Deck Permit in Denver, Colorado
By Mario Bailey Last checked 2026-06-17 · 2 official sources
Verified against official sources Confirmed on official pageIt depends
Quick answer
Denver requires a zoning permit for uncovered decks 12 inches or more off the ground and a building permit for decks 30 inches or more above grade. All covered patios, porches, pergolas, and carports require both a zoning and building permit regardless of height. Applications are submitted through the CPD e-permits portal.
Typical threshold: uncovered decks under 12 in off the ground require no permit; 12 in or more requires a zoning permit; 30 in or more also requires a building permit.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help
Tell us where your project stands. Free to ask; no obligation.
Where we have a vetted local pro who handles permits in Denver, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
When a permit is usually needed
For any uncovered deck 12 inches or more above grade or any covered deck structure
What deck permit costs in Denver
Valuation-based building permit fee per CPD Table 1 with a $20 minimum for work valued at $500 or less, per the Development Fees schedule (ADMIN 138, rev. May 2024).
How Denver compares in Colorado
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Denverthis page | It depends | uncovered decks under 12 in off the ground require no permit; 12 in or more requires a zoning permit; 30 in or more also requires a building permit |
| Jefferson County | Permit required | No exemption by height or size: a Building Permit is required for new decks, deck expansions, replacement decks, and deck repairs. Only a ground-level concrete pad, rather than an elevated deck, avoids the permit. |
Closest deck permit thresholds outside Colorado
Jurisdictions we cover whose limit sits nearest Denver's 12 in.
- Chandler, Arizona, Decks not exceeding 200 sq ft in area, not more than 30 inches above grade at any point, not attached to a dwelling or townhouse, and not serving a required exit door are exempt from a building permit; any deck exceeding those limits or attached to the residence requires a permit.
- Dallas, Texas, decks platforms walks or driveways not more than 30 inches above grade and not over any basement or story on single-family or duplex premises are exempt
- Minneapolis, Minnesota, freestanding decks less than 30 in above grade that are not attached with frost footings and do not serve the main entrance are exempt; all other decks require a permit
- Pima County, Arizona, Decks and non-structural flat work not more than 30 inches above adjacent grade, not over any basement or story below, and not part of an accessible route do not require a permit; a deck greater than 30 inches above finished grade or floor level requires a permit.
How to apply in Denver
A residential deck permit application is a set of construction documents that show what will be built and prove it meets the IRC deck provisions. In practice that means a scaled site plan locating the deck and its setbacks, plus deck plans and structural details covering the footings, posts, beams, joists, ledger, guards, and stairs.
What most deck permit applications include:
- A permit application identifying the work, the deck's size (square footage), and whether electrical work such as lights or receptacles is included, submitted for plan review before construction begins (IRC R106).
- A scaled site plan (for example 1/4 inch to 1 foot) showing the new deck's location relative to the house, its overall length and width, and dimensioned distances from the deck to all property lines and other structures so required setbacks can be verified (IRC R106.1.1).
- A deck plan drawn to scale showing overall dimensions and the framing layout: joist size, spacing, span, and species; beam size and span; post size and height; and footing or pier size and depth (IRC R507.4 posts, R507.5 beams, R507.6 joists, R507.3 footings).
- A section or side elevation with connection details showing the ledger attachment to the house band joist with flashing, the fastener or bolt schedule, joist hangers, post-to-beam and post-to-footing connections, and the required lateral load connection (IRC R507.9 ledger connection, R507.9.2 lateral connection, R507.2.4 flashing).
- Footing sizing derived from tributary area, the soil bearing value, and design loads per IRC Table R507.3.1, with footings shown bearing on undisturbed soil at the frost depth required by the jurisdiction (IRC R507.3).
- Details for the guards required where the walking surface is more than 30 inches above grade, and for the stairs and handrails, showing guard height and opening limits, stair riser and tread dimensions, and handrail location (IRC R312 guards, R311.7 stairs and handrails).
- For designs that fall outside the prescriptive R507 tables (for example multi-story or stacked decks, or a ledger attached to a cantilever), engineered and stamped structural plans are submitted in place of the prescriptive details (IRC R507.1 and R301).
General submittal guidance from IRC R106.1.1 (construction documents) and IRC R507 (exterior decks), 2021 IRC. Source. City and County of Denver Community Planning and Development sets the exact checklist for Denver.
Where to apply in Denver:
City and County of Denver Community Planning and Development
- 201 W. Colfax Ave., Dept. 205, Denver, CO 80202
- Phone: 720-865-2720
- Email: planreview@denvergov.org
Inspections and closing out your permit
Deck work is inspected in sequence as it is built: the footings before concrete is placed, the framing before the decking boards go down, and a final inspection once the deck is complete. Each stage checks the items that would be hidden or unsafe if missed.
- Footing or pier inspection: after the holes are dug and any forms or reinforcing are set but before concrete is placed, the inspector checks footing depth and diameter, a flat undisturbed bearing surface, and that the holes are free of water (IRC R109.1.1 foundation inspection; R507.3 footings).
- Framing inspection: after the deck is framed but before the decking conceals it, the inspector verifies the ledger attachment and its flashing, the fastener and bolt schedule, joist hangers and metal connectors, post-to-beam and post-to-footing connections, and the lateral load connection; call it before decking is installed (IRC R109.1.4 frame inspection; R507.9 ledger and flashing).
