Pool Permit in Denver, Colorado
By Mario Bailey Last checked 2026-06-17 · 2 official sources
Verified against official sources Confirmed on official pagePermit required
Quick answer
Permanent residential swimming pools in Denver require a building permit, a zoning permit, and a Sewer Use and Drainage Permit (SUDP). Temporary above-ground pools removed at the end of the season do not require permits. Additional trade permits for electrical, plumbing, and mechanical work may also be needed.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help
Tell us where your project stands. Free to ask; no obligation.
Where we have a vetted local pro who handles permits in Denver, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
When a permit is usually needed
Before constructing any permanent residential swimming pool spa or water feature
What pool permit costs in Denver
No pool-specific fee line; pool construction is a standard valuation-based building permit under CPD Table 1 with a $20 minimum, with plumbing and electrical trade work permitted and charged separately.
How Denver compares in Colorado
No Colorado jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Denverthis page | Permit required | No pool-specific fee line; |
| Jefferson County | Permit required | Pools of any size need a Miscellaneous Permit priced at $90 on the 2026 zonin... |
How to apply in Denver
A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.
What most pool permit applications include:
- Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
- The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
- For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
- A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
- Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
- The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).
General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. City and County of Denver Community Planning and Development sets the exact checklist for Denver.
Where to apply in Denver:
City and County of Denver Community Planning and Development
- 201 W. Colfax Ave., Dept. 205, Denver, CO 80202
- Phone: 720-865-2720
- Email: planreview@denvergov.org
Inspections and closing out your permit
Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
- Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
- A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
- A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
- A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
- At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Denver permit portal or by phone at 720-865-2720.
Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Pool Permit checklist for Denver
- Confirm the requirement. Yes, a permit is required. Usually needed: Before constructing any permanent residential swimming pool spa or water feature.
- Budget the fee. No pool-specific fee line; pool construction is a standard valuation-based building permit under CPD Table 1 with a $20 minimum, with plumbing and electrical trade work permitted and charged separately. Official fee schedule.
- Apply. A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect. Start at the Denver permit portal.
- Keep the office details handy. City and County of Denver Community Planning and Development. Phone: 720-865-2720. Address: 201 W. Colfax Ave., Dept. 205, Denver, CO 80202.
- Plan for inspections. Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
Compiled from the official sources on this page. Last checked 2026-06-17.
The checklist stays on this page either way. We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Permitting activity in Denver
In 2024, Denver authorized permits for 3,994 new residential housing units (872 single-family, 3,122 in multi-family buildings), valued at $788M, down from5,725 the year before. That works out to about 5.4 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 735,538.
About Denver
Denver has about 352,593 housing units. The median home is valued at $586,700, against a median household income of $91,681. About 49% of homes are owner-occupied, and the typical home was built around 1974.
Source: U.S. Census Bureau, American Community Survey 2023 5-year.
Frequently asked questions
- Do you need a pool permit in Denver?
- Permanent residential swimming pools in Denver require a building permit, a zoning permit, and a Sewer Use and Drainage Permit (SUDP). Temporary above-ground pools removed at the end of the season do not require permits. Additional trade permits for electrical, plumbing, and mechanical work may also be needed. Always confirm with the City and County of Denver Community Planning and Development before starting.
- How much does a pool permit cost in Denver?
- No pool-specific fee line; pool construction is a standard valuation-based building permit under CPD Table 1 with a $20 minimum, with plumbing and electrical trade work permitted and charged separately. See the official fee schedule for current amounts.
- Where do you apply for a pool permit in Denver?
- You can apply through the Denver permit portal or contact the City and County of Denver Community Planning and Development directly. The links are listed on this page.
From the Library
What else needs a permit in Denver
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | uncovered decks under 12 in off the ground require no permit; 12 in or more requires a zoning permit; 30 in or more also requires a building permit | Valuation-based building permit fee per CPD Table 1 with a $20 minimum for work valued... |
| Electrical Permit | Permit required | Not specified | Valuation-based fee per CPD Table 1 with a $20 minimum for work valued at $500 or less; |
| Fence Permit | It depends | fences shorter than 4 ft require no permit; fences 4 ft or taller require at minimum a zoning permit; most fence types over 4 ft also require a building permit | Zoning construction permit fee with a $10 minimum for fences valued at $500 or less; |
| HVAC Permit | Permit required | Not specified | Valuation-based fee per CPD Table 1 with a $20 minimum; |
| Patio Permit | It depends | covered patios always require a zoning and building permit; uncovered ground-level patios may not require a permit | Valuation-based building permit fee per CPD Table 1 with a $20 minimum; |
| Plumbing Permit | Permit required | Not specified | Valuation-based fee per CPD Table 1 with a $20 minimum; |
| Roof Replacement Permit | Permit required | Not specified | Issued as a no-plan-review quick permit; |
| Shed Permit | It depends | sheds up to 200 sq ft with 8 ft top plate and 14 ft max height do not require a building permit but may require a zoning permit in some zone districts | No building permit for one-story detached sheds up to 200 sq ft, 8 ft top plate and 14... |
| Solar Permit | Permit required | Not specified | $50 flat permit fee for the solar photovoltaic portion of a project with no plan review... |
Pool Permit in other Colorado localities
Official sources
- https://denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/Plan-Review-Permits-and-Inspections/Single-Family-and-Duplex-Projects/Swimming-Pools-Spas-and-Water-Features
- https://www.denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/E-permits
- https://www.bountifulutah.gov/file/ee478521-f791-4cee-a755-2d923ff70257
Verified by a person against the sources above on 2026-06-17, not confirmed with City and County of Denver Community Planning and Development. Rules change; confirm before you build. How we verify.
Last checked: 2026-06-17Report an error on this page