Texas / Plano

Solar Permit in Plano, Texas

Permit required

Yes, a permit is required

Before installing a rooftop or accessory-structure photovoltaic system. The signed self-checklist goes in with the plans and the application.

Confirmed on official page Verified City of Plano Building Inspections Department

By Mario Bailey, verified against official sources

Quick answer

Plano permits residential solar as a photovoltaic installation, with its own $150.00 line in the adopted fee schedule. The City publishes a Solar Panel PV Checklist that must be signed and submitted with the plans and application, calling for inverter, module and racking manufacturer sheets in duplicate, a site plan showing modules, inverters, combiner boxes, all AC and DC disconnects, the utility disconnect, meters and the service panel board, and one-line or three-line diagrams. If the equipment pushes the roof load assembly past 10 psf, a structural load assessment letter from a State of Texas licensed engineer is required. The wiring itself falls under the Electrical Code permit requirement in Chapter 6, Section 6-351.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a rooftop or accessory-structure photovoltaic system. The signed self-checklist goes in with the plans and the application.

What a solar permit costs in Plano

Line item
solar permitBy formulaBuilding Inspections Fee Schedule effective Jan. 2, 2026 (Exhibit "A" to Ordinance No. 2025-11-4): "PHOTOVOLTAIC (Residential) 150.00".
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Plano compares in Texas

No Texas jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
ArlingtonPermit requiredPlanning and Development Services Fee Schedule, Effective June 1, 2026...
AustinPermit requiredSolar permits carry a $32.47 intake fee plus a $111.66 auxiliary power...
Corpus ChristiPermit requiredThe FY 2026 Development Fee Schedule publishes no solar line item.
DallasPermit requiredNo solar-specific line
El PasoPermit requiredFY 2026 Schedule C Departmental Fee List, Planning & Inspections, prices solar...
Fort WorthPermit requiredThe Schedule of Mechanical Fees, Table 1-H, carries a "Solar energy system:...
Planothis pagePermit requiredBuilding Inspections Fee Schedule effective Jan.

How to apply in Plano

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Plano Building Inspections Department sets the exact checklist for Plano.

Where to apply in Plano:

City of Plano Building Inspections Department

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Plano permit portal or by phone at 972-941-7140.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Plano?
Plano permits residential solar as a photovoltaic installation, with its own $150.00 line in the adopted fee schedule. The City publishes a Solar Panel PV Checklist that must be signed and submitted with the plans and application, calling for inverter, module and racking manufacturer sheets in duplicate, a site plan showing modules, inverters, combiner boxes, all AC and DC disconnects, the utility disconnect, meters and the service panel board, and one-line or three-line diagrams. If the equipment pushes the roof load assembly past 10 psf, a structural load assessment letter from a State of Texas licensed engineer is required. The wiring itself falls under the Electrical Code permit requirement in Chapter 6, Section 6-351. Always confirm with the City of Plano Building Inspections Department before starting.
How much does a solar permit cost in Plano?
Building Inspections Fee Schedule effective Jan. 2, 2026 (Exhibit "A" to Ordinance No. 2025-11-4): "PHOTOVOLTAIC (Residential) 150.00". See the official fee schedule for current amounts.
Where do you apply for a solar permit in Plano?
You can apply through the Plano permit portal or contact the City of Plano Building Inspections Department directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Plano?
Under Texas law (Tex. Occupations Code 1305.003(a)(6), 1301.051; Tex. Local Government Code 233.157(c)): Texas licenses individual construction trades rather than general contractors, so no state statute requires a license to act as your own general contractor on your own house. For electrical work, the state licensing law does not apply to work performed in or on a dwelling by a person who owns and resides in it, but only where no municipal ordinance specifically regulates that work, so city electrical licensing and permit rules still control inside city limits (Occupations Code 1305.003(a)(6)). For plumbing, a property owner does not need a state license to perform plumbing in the owner's homestead (Occupations Code 1301.051). In opt-in counties' unincorporated areas, an individual who builds their own house or acts as their own contractor is exempt from the Class C misdemeanor penalty for inspection notice failures if they intend to use the home as their primary residence (Local Government Code 233.157(c)). None of these exemptions waive local permit or inspection requirements where they apply. Confirm how Plano applies this before you apply.

From the Library

What else needs a permit in Plano

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsdeck area, and the exemption also requires the deck to be no more than 30 inches above grade at any point, unattached to the dwelling or townhouse, and not serving the required exit doorThe Jan.
Electrical PermitPermit requiredNot specifiedBuilding Inspections Fee Schedule effective Jan.
Fence PermitIt dependsshare of an existing fence's area repaired, measured over any 12-month periodBuilding Inspections Fee Schedule effective Jan.
HVAC PermitPermit requiredNot specifiedBuilding Inspections Fee Schedule effective Jan.
Patio PermitIt dependsNot specifiedThe Jan.
Plumbing PermitPermit requiredNot specifiedBuilding Inspections Fee Schedule effective Jan.
Pool PermitIt dependsdepth of a prefabricated swimming poolBuilding Inspections Fee Schedule effective Jan.
Roof Replacement PermitIt dependsshare of the roof being re-roofedBuilding Inspections Fee Schedule effective Jan.
Shed PermitIt dependsfloor area of a one-story detached accessory structureBuilding Inspections Fee Schedule effective Jan.

Solar Permit in other Texas localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Plano documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Plano Building Inspections Department. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Solar Permit requirements across Texas localities

Permit required
Get quotes