Maryland / Anne Arundel County
Electrical Permit in Anne Arundel County, Maryland
It depends
Sometimes, depending on the project
Before installing, altering or replacing wiring, circuits, fixtures, panels or services; like-for-like breaker swaps, receptacle reinstallation and minor repairs are exempt.
Issued byAnne Arundel County Department of Inspections and Permits, Permit Center
By Mario Bailey, verified against official sources
Quick answer
Outside Annapolis, any electrical installation, alteration or replacement needs an electrical permit, and only a county-licensed electrician (master general or restricted license) may apply. The Construction Code exempts cord-and-plug temporary decorative lighting, reinstalling receptacles (but not new outlets), replacing branch-circuit overcurrent devices of the required capacity in the same location, minor repairs such as replacing lamps or plugging approved portable equipment into existing receptacles, and testing or servicing equipment.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before installing, altering or replacing wiring, circuits, fixtures, panels or services; like-for-like breaker swaps, receptacle reinstallation and minor repairs are exempt.
What an electrical permit costs in Anne Arundel County
How Anne Arundel County compares in Maryland
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Anne Arundel Countythis page | It depends | Before installing, altering or replacing wiring, circuits, fixtures, panels or services |
| Baltimore County | It depends | Before any electrical work, including extending circuit wiring, low voltage wiring, and... |
| Howard County | Permit required | Any size |
| Montgomery County | Permit required | Any size |
| Prince George's County | Permit required | Any size |
How to apply in Anne Arundel County
In Anne Arundel County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- For Anne Arundel County, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- For Anne Arundel County, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Anne Arundel County Department of Inspections and Permits, Permit Center sets the exact checklist for Anne Arundel County.
Where to apply in Anne Arundel County:
Anne Arundel County Department of Inspections and Permits, Permit Center
- 2664 Riva Road, Heritage Office Complex, Annapolis, MD 21401
- Phone: (410) 222-7730
- Email: permitcenterhelp@aacounty.org
Electrical Permit in Anne Arundel County compared with nearby Maryland localities
| Locality | Permit needed? | Threshold | What each Maryland schedule says | Verified |
|---|---|---|---|---|
| Anne Arundel County | It depends | Before installing, altering or replacing wiring, circuits, fixtures, panels or services | ...not include service change or subpanel) | Any number of electrical devices |... | |
| Baltimore County | It depends | Before any electrical work, including extending circuit wiring, low voltage wiring, and... | ...(each meter), new, modification, upgrade, replacement or reconnection... | |
| Howard County | Permit required | Any size | $50 non-refundable permit application fee, plus $50 for 25 or fewer outlets/fixtures... | |
| Montgomery County | Permit required | Any size | $111.94 minimum fee for a residential one or two family dwelling electrical permit... | |
| Prince George's County | Permit required | Any size | ...work by item: "Electrical Permit Fee - Rough Wire Outlet, Segment of 15"... |
Inspections and closing out your permit
In Anne Arundel County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- In Anne Arundel County: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- In Anne Arundel County: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- In Anne Arundel County: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- In Anne Arundel County: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- In Anne Arundel County: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- In Anne Arundel County: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- In Anne Arundel County: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Anne Arundel County permit portal or by phone at (410) 222-7730.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Anne Arundel County
- Confirm the requirement. Sometimes, depending on the project. Usually needed: Before installing, altering or replacing wiring, circuits, fixtures, panels or services; like-for-like breaker swaps, receptacle reinstallation and minor repairs are exempt.
- Budget the fee. Electrical, "Residential additions, alterations, remodeling (does not include service change or subpanel) | Any number of electrical devices | $95.00"; with service change or subpanel up to 200 amps $147.00; "1 electrical appliance or motor | $25.00" for repair or replacement; plus a $43.00 non-refundable application fee (effective October 1, 2024). Official fee schedule.
- Apply. In Anne Arundel County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Anne Arundel County permit portal.
- Keep the office details handy. Anne Arundel County Department of Inspections and Permits, Permit Center. Phone: (410) 222-7730. Address: 2664 Riva Road, Heritage Office Complex, Annapolis, MD 21401.
- Plan for inspections. In Anne Arundel County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in Anne Arundel County?
- Outside Annapolis, any electrical installation, alteration or replacement needs an electrical permit, and only a county-licensed electrician (master general or restricted license) may apply. The Construction Code exempts cord-and-plug temporary decorative lighting, reinstalling receptacles (but not new outlets), replacing branch-circuit overcurrent devices of the required capacity in the same location, minor repairs such as replacing lamps or plugging approved portable equipment into existing receptacles, and testing or servicing equipment. Always confirm with the Anne Arundel County Department of Inspections and Permits, Permit Center before starting.
- How much does an electrical permit cost in Anne Arundel County?
- Electrical, "Residential additions, alterations, remodeling (does not include service change or subpanel) | Any number of electrical devices | $95.00"; with service change or subpanel up to 200 amps $147.00; "1 electrical appliance or motor | $25.00" for repair or replacement; plus a $43.00 non-refundable application fee (effective October 1, 2024). See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in Anne Arundel County?
- You can apply through the Anne Arundel County permit portal or contact the Anne Arundel County Department of Inspections and Permits, Permit Center directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in Anne Arundel County?
- Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Anne Arundel County applies this before you apply.
From the Library
What else needs a permit in Anne Arundel County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before moving or replacing fixtures or piping, adding circuits, or relocating or... | Trade permits as scoped: plumbing "First plumbing fixture | $51.00", "Each additional... |
| Deck Permit | It depends | detached residential deck not more than 30 inches above grade and not attached to any structure; attached decks and decks in the critical area always need a permit | Building permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |... |
| EV Charger Permit | It depends | Before installing a hardwired charger or a new circuit or receptacle for one | ...not include service change or subpanel) | Any number of electrical devices |... |
| Fence Permit | It depends | height of a fence accessory to a residential structure; any fence on waterfront property or a corner lot with intersecting streets needs a permit regardless of height | Building permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |... |
| HVAC Permit | It depends | Before installing or replacing a furnace, heat pump, central air conditioner or ductwork | Mechanical, residential: "Heating and Air Conditioning | $121.00", "Heating System |... |
| Patio Permit | It depends | patio height above adjacent grade; the exemption also requires that the patio is not over a basement or story below and is not part of an accessible route | ...a building permit is valuation-based: Building permits are valuation-based:... |
| Plumbing Permit | It depends | Before adding, relocating or replacing fixtures or piping | ...plumbing and all commercial plumbing work": "First plumbing fixture | $51.00"... |
| Pool Permit | It depends | prefabricated pools; every in-ground pool and every hot tub needs a permit | Building permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |... |
| Roof Replacement Permit | It depends | Before replacing roof sheathing together with shingles, or any trusses | Building permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |... |
| Shed Permit | It depends | one-story detached shed accessory to a residence, average height not over 10 feet; every shed in the Chesapeake Bay Critical Area and any shed within 3 feet of the house needs a permit | Building permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |... |
| Solar Permit | Permit required | Any size | ...on the estimated value of the work": Building permits are valuation-based:... |
| Water Heater Permit | Permit required | Any size | Plumbing: "First plumbing fixture | $51.00" plus a $43.00 application fee |
Electrical Permit in other Maryland localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Anne Arundel County documents; the office above sets the local rules.
How this electrical permit page for Anne Arundel County was verified. 2 official sources: aacounty.org, codelibrary.amlegal.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Anne Arundel County Department of Inspections and Permits, Permit Center. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Maryland localities