Water Heater Permit in Anne Arundel County, Maryland

Permit required

Yes, a permit is required

Before installing or replacing any water heater, gas or electric.

Confirmed on official page Verified

Issued byAnne Arundel County Department of Inspections and Permits, Permit Center

By Mario Bailey, verified against official sources

Quick answer

Outside Annapolis, replacing a water heater is a permitted plumbing job: the Construction Code requires a permit to install or replace any plumbing, gas, mechanical or electrical system, and its plumbing exemptions cover only leak repairs, stoppages and toilet reinstallation without replacing fixtures. The county's plumbing application lists water heaters with a Replace option, and a gas unit also goes on a gas permit; all are pulled by county-licensed tradespeople.

Who is pulling this permit?

Hire it out

Sponsored

Plumbers usually pull this permit as part of the replacement. If yours failed and you are choosing a plumber under time pressure, comparing a couple of quotes still pays.

Compare plumber quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before installing or replacing any water heater, gas or electric.

What a water heater permit costs in Anne Arundel County

Line item
water heater permitBy formulaPlumbing: "First plumbing fixture | $51.00" plus a $43.00 application fee; a gas water heater also needs a gas permit (minimum $69.00); electrical connection on the electrical schedule ("1 electrical appliance or motor | $25.00" for repair or replacement). Effective October 1, 2024.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Anne Arundel County compares in Maryland

JurisdictionPermit needed?Threshold
Anne Arundel Countythis pagePermit requiredAny size
Howard CountyIt dependsIt depends on the county
Montgomery CountyIt dependsIt depends on the county

How to apply in Anne Arundel County

In Anne Arundel County, replacing a residential water heater needs a permit before work starts, because swapping the appliance counts as installing regulated plumbing and fuel gas work, not an exempt repair. The application itself stays light: it identifies the work and its location, and most offices only ask for extra fuel or capacity details when the replacement changes fuel type or input size.

What most water heater permit applications include:

  • For Anne Arundel County, a permit must be obtained before an owner or contractor installs, alters, or replaces any plumbing, fuel gas, or electrical system regulated by the code, which covers putting in a new water heater (IRC R105.1).
  • Water heater replacement is not on the code's short list of exempt plumbing work, and replacing defective piping with new material is expressly defined as new work that needs a permit and inspection (IRC R105.2).
  • For Anne Arundel County, the application itself only has to identify and describe the work and describe the location of the building or work, which is why most offices can process a water heater permit as a short form rather than a full plan set (IRC R105.3).
  • Once a complete application is on file, the building official must act on it and issue the permit as soon as practicable if the proposed work conforms to code, which is the basis for the same-day or next-business-day turnaround many permit offices offer for a straight swap (IRC R105.3.1).
  • For Anne Arundel County, the permit only stays valid if the work starts within the code's default window before it lapses, so scheduling the replacement and its inspection soon after the permit issues matters (IRC R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1, Section R105 (Permits). Source. Anne Arundel County Department of Inspections and Permits, Permit Center sets the exact checklist for Anne Arundel County.

Where to apply in Anne Arundel County:

Anne Arundel County Department of Inspections and Permits, Permit Center

Water Heater Permit in Anne Arundel County compared with nearby Maryland localities

LocalityPermit needed?ThresholdWhat each Maryland schedule saysVerified
Anne Arundel CountyPermit requiredAny sizePlumbing: "First plumbing fixture | $51.00" plus a $43.00 application fee
Howard CountyIt dependsIt depends on the countyWater heater replacement bills as the $50 plumbing filing fee plus the $25...
Montgomery CountyIt dependsIt depends on the countySee schedule

Inspections and closing out your permit

In Anne Arundel County, a water heater swap normally draws one inspection, a final, since the work is exposed rather than buried behind new framing. That single visit confirms the relief valve and its discharge pipe, thermal expansion control and seismic strapping where the installation requires them, and, on gas units, adequate combustion air and an approved vent connection.

  1. In Anne Arundel County: the lifecycle has one required visit, the final inspection, made after the permitted work is complete and before the water heater goes into service; because a straight swap conceals nothing behind framing, offices typically do not schedule a separate rough-in visit for it (IRC R109.1.6).
  2. In Anne Arundel County: the inspector confirms the water heater is protected by either a separate pressure relief valve and temperature relief valve, or one combination valve rated for the appliance (IRC P2804.1).
  3. In Anne Arundel County: the relief valve's discharge pipe is checked for an unobstructed, un-trapped gravity path that ends through an air gap no more than 6 inches above the floor or pan, since a wrong discharge pipe is one of the most common reasons a water heater fails inspection (IRC P2804.6.1).
  4. In Anne Arundel County: where the water heater feeds a closed system, for instance behind a backflow preventer or check valve, the inspector looks for a thermal expansion control device sized to absorb the resulting pressure increase (IRC P2903.4.2).
  5. In Anne Arundel County: on a gas-fired unit, the inspector verifies the space provides enough combustion air, sized at 50 cubic feet per 1,000 Btu per hour of the appliance's input rating unless an engineered alternative method is used (IRC G2407.5.1).
  6. In Anne Arundel County: the gas unit's vent must tie into an approved venting system, which the inspector checks along with the vent's physical connections and support (IRC G2427.1, G2427.2).
  7. In Anne Arundel County: where site conditions call for them, the inspector also checks for a drain pan under a tank whose leakage would cause damage, and for seismic strapping in the upper and lower thirds of the tank in the seismic design categories and townhouse conditions where the code requires it (IRC P2801.6; P2801.8).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Anne Arundel County permit portal or by phone at (410) 222-7730.

