Before installing an in-ground pool at or above the exempt size, before any pool with structural work or supports, and before any pool with a permanently equipped water circulating system.
Quick answer
The Building Division requires a permit for "swimming pools more than 24 inches deep or more than 30 inches wall height and with a surface area of 250 square feet or more", and separately for any pool involving structural work or supports and for all pools with a permanently equipped water circulating system. The matching exemption covers above-ground pools and in-ground pools under 24 inches of water depth with a surface area under 250 square feet. All pools, hot tubs and spas must still keep the setbacks in the Zoning Ordinance. The fence exemption does not travel here: the codified exemption for replacing an existing fence expressly does not apply when the fence encloses a swimming pool, hot tub or spa, so pool barrier work needs its own permit.
- Typical threshold
- inches of water depth, applied together with a 250 square foot surface area test
- Issued by
- City of St. Louis Building Division, Permit Section (Department of Public Safety)
- Phone
- (314) 622-3313
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Pool builders handle the permit and its safety requirements as part of the job. Comparing a few bids before you sign is the useful next step.
Compare pool builder quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
What a pool permit costs in St. Louis
- Fee schedule in force
- Official scheduleRead .
Charged as a building permit on estimated construction cost: $25.00 application fee plus $19.00 for $0 to $1,000.00 (total $44.00), $23.00 for $1,001 to $2,000.00, $30.00 for $2,001 to $3,000.00, and "$10.00 per thousand estimated construction cost or fraction thereof" above $3,000.00.
A pool with a permanently equipped water circulating system will also need a separate plumbing permit ($30.00 application fee) and usually an electrical permit ($25.00 application fee).
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in St. Louis
General guide, not specific to this office
What a pool permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a pool permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
City of St. Louis Building Division, Permit Section (Department of Public Safety)
- Building Division Permit Section, City Hall, 1200 Market Street, Room 425, St. Louis, MO 63103
- Phone: (314) 622-3313
- Email: stlcitypermits@stlouis-mo.gov
Pool Permit in St. Louis compared with nearby Missouri localities
| Locality | Permit needed? | Threshold | What each Missouri schedule says | Verified |
|---|---|---|---|---|
| St. Louis | It depends | inches of water depth, applied together with a 250 square foot surface area test | Charged as a building permit on estimated construction cost: $25.00 application fee plus $19.00 for $0 to $1,000.00 (total $44.00); the schedule has the rest | |
| Kansas City | It depends | water capacity of a prefabricated above ground pool accessory to a one- or two-family dwelling that is also less than 24 inches deep with its walls entirely above the adjacent grade | See schedule |
Your Pool Permit checklist for St. Louis
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: inches of water depth, applied together with a 250 square foot surface area test. Read the rule where we read it: stlouis-mo.gov: permits.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the St. Louis permit portal.
- Keep the office details handy. City of St. Louis Building Division, Permit Section (Department of Public Safety). Phone: (314) 622-3313. Email: stlcitypermits@stlouis-mo.gov. Address: Building Division Permit Section, City Hall, 1200 Market Street, Room 425, St. Louis, MO 63103.
Compiled from the official sources on this page. Last checked .
Permitting activity in St. Louis
In 2025, St. Louis authorized permits for 272 new residential housing units (57 single-family, 215 in multi-family buildings), valued at $51M, down from 294 the year before. That works out to about 0.9 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 297,645.
What else needs a permit in St. Louis
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | inches above adjacent grade for an uncovered wood deck or patio resting directly on the ground or a rock base with no permanent foundation | Charged as a building permit on estimated construction cost: $25.00 application fee plus $19.00 for $0 to $1,000.00 (total $44.00); the schedule has the rest |
| Electrical Permit | It depends | Before starting any electrical work other than the code's listed minor repairs, and... | The application fee for all electrical permits is $25.00 |
| Fence Permit | It depends | Before building any new fence | See schedule |
| HVAC Permit | It depends | Before installing or replacing a furnace, condensing unit, combination system, boiler... | There is a $25.00 application fee for each permit |
| Patio Permit | It depends | Not needed for a flat, open, at-grade paved patio on the same lot as the house | See schedule |
| Plumbing Permit | It depends | Before any plumbing, drainlaying or process drainage work, any connection to a sewer... | The application fee for all plumbing permits is $30.00 |
| Roof Replacement Permit | It depends | percent of roof sheathing removed and replaced during a like-material roof covering replacement | See schedule |
| Shed Permit | It depends | square feet of floor area for a detached accessory building, which must also keep the setbacks required by the Zoning Ordinance | See schedule |
| Solar Permit | Permit required | Any size | Charged as a building permit on estimated construction cost: $25.00 application fee plus $19.00 for $0 to $1,000.00; the schedule has the rest |
Frequently asked questions
- Do you need a pool permit in St. Louis?
- It depends on the project. Inches of water depth, applied together with a 250 square foot surface area test. If you are unsure how that applies to your project, call the permit office at (314) 622-3313 before you start.
- How much does a pool permit cost in St. Louis?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Aug 2026. For the figure on your own project, call the permit office at (314) 622-3313.
- Where do you apply for a pool permit in St. Louis?
- You can apply through the St. Louis permit portal or contact the City of St. Louis Building Division, Permit Section (Department of Public Safety) directly. The links are listed on this page.
- Can a homeowner pull a pool permit themselves in St. Louis?
- Under Missouri law (RSMo 701.055.1 and 701.055.2; RSMo 327.101.2(5)(a); RSMo 327.191.2(5)(a); RSMo 700.656.5): Missouri does not license general contractors at the state level and has no statewide owner-builder permit statute, disclosure affidavit, or resale restriction comparable to Florida's one year rule. Whether a homeowner may pull the permit and do the work is decided by the city or county that issues the permit. Where state law does speak, it is permissive: RSMo 327.101.2(5)(a) and RSMo 327.191.2(5)(a) let an unlicensed person render architectural and engineering services for the construction, remodeling or repair of a privately owned dwelling house, provided the drawings say the person is not licensed, so plans for a house do not have to be sealed by an architect or engineer. RSMo 701.055.1 expressly preserves a property owner's right to install, modify or repair their own on-site sewage disposal system as long as the state standard is met, and RSMo 701.055.2 adds that no permit or contractor registration is required simply to clean it. RSMo 700.656.5 exempts a person who installs a manufactured home on his or her own property for his or her own occupancy from the otherwise mandatory state installer license. None of these exemptions excuses a local permit where the local jurisdiction requires one. Confirm how St. Louis applies this before you apply.
From the Library
Pool Permit in other Missouri localities
Everything above, sourced
How this pool permit page for St. Louis was verified. 2 official sources: stlouis-mo.gov, stlouis-mo.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of St. Louis Building Division, Permit Section (Department of Public Safety). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page