- Final inspection: after the deck is complete and before it is used, the inspector confirms guard height and opening limits (a 4 inch sphere must not pass, 4 3/8 inch at stairs), stair riser and tread dimensions, handrail height and graspability where there are 4 or more risers, stair landings, and required stair lighting (IRC R109.1.6 final inspection; R312 guards, R311.7 stairs and handrails).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Denver permit portal or by phone at 720-865-2720.
Inspection sequence from IRC R109 (inspections: R109.1.1 footing before concrete, R109.1.4 frame, R109.1.6 final), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Deck Permit checklist for Denver
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: uncovered decks under 12 in off the ground require no permit; 12 in or more requires a zoning permit; 30 in or more also requires a building permit. Usually needed: For any uncovered deck 12 inches or more above grade or any covered deck structure.
- Budget the fee. Valuation-based building permit fee per CPD Table 1 with a $20 minimum for work valued at $500 or less, per the Development Fees schedule (ADMIN 138, rev. May 2024). Official fee schedule.
- Apply. A residential deck permit application is a set of construction documents that show what will be built and prove it meets the IRC deck provisions. In practice that means a scaled site plan locating the deck and its setbacks, plus deck plans and structural details covering the footings, posts, beams, joists, ledger, guards, and stairs. Start at the Denver permit portal.
- Keep the office details handy. City and County of Denver Community Planning and Development. Phone: 720-865-2720. Address: 201 W. Colfax Ave., Dept. 205, Denver, CO 80202.
- Plan for inspections. Deck work is inspected in sequence as it is built: the footings before concrete is placed, the framing before the decking boards go down, and a final inspection once the deck is complete. Each stage checks the items that would be hidden or unsafe if missed.
Compiled from the official sources on this page. Last checked 2026-06-17.
The checklist stays on this page either way. We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Permitting activity in Denver
In 2024, Denver authorized permits for 3,994 new residential housing units (872 single-family, 3,122 in multi-family buildings), valued at $788M, down from5,725 the year before. That works out to about 5.4 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 735,538.
About Denver
Denver has about 352,593 housing units. The median home is valued at $586,700, against a median household income of $91,681. About 49% of homes are owner-occupied, and the typical home was built around 1974.
Source: U.S. Census Bureau, American Community Survey 2023 5-year.
Frequently asked questions
- Do you need a deck permit in Denver?
- Denver requires a zoning permit for uncovered decks 12 inches or more off the ground and a building permit for decks 30 inches or more above grade. All covered patios, porches, pergolas, and carports require both a zoning and building permit regardless of height. Applications are submitted through the CPD e-permits portal. Uncovered decks under 12 in off the ground require no permit; 12 in or more requires a zoning permit; 30 in or more also requires a building permit. Always confirm with the office before starting.
- How much does a deck permit cost in Denver?
- Valuation-based building permit fee per CPD Table 1 with a $20 minimum for work valued at $500 or less, per the Development Fees schedule (ADMIN 138, rev. May 2024). See the official fee schedule for current amounts.
- Where do you apply for a deck permit in Denver?
- You can apply through the Denver permit portal or contact the City and County of Denver Community Planning and Development directly. The links are listed on this page.
From the Library
What else needs a permit in Denver
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Electrical Permit | Permit required | Not specified | Valuation-based fee per CPD Table 1 with a $20 minimum for work valued at $500 or less; |
| Fence Permit | It depends | fences shorter than 4 ft require no permit; fences 4 ft or taller require at minimum a zoning permit; most fence types over 4 ft also require a building permit | Zoning construction permit fee with a $10 minimum for fences valued at $500 or less; |
| HVAC Permit | Permit required | Not specified | Valuation-based fee per CPD Table 1 with a $20 minimum; |
| Patio Permit | It depends | covered patios always require a zoning and building permit; uncovered ground-level patios may not require a permit | Valuation-based building permit fee per CPD Table 1 with a $20 minimum; |
| Plumbing Permit | Permit required | Not specified | Valuation-based fee per CPD Table 1 with a $20 minimum; |
| Pool Permit | Permit required | Not specified | No pool-specific fee line; |
| Roof Replacement Permit | Permit required | Not specified | Issued as a no-plan-review quick permit; |
| Shed Permit | It depends | sheds up to 200 sq ft with 8 ft top plate and 14 ft max height do not require a building permit but may require a zoning permit in some zone districts | No building permit for one-story detached sheds up to 200 sq ft, 8 ft top plate and 14... |
| Solar Permit | Permit required | Not specified | $50 flat permit fee for the solar photovoltaic portion of a project with no plan review... |
Deck Permit in other Colorado localities
Official sources
- https://www.denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/Plan-Review-Permits-and-Inspections/Single-Family-and-Duplex-Projects/Residential-Decks
- https://www.denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/E-permits
- https://www.grafton-ma.gov/DocumentCenter/View/17797/2021-IRC-Residential-Deck-Guide
- https://www.spearfish.gov/DocumentCenter/View/5233/Residential-Deck-handout-PDF
Verified by a person against the sources above on 2026-06-17, not confirmed with City and County of Denver Community Planning and Development. Rules change; confirm before you build. How we verify.
Last checked: 2026-06-17Report an error on this page
Compare
Deck Permit across Colorado