require a permit; a patio cover (roofed structure) requires a permit regardless of size, per the city's Patio Covers guidance.
GilbertIt dependsOnly one-story detached non-habitable accessory structures up to 200 square feet are exempt from permit; attached patio covers and larger structures require a building permit.
Maricopa CountyIt dependsattached patio cover or patio enclosure connected to the house requires a building permit; ground-level open patio slab does not
MesaIt dependsopen ground-level patio slabs do not require a permit; covered patio structures or enclosed patio rooms require a permit
Peoriathis pagePermit requiredNot specified
PhoenixPermit requiredNot specified
Pima CountyIt dependsAn open, ground-level patio slab counts as non-structural flat work not more than 30 inches above adjacent grade and does not require a permit; enclosing a porch or patio (adding walls, screens, or a roof enclosure) requires a permit.

How to apply in Peoria

Applying for a patio permit means submitting a site plan and framing plans for a roofed patio cover, since a cover is treated as its own permitted structure regardless of size. A plain concrete or paver patio slab at or near grade is, by contrast, often exempt from that same building permit requirement.

What most patio permit applications include:

  • Filing a permit application with the local building department, which only the property owner or an authorized agent may sign, since a patio cover is treated as its own permitted structure regardless of size (IRC R105.1).
  • A scaled site plan showing the new patio cover's size and location relative to the house and other existing structures, with dimensioned distances to all property lines so required setbacks can be verified before the permit is approved (IRC R106.2).
  • Construction documents such as a framing plan and elevation, showing rafter or beam sizes and spacing, the distance between supporting posts, and the method of attachment to the house, drawn with enough clarity for the building official to confirm the work will conform to the code (IRC R106.1).
  • For the roof structure itself, plans showing compliance with the patio cover appendix's structural limits, such as adequate footing sizes for the applied post loads, since a shallow slab on grade may substitute for a deeper footing only in limited cases up to about 750 pounds of load per post (IRC Appendix AH, Section AH105.2).
  • By contrast, an at grade concrete or paver patio that is not attached to the dwelling and stays within the code's small flatwork thresholds, similar to a sidewalk, driveway, or low deck under 200 square feet and 30 inches high, commonly needs no building permit at all, so none of the plan review steps above apply (IRC R105.2).

General submittal guidance from 2021 International Residential Code (IRC), Sections R105 and R106, with Appendix AH Patio Covers (named Appendix H in the 2012, 2015, and 2018 editions). Source. Development and Engineering Department, Building Development sets the exact checklist for Peoria.

Where to apply in Peoria:

Development and Engineering Department, Building Development

Inspections and closing out your permit

A permitted patio cover follows the same footing, frame, and final inspection sequence used for any small accessory structure, since the posts and roof framing have to be checked before they are covered and again once the work is done. An at grade patio slab that qualifies as exempt flatwork usually needs no building inspection at all, because inspections only attach to work that required a permit in the first place.

  1. A footing inspection once the excavation, forms, and any reinforcing steel are in place but before concrete is poured, confirming the posts supporting a patio cover will bear on adequate footings (IRC R109.1.1).
  2. A frame inspection after the rafters, beams, posts, and any required rough in work are in place but before the roof sheathing or covering material conceals them, since a solid patio cover roof cannot be signed off once it is covered without this check (IRC R109.1.4).
  3. A final inspection once all permitted work, including roofing and post anchorage, is complete, which the code requires before the structure may be used (IRC R109.1.6).
  4. An at grade concrete or paver patio that qualifies as exempt flatwork under the permit rules is not subject to any of these inspection stages, since the inspection sequence only attaches to work that required a permit in the first place (IRC R105.2).
  5. Each inspection has to be requested by the permit holder rather than happening automatically, and the approved plans and permit card need to be on site and available when the inspector arrives (IRC R109.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Peoria permit portal or by phone at 623-773-7225.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a patio permit in Peoria?
Handout 502 states a building permit is required for the construction, repair or enclosure of a patio cover or carport, and a footing and final inspection must pass before the work is complete. Patio covers are limited to one story not exceeding 12 feet and recreational outdoor living use. Attached patio covers qualify for over the counter plan review by appointment, and plans are submitted online at devservices.peoriaaz.gov. Always confirm with the Development and Engineering Department, Building Development before starting.
How much does a patio permit cost in Peoria?
Valuation-based building permit fee, minimum 87 dollars; patio covers are valued at 13 dollars per square foot and enclosed patios at 19.50 dollars per square foot in the Building Valuation Table (Development Fee Schedule Rev 9/2025). See the official fee schedule for current amounts.
How long does a patio permit take in Peoria?
First plan review 5 business days for Addition-Alteration and Patio per posted Plan Review Timelines (business days on a Monday to Thursday 4 day work week). Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a patio permit in Peoria?
You can apply through the Peoria permit portal or contact the Development and Engineering Department, Building Development directly. The links are listed on this page.

From the Library

What else needs a permit in Peoria

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsPlatforms not more than 30 inches above adjacent grade that are not over a basement or story below and are not part of an accessible route are exempt from a permit.Valuation-based building permit fee, minimum 87 dollars;
Electrical PermitIt dependsMinor in-kind work is exempt, including replacement of receptacles, switches or control devices rated 60 amperes or less and in-kind replacement of circuit breakers rated 125 amperes or less other than a service disconnect; new or altered wiring, services and panels require a permit.Valuation-based building permit fee, minimum 87 dollars (Development Fee Schedule Rev 9...
Fence PermitIt dependsFences not over 3 feet high are exempt; fences over 3 feet and up to 7 feet require a building permit demonstrating zoning and site drainage compliance, and walls over 7 feet also require structural calculations.Fence valuation for permit fees is 1.50 dollars per linear foot under 3 feet, 4 dollars...
HVAC PermitIt dependsLike-for-like replacement by a licensed contractor of an outdoor refrigeration unit of 5 tons or less is exempt, while replacement of equipment located inside the building and any new or altered mechanical system requires a permit.Valuation-based building permit fee, minimum 87 dollars (Development Fee Schedule Rev 9...
Plumbing PermitIt dependsLeak repairs, clearing stoppages and in-kind replacement of water closets, valves or fixtures are exempt, and a like-for-like water heater replacement in a one- or two-family dwelling is exempt only when performed by a licensed contractor; relocating or replacing concealed piping, valves or fixtures requires a permit.Valuation-based building permit fee, minimum 87 dollars (Development Fee Schedule Rev 9...
Pool PermitPermit requiredPrefabricated above-ground pools accessory to a dwelling holding not more than 5,000 gallons are exempt from a pool permit, but the required barrier must still be permitted.Swimming Pool, Spa and/or Hot Tub Permit is 345 dollars and Swimming Pool Plot Plan rev...
Roof Replacement PermitIt dependsRe-roofing with the same type of material as the original roofing is exempt, provided not more than two layers of asphalt shingles are applied over an existing asphalt shingle roof; other roof replacements require a permit.Valuation-based building permit fee, minimum 87 dollars (Development Fee Schedule Rev 9...
Shed PermitIt dependsOne-story detached accessory structures used as tool and storage sheds, playhouses and similar uses are exempt from a building permit when the floor area is not greater than 200 square feet.Valuation-based building permit fee, minimum 87 dollars;
Solar PermitPermit requiredNot specifiedResidential Solar Photovoltaic Permit is 184 dollars for a 40 amp circuit or less/8K or...

Patio Permit in other Arizona localities

Official sources

Verified by a person against the sources above on 2026-07-19, not confirmed with Development and Engineering Department, Building Development. Rules change; confirm before you build. How we verify.

Last checked: 2026-07-19Report an error on this page