Inspection sequence from 2021 International Residential Code (IRC), Chapters 24, 28, and 29 (Fuel Gas; Water Heaters; Water Supply and Distribution). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a water heater permit in Anne Arundel County?
Outside Annapolis, replacing a water heater is a permitted plumbing job: the Construction Code requires a permit to install or replace any plumbing, gas, mechanical or electrical system, and its plumbing exemptions cover only leak repairs, stoppages and toilet reinstallation without replacing fixtures. The county's plumbing application lists water heaters with a Replace option, and a gas unit also goes on a gas permit; all are pulled by county-licensed tradespeople. Always confirm with the Anne Arundel County Department of Inspections and Permits, Permit Center before starting.
How much does a water heater permit cost in Anne Arundel County?
Plumbing: "First plumbing fixture | $51.00" plus a $43.00 application fee; a gas water heater also needs a gas permit (minimum $69.00); electrical connection on the electrical schedule ("1 electrical appliance or motor | $25.00" for repair or replacement). Effective October 1, 2024. See the official fee schedule for current amounts.
Where do you apply for a water heater permit in Anne Arundel County?
You can apply through the Anne Arundel County permit portal or contact the Anne Arundel County Department of Inspections and Permits, Permit Center directly. The links are listed on this page.
Can a homeowner pull a water heater permit themselves in Anne Arundel County?
Under Maryland law (Md. Code, Bus. Occ. and Prof. 12-301(b), 6-607(1); Public Safety 12-505): It depends on the trade and the county. Plumbing: state law exempts an individual who personally provides plumbing services in their own residence, but homeowners may not make final connections between the residence and public or private water supply or disposal systems, and Baltimore County plus the WSSC-area counties are largely carved out of the state plumbing title. Electrical: the Maryland Electricians Act prohibits providing electrical services for compensation without a license; it has no express homeowner exemption, so uncompensated work on one's own home falls outside the licensing prohibition, but each county decides whether it will issue an electrical permit to an unlicensed homeowner. Building permits are issued by local jurisdictions, which set their own owner-applicant rules. Confirm how Anne Arundel County applies this before you apply.

From the Library

What else needs a permit in Anne Arundel County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsBefore moving or replacing fixtures or piping, adding circuits, or relocating or...Trade permits as scoped: plumbing "First plumbing fixture | $51.00", "Each additional...
Deck PermitIt dependsdetached residential deck not more than 30 inches above grade and not attached to any structure; attached decks and decks in the critical area always need a permitBuilding permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |...
Electrical PermitIt dependsBefore installing, altering or replacing wiring, circuits, fixtures, panels or services...not include service change or subpanel) | Any number of electrical devices |...
EV Charger PermitIt dependsBefore installing a hardwired charger or a new circuit or receptacle for one...not include service change or subpanel) | Any number of electrical devices |...
Fence PermitIt dependsheight of a fence accessory to a residential structure; any fence on waterfront property or a corner lot with intersecting streets needs a permit regardless of heightBuilding permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |...
HVAC PermitIt dependsBefore installing or replacing a furnace, heat pump, central air conditioner or ductworkMechanical, residential: "Heating and Air Conditioning | $121.00", "Heating System |...
Patio PermitIt dependspatio height above adjacent grade; the exemption also requires that the patio is not over a basement or story below and is not part of an accessible route...a building permit is valuation-based: Building permits are valuation-based:...
Plumbing PermitIt dependsBefore adding, relocating or replacing fixtures or piping...plumbing and all commercial plumbing work": "First plumbing fixture | $51.00"...
Pool PermitIt dependsprefabricated pools; every in-ground pool and every hot tub needs a permitBuilding permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |...
Roof Replacement PermitIt dependsBefore replacing roof sheathing together with shingles, or any trussesBuilding permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |...
Shed PermitIt dependsone-story detached shed accessory to a residence, average height not over 10 feet; every shed in the Chesapeake Bay Critical Area and any shed within 3 feet of the house needs a permitBuilding permits are valuation-based: "$0-$3,000 | $86.00" rising to "Above $25,000 |...
Solar PermitPermit requiredAny size...on the estimated value of the work": Building permits are valuation-based:...

Water Heater Permit in other Maryland localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Anne Arundel County documents; the office above sets the local rules.

How this water heater permit page for Anne Arundel County was verified. 2 official sources: aacounty.org, codelibrary.amlegal.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Anne Arundel County Department of Inspections and Permits, Permit Center. Rules change; confirm before you build. How we verify.