Pool Permit in Denver, Colorado

By Mario Bailey Last checked 2026-06-17 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

Permanent residential swimming pools in Denver require a building permit, a zoning permit, and a Sewer Use and Drainage Permit (SUDP). Temporary above-ground pools removed at the end of the season do not require permits. Additional trade permits for electrical, plumbing, and mechanical work may also be needed.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Denver, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before constructing any permanent residential swimming pool spa or water feature

What pool permit costs in Denver

No pool-specific fee line; pool construction is a standard valuation-based building permit under CPD Table 1 with a $20 minimum, with plumbing and electrical trade work permitted and charged separately.

Official fee schedule

How Denver compares in Colorado

No Colorado jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Denverthis pagePermit requiredNo pool-specific fee line;
Jefferson CountyPermit requiredPools of any size need a Miscellaneous Permit priced at $90 on the 2026 zonin...

How to apply in Denver

A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.

What most pool permit applications include:

  • Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
  • The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
  • For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
  • A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
  • Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
  • The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).

General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. City and County of Denver Community Planning and Development sets the exact checklist for Denver.

Where to apply in Denver:

City and County of Denver Community Planning and Development

Inspections and closing out your permit

Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.

  1. Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
  2. A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
  3. A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
  4. A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
  5. At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Denver permit portal or by phone at 720-865-2720.

Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Denver

In 2024, Denver authorized permits for 3,994 new residential housing units (872 single-family, 3,122 in multi-family buildings), valued at $788M, down from5,725 the year before. That works out to about 5.4 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 735,538.

About Denver

Denver has about 352,593 housing units. The median home is valued at $586,700, against a median household income of $91,681. About 49% of homes are owner-occupied, and the typical home was built around 1974.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a pool permit in Denver?
Permanent residential swimming pools in Denver require a building permit, a zoning permit, and a Sewer Use and Drainage Permit (SUDP). Temporary above-ground pools removed at the end of the season do not require permits. Additional trade permits for electrical, plumbing, and mechanical work may also be needed. Always confirm with the City and County of Denver Community Planning and Development before starting.
How much does a pool permit cost in Denver?
No pool-specific fee line; pool construction is a standard valuation-based building permit under CPD Table 1 with a $20 minimum, with plumbing and electrical trade work permitted and charged separately. See the official fee schedule for current amounts.
Where do you apply for a pool permit in Denver?
You can apply through the Denver permit portal or contact the City and County of Denver Community Planning and Development directly. The links are listed on this page.

From the Library

What else needs a permit in Denver

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsuncovered decks under 12 in off the ground require no permit; 12 in or more requires a zoning permit; 30 in or more also requires a building permitValuation-based building permit fee per CPD Table 1 with a $20 minimum for work valued...
Electrical PermitPermit requiredNot specifiedValuation-based fee per CPD Table 1 with a $20 minimum for work valued at $500 or less;
Fence PermitIt dependsfences shorter than 4 ft require no permit; fences 4 ft or taller require at minimum a zoning permit; most fence types over 4 ft also require a building permitZoning construction permit fee with a $10 minimum for fences valued at $500 or less;
HVAC PermitPermit requiredNot specifiedValuation-based fee per CPD Table 1 with a $20 minimum;
Patio PermitIt dependscovered patios always require a zoning and building permit; uncovered ground-level patios may not require a permitValuation-based building permit fee per CPD Table 1 with a $20 minimum;
Plumbing PermitPermit requiredNot specifiedValuation-based fee per CPD Table 1 with a $20 minimum;
Roof Replacement PermitPermit requiredNot specifiedIssued as a no-plan-review quick permit;
Shed PermitIt dependssheds up to 200 sq ft with 8 ft top plate and 14 ft max height do not require a building permit but may require a zoning permit in some zone districtsNo building permit for one-story detached sheds up to 200 sq ft, 8 ft top plate and 14...
Solar PermitPermit requiredNot specified$50 flat permit fee for the solar photovoltaic portion of a project with no plan review...

Pool Permit in other Colorado localities

Official sources

Verified by a person against the sources above on 2026-06-17, not confirmed with City and County of Denver Community Planning and Development. Rules change; confirm before you build. How we verify.

Last checked: 2026-06-17Report an error on this page

Compare Pool Permit requirements across Colorado localities