Colorado / Denver

Electrical Permit in Denver, Colorado

By Mario Bailey Last checked 2026-06-17 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

An electrical permit is required in Denver for all residential electrical work including service installations, panel and subpanel work, interior and exterior wiring, EV chargers, and solar systems. Service up to 400 amps and solar under 10 kW DC qualify for the quick permit process without plan review. Homeowners of single-family homes may apply directly.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Denver, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

For all electrical work including wiring panels service upgrades and EV chargers

What electrical permit costs in Denver

Valuation-based fee per CPD Table 1 with a $20 minimum for work valued at $500 or less; service work at 400 amps or less issues as a no-plan-review quick permit, per the Development Fees schedule and Quick Permits page.

Official fee schedule

How Denver compares in Colorado

No Colorado jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Denverthis pagePermit requiredValuation-based fee per CPD Table 1 with a $20 minimum for work valued at $50...
Jefferson CountyPermit requiredElectrical permits not tied to an active building permit bill on the countywi...

How to apply in Denver

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City and County of Denver Community Planning and Development sets the exact checklist for Denver.

Where to apply in Denver:

City and County of Denver Community Planning and Development

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Denver permit portal or by phone at 720-865-2720.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Denver

In 2024, Denver authorized permits for 3,994 new residential housing units (872 single-family, 3,122 in multi-family buildings), valued at $788M, down from5,725 the year before. That works out to about 5.4 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 735,538.

About Denver

Denver has about 352,593 housing units. The median home is valued at $586,700, against a median household income of $91,681. About 49% of homes are owner-occupied, and the typical home was built around 1974.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a electrical permit in Denver?
An electrical permit is required in Denver for all residential electrical work including service installations, panel and subpanel work, interior and exterior wiring, EV chargers, and solar systems. Service up to 400 amps and solar under 10 kW DC qualify for the quick permit process without plan review. Homeowners of single-family homes may apply directly. Always confirm with the City and County of Denver Community Planning and Development before starting.
How much does a electrical permit cost in Denver?
Valuation-based fee per CPD Table 1 with a $20 minimum for work valued at $500 or less; service work at 400 amps or less issues as a no-plan-review quick permit, per the Development Fees schedule and Quick Permits page. See the official fee schedule for current amounts.
Where do you apply for a electrical permit in Denver?
You can apply through the Denver permit portal or contact the City and County of Denver Community Planning and Development directly. The links are listed on this page.

From the Library

What else needs a permit in Denver

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsuncovered decks under 12 in off the ground require no permit; 12 in or more requires a zoning permit; 30 in or more also requires a building permitValuation-based building permit fee per CPD Table 1 with a $20 minimum for work valued...
Fence PermitIt dependsfences shorter than 4 ft require no permit; fences 4 ft or taller require at minimum a zoning permit; most fence types over 4 ft also require a building permitZoning construction permit fee with a $10 minimum for fences valued at $500 or less;
HVAC PermitPermit requiredNot specifiedValuation-based fee per CPD Table 1 with a $20 minimum;
Patio PermitIt dependscovered patios always require a zoning and building permit; uncovered ground-level patios may not require a permitValuation-based building permit fee per CPD Table 1 with a $20 minimum;
Plumbing PermitPermit requiredNot specifiedValuation-based fee per CPD Table 1 with a $20 minimum;
Pool PermitPermit requiredNot specifiedNo pool-specific fee line;
Roof Replacement PermitPermit requiredNot specifiedIssued as a no-plan-review quick permit;
Shed PermitIt dependssheds up to 200 sq ft with 8 ft top plate and 14 ft max height do not require a building permit but may require a zoning permit in some zone districtsNo building permit for one-story detached sheds up to 200 sq ft, 8 ft top plate and 14...
Solar PermitPermit requiredNot specified$50 flat permit fee for the solar photovoltaic portion of a project with no plan review...

Electrical Permit in other Colorado localities

Official sources

Verified by a person against the sources above on 2026-06-17, not confirmed with City and County of Denver Community Planning and Development. Rules change; confirm before you build. How we verify.

Last checked: 2026-06-17Report an error on this page

Compare Electrical Permit requirements across Colorado localities