It depends

Sometimes, depending on the project

Before building or placing a shed or detached garage larger than 50 square feet

Confirmed on official page Verified City of Sterling Heights Office of Building (Building Division), Office of City Development

By Mario Bailey, verified against official sources

Quick answer

The Shed and Garage Packet sets the permit line at 50 square feet: a shed of 50 square feet or smaller needs no permit but still has to meet the location rules, and anything larger needs a building permit plus a concrete pad and rat wall. Setbacks apply either way: minimum 3 feet from the side property line, 6 feet from the rear property line and out of any easement, and 10 feet from the house or any other accessory structure. Height is capped at 10 feet on lots of a quarter acre or less and 15 feet on larger lots, door width at 6 feet, slab depth at a minimum of 3 1/2 inches and the rat wall at a minimum of 6 inches by 18 inches. Sheds and garages over 200 square feet also require construction drawings, and an electrical permit is required for any electrical installed in the structure.

Typical threshold: shed floor area above which a building permit is required.

Diagram of the 50 sq ft footprint area threshold for a shed permit in Sterling Heights, Michigan
Threshold illustrated: 50 sq ft. Whether Sterling Heights requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-08-15.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before building or placing a shed or detached garage larger than 50 square feet

What a shed permit costs in Sterling Heights

Line item
shed permitBy formulaBuilding Permit Application 26-27 fee chart: 'Sheds (Between 50 - 200 sq. ft)' $78.00, plus the non-refundable $56.00 application fee. Sheds and garages over 200 sq ft are permitted under the same building permit and also need an electrical permit if any electrical is installed. Re-inspection fee $75.00; re-establish expired permit $77.00.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Sterling Heights compares in Michigan

JurisdictionPermit needed?Threshold
Ann ArborPermit requiredNot specified
DetroitIt dependsfloor area of a one-story detached accessory structure in residential construction
Grand RapidsPermit requiredNot specified
Sterling Heightsthis pageIt dependsshed floor area above which a building permit is required

Closest shed permit thresholds outside Michigan

Jurisdictions we cover whose limit sits nearest Sterling Heights's 50 sq ft.

  • Polk County, Florida, Prefabricated reach-in storage structures of closet use are exempt only up to 5 ft mean height, 50 sq ft area and 250 cubic ft with no electrical or plumbing; all larger or walk-in structures require a permit.
  • St. Louis, Missouri, square feet of floor area for a detached accessory building, which must also keep the setbacks required by the Zoning Ordinance
  • Palm Beach County, Florida, Accessory storage enclosures (sheds) up to 6 ft x 6 ft x 6 ft high, for single-family dwellings only, qualify for a Type 1 Site Plan Review Permit (zoning review only, no Building Code plan review or inspection); sheds larger than that footprint or height require a standard Type 2(A) Building Permit with plan review and inspections.
  • Sarasota County, Florida, Plastic or rubber storage containers less than 7 feet tall and less than 65 square feet that meet any applicable setback requirements do not need a building permit; all other storage or utility sheds require a permit.

How to apply in Sterling Heights

A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. City of Sterling Heights Office of Building (Building Division), Office of City Development sets the exact checklist for Sterling Heights.

Where to apply in Sterling Heights:

City of Sterling Heights Office of Building (Building Division), Office of City Development

Inspections and closing out your permit

A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Sterling Heights permit portal or by phone at 586-446-2360.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a shed permit in Sterling Heights?
The Shed and Garage Packet sets the permit line at 50 square feet: a shed of 50 square feet or smaller needs no permit but still has to meet the location rules, and anything larger needs a building permit plus a concrete pad and rat wall. Setbacks apply either way: minimum 3 feet from the side property line, 6 feet from the rear property line and out of any easement, and 10 feet from the house or any other accessory structure. Height is capped at 10 feet on lots of a quarter acre or less and 15 feet on larger lots, door width at 6 feet, slab depth at a minimum of 3 1/2 inches and the rat wall at a minimum of 6 inches by 18 inches. Sheds and garages over 200 square feet also require construction drawings, and an electrical permit is required for any electrical installed in the structure. Shed floor area above which a building permit is required. Always confirm with the office before starting.
How much does a shed permit cost in Sterling Heights?
Building Permit Application 26-27 fee chart: 'Sheds (Between 50 - 200 sq. ft)' $78.00, plus the non-refundable $56.00 application fee. Sheds and garages over 200 sq ft are permitted under the same building permit and also need an electrical permit if any electrical is installed. Re-inspection fee $75.00; re-establish expired permit $77.00. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Sterling Heights?
You can apply through the Sterling Heights permit portal or contact the City of Sterling Heights Office of Building (Building Division), Office of City Development directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Sterling Heights?
Under Michigan law (MCL 339.2403(b), (c); MCL 339.2401(a)(iii), (b)(ii)(A); MCL 339.5737(3)(g); MCL 339.6107(2)(d); MCL 339.5819): Yes. A Michigan homeowner may pull the building permit and do the work on their own home without a residential builder license, because the licensing article both defines the trade to exclude them and exempts them outright. MCL 339.2401(a)(iii) says a residential builder is a person that erects a residential structure except for the person's own use and occupancy on the person's property, and MCL 339.2403(b) exempts an owner of property with reference to a structure on the property for the owner's own use and occupancy. Own use and occupancy is the condition, so the exemption does not cover building to sell, and MCL 339.2403(c) limits owners of rental property to maintenance and alteration of that property. The statute sets no cap on how many times a homeowner may use the exemption; the only frequency rule in the article catches purchase, substantial rehabilitation, and resale of the same structure more than twice in 1 calendar year, and MCL 339.2401(b)(ii)(A) exempts work for the person's own use and occupancy from even that. Homeowners can also pull their own trade permits: electrical work in a single family home and accompanying outbuildings owned and occupied or to be occupied by the person doing the work (MCL 339.5737(3)(g)), their own plumbing, building sewer, or private sewer in their single-family dwelling if a permit is secured (MCL 339.6107(2)(d)), and a heating or refrigerating system if the owner affirms in the permit application that they are or will become the owner and occupant (MCL 339.5819). Confirm how Sterling Heights applies this before you apply.

From the Library

What else needs a permit in Sterling Heights

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedBuilding Permit Application 26-27 fee chart: 'Deck/Porch' $78.00, plus the...
Electrical PermitIt dependsNot specifiedElectrical Permit Application 26-27: non-refundable application fee $55.00, then per item.
Fence PermitPermit requiredNot specifiedFence Permit Application 2026-2027 (revised 8/12/2026) fee box: WOOD $46, METAL $46...
HVAC PermitPermit requiredNot specifiedMechanical Permit Application 2026-2027: non-refundable application fee $55.00, then per...
Patio PermitIt dependsNot specifiedWhere a concrete permit is required, Building Permit Application 26-27 fee chart:...
Plumbing PermitPermit requiredNot specifiedPlumbing Permit Application 2026-2027: non-refundable application fee $55.00, then per...
Pool PermitIt dependspool or hot tub side wall height above which the permit package appliesBuilding Permit Application 26-27 fee chart: 'Swimming pool (Above Ground)' $78.00...
Roof Replacement PermitPermit requiredNot specifiedBuilding Permit Application 26-27 fee chart: 'Roof or Re-roof' $78.00, plus the...
Solar PermitPermit requiredNot specifiedBuilding Permit Application 26-27 fee chart: 'Solar Panels' $153.00, plus the...

Shed Permit in other Michigan localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Sterling Heights documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Sterling Heights Office of Building (Building Division), Office of City Development. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page