Michigan / Sterling Heights

Fence Permit in Sterling Heights, Michigan

Permit required

Yes, a permit is required

Before installing, replacing or extending a fence, including a pool barrier fence

Quick answer

A City of Sterling Heights fence permit (application prefix PF) is required for any residential fence, at any height. The Fence Permit Guidelines explain the structure: a fence under 7 feet is exempt from the permit requirement in Section 105.2 of the Michigan Building Code and Michigan Residential Code, but the city still issues its own land use fence permit, administered by the Building Department, so there is no height below which a homeowner can skip the city permit. The 7 foot line marks only where the state building-code exemption stops applying: at 7 feet and above a building permit is also required, and commercial fences at that height must comply with Section 312 of the Michigan Building Code. The application must state the fence material and height and be accompanied by a plot plan, mortgage survey, boundary survey or aerial image showing fence lengths and distances to lot lines. Residential fences may not exceed 6 feet in height without formal approval from the Board of Ordinance Appeals, and no fence may be installed in a front yard.

Issued by
City of Sterling Heights Office of Building (Building Division), Office of City Development
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Fence installers usually handle any required permit as part of the job. Compare a few bids before you commit.

Compare fence installer quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What a fence permit costs in Sterling Heights

Fee schedule in force
Official scheduleRead .
Published in
Fence Permit Application 2026-2027 (revised 8/12/2026) fee box:
  • WOOD $46, METAL $46, WIRE $46, PVC $46, MASONRY $134, SEPARATION $134.
  • Payment and a plot plan are due at the time of application.
  • No separate application fee is listed on the fence application.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Sterling Heights compares in Michigan

No Michigan jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Ann ArborPermit requiredThe Planning Services Fence Guidelines handout (revised 3/3/2025) states a flat Fence Permit Fee of $75.00
DetroitIt dependsSee schedule
Grand RapidsPermit requiredFY 2027 Planning, Design and Development Fee Schedule, Planning Fees effective July 1, 2026, ZONING PERMITS: "Level I $25.00" covering "Fence, Paving"
Sterling Heightsthis pagePermit requiredFence Permit Application 2026-2027 (revised 8/12/2026) fee box: WOOD $46, METAL $46, WIRE $46, PVC $46, MASONRY $134, SEPARATION $134

How to apply in Sterling Heights

General guide, not specific to this office

What a fence permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a fence permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

City of Sterling Heights Office of Building (Building Division), Office of City Development

Permitting activity in Sterling Heights

In 2025, Sterling Heights authorized permits for 672 new residential housing units (47 single-family, 625 in multi-family buildings), valued at $70M, up from 70 the year before. That works out to about 5.1 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 131,709.

What else needs a permit in Sterling Heights

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeBuilding Permit Application 26-27 fee chart: 'Deck/Porch' $78.00, plus the non-refundable $56.00 application fee
Electrical PermitIt dependsBefore any electrical work, including work that reuses existing wiringElectrical Permit Application 26-27: non-refundable application fee $55.00, then per item
HVAC PermitPermit requiredAny sizeMechanical Permit Application 2026-2027: non-refundable application fee $55.00, then per item
Patio PermitIt dependsBefore pouring or replacing concrete other than a flat backyard patio poured on grade...Where a concrete permit is required, Building Permit Application 26-27 fee chart: 'Concrete' $78.00, plus the non-refundable $56.00 application fee
Plumbing PermitPermit requiredAny sizePlumbing Permit Application 2026-2027: non-refundable application fee $55.00, then per fixture
Pool PermitIt dependspool or hot tub side wall height above which the permit package appliesBuilding Permit Application 26-27 fee chart: 'Swimming pool (Above Ground)' $78.00, 'Swimming pool (Below Ground)' $160.00; the schedule has the rest
Roof Replacement PermitPermit requiredAny sizeBuilding Permit Application 26-27 fee chart: 'Roof or Re-roof' $78.00, plus the non-refundable $56.00 application fee
Shed PermitIt dependsshed floor area above which a building permit is requiredBuilding Permit Application 26-27 fee chart: 'Sheds (Between 50 - 200 sq. ft)' $78.00, plus the non-refundable $56.00 application fee
Solar PermitPermit requiredAny sizeBuilding Permit Application 26-27 fee chart: 'Solar Panels' $153.00, plus the non-refundable $56.00 application fee

Frequently asked questions

Do you need a fence permit in Sterling Heights?
Yes, before installing, replacing or extending a fence, including a pool barrier fence. If you are unsure how that applies to your project, call the permit office at 586-446-2360 before you start.
How much does a fence permit cost in Sterling Heights?
The fee wording from the official schedule is in the cost table on this page, as we read it on 15 Aug 2026. For the figure on your own project, call the permit office at 586-446-2360.
Where do you apply for a fence permit in Sterling Heights?
You can apply through the Sterling Heights permit portal or contact the City of Sterling Heights Office of Building (Building Division), Office of City Development directly. The links are listed on this page.
Can a homeowner pull a fence permit themselves in Sterling Heights?
Under Michigan law (MCL 339.2403(b), (c); MCL 339.2401(a)(iii), (b)(ii)(A); MCL 339.5737(3)(g); MCL 339.6107(2)(d); MCL 339.5819): Yes. A Michigan homeowner may pull the building permit and do the work on their own home without a residential builder license, because the licensing article both defines the trade to exclude them and exempts them outright. MCL 339.2401(a)(iii) says a residential builder is a person that erects a residential structure except for the person's own use and occupancy on the person's property, and MCL 339.2403(b) exempts an owner of property with reference to a structure on the property for the owner's own use and occupancy. Own use and occupancy is the condition, so the exemption does not cover building to sell, and MCL 339.2403(c) limits owners of rental property to maintenance and alteration of that property. The statute sets no cap on how many times a homeowner may use the exemption; the only frequency rule in the article catches purchase, substantial rehabilitation, and resale of the same structure more than twice in 1 calendar year, and MCL 339.2401(b)(ii)(A) exempts work for the person's own use and occupancy from even that. Homeowners can also pull their own trade permits: electrical work in a single family home and accompanying outbuildings owned and occupied or to be occupied by the person doing the work (MCL 339.5737(3)(g)), their own plumbing, building sewer, or private sewer in their single-family dwelling if a permit is secured (MCL 339.6107(2)(d)), and a heating or refrigerating system if the owner affirms in the permit application that they are or will become the owner and occupant (MCL 339.5819). Confirm how Sterling Heights applies this before you apply.

From the Library

Fence Permit in other Michigan localities

Everything above, sourced

How this fence permit page for Sterling Heights was verified. 2 official sources: sterlingheights.gov, sterlingheights.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Sterling Heights Office of Building (Building Division), Office of City Development. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project