Patio Permit in St. Louis, Missouri

It depends

Sometimes, depending on the project

Not needed for a flat, open, at-grade paved patio on the same lot as the house. Needed once you add a roof, cover or enclosure, or build the patio on a permanent foundation.

Confirmed on official page Verified City of St. Louis Building Division, Permit Section (Department of Public Safety)

By Mario Bailey, verified against official sources

Quick answer

An at-grade paved patio is exempt in the City of St. Louis: the Building Division lists "paved areas for residential use on the same lot as the primary structure, without roof, covers or enclosures" among work that usually does not require a permit. The exemption turns on the cover, not the size, so a patio cover, pergola roof or screened enclosure pushes the project into permit territory, and the Division publishes a dedicated Attached Patio Cover plan guideline for exactly that case. Title 25 adds two limits the web page omits: the slab or wood patio must rest directly on the ground or a rock base, sit on no permanent foundation, and stay a maximum of twelve inches above adjacent grade.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Not needed for a flat, open, at-grade paved patio on the same lot as the house. Needed once you add a roof, cover or enclosure, or build the patio on a permanent foundation.

What a patio permit costs in St. Louis

Line item
patio permitBy formulaA patio cover is charged as a building permit on estimated construction cost: $25.00 application fee plus $19.00 for $0 to $1,000.00 (total $44.00), $23.00 for $1,001 to $2,000.00, $30.00 for $2,001 to $3,000.00, and "$10.00 per thousand estimated construction cost or fraction thereof" above $3,000.00. Fees are non-refundable.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in St. Louis

Applying for a patio permit means submitting a site plan and framing plans for a roofed patio cover, since a cover is treated as its own permitted structure regardless of size. A plain concrete or paver patio slab at or near grade is, by contrast, often exempt from that same building permit requirement.

What most patio permit applications include:

  • Filing a permit application with the local building department, which only the property owner or an authorized agent may sign, since a patio cover is treated as its own permitted structure regardless of size (IRC R105.1).
  • A scaled site plan showing the new patio cover's size and location relative to the house and other existing structures, with dimensioned distances to all property lines so required setbacks can be verified before the permit is approved (IRC R106.2).
  • Construction documents such as a framing plan and elevation, showing rafter or beam sizes and spacing, the distance between supporting posts, and the method of attachment to the house, drawn with enough clarity for the building official to confirm the work will conform to the code (IRC R106.1).
  • For the roof structure itself, plans showing compliance with the patio cover appendix's structural limits, such as adequate footing sizes for the applied post loads, since a shallow slab on grade may substitute for a deeper footing only in limited cases up to about 750 pounds of load per post (IRC Appendix AH, Section AH105.2).
  • By contrast, an at grade concrete or paver patio that is not attached to the dwelling and stays within the code's small flatwork thresholds, similar to a sidewalk, driveway, or low deck under 200 square feet and 30 inches high, commonly needs no building permit at all, so none of the plan review steps above apply (IRC R105.2).

General submittal guidance from 2021 International Residential Code (IRC), Sections R105 and R106, with Appendix AH Patio Covers (named Appendix H in the 2012, 2015, and 2018 editions). Source. City of St. Louis Building Division, Permit Section (Department of Public Safety) sets the exact checklist for St. Louis.

Where to apply in St. Louis:

City of St. Louis Building Division, Permit Section (Department of Public Safety)

  • Building Division Permit Section, City Hall, 1200 Market Street, Room 425, St. Louis, MO 63103
  • Phone: (314) 622-3313
  • Email: stlcitypermits@stlouis-mo.gov

Inspections and closing out your permit

A permitted patio cover follows the same footing, frame, and final inspection sequence used for any small accessory structure, since the posts and roof framing have to be checked before they are covered and again once the work is done. An at grade patio slab that qualifies as exempt flatwork usually needs no building inspection at all, because inspections only attach to work that required a permit in the first place.

  1. A footing inspection once the excavation, forms, and any reinforcing steel are in place but before concrete is poured, confirming the posts supporting a patio cover will bear on adequate footings (IRC R109.1.1).
  2. A frame inspection after the rafters, beams, posts, and any required rough in work are in place but before the roof sheathing or covering material conceals them, since a solid patio cover roof cannot be signed off once it is covered without this check (IRC R109.1.4).
  3. A final inspection once all permitted work, including roofing and post anchorage, is complete, which the code requires before the structure may be used (IRC R109.1.6).
  4. An at grade concrete or paver patio that qualifies as exempt flatwork under the permit rules is not subject to any of these inspection stages, since the inspection sequence only attaches to work that required a permit in the first place (IRC R105.2).
  5. Each inspection has to be requested by the permit holder rather than happening automatically, and the approved plans and permit card need to be on site and available when the inspector arrives (IRC R109.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the St. Louis permit portal or by phone at (314) 622-3313.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a patio permit in St. Louis?
An at-grade paved patio is exempt in the City of St. Louis: the Building Division lists "paved areas for residential use on the same lot as the primary structure, without roof, covers or enclosures" among work that usually does not require a permit. The exemption turns on the cover, not the size, so a patio cover, pergola roof or screened enclosure pushes the project into permit territory, and the Division publishes a dedicated Attached Patio Cover plan guideline for exactly that case. Title 25 adds two limits the web page omits: the slab or wood patio must rest directly on the ground or a rock base, sit on no permanent foundation, and stay a maximum of twelve inches above adjacent grade. Always confirm with the City of St. Louis Building Division, Permit Section (Department of Public Safety) before starting.
How much does a patio permit cost in St. Louis?
A patio cover is charged as a building permit on estimated construction cost: $25.00 application fee plus $19.00 for $0 to $1,000.00 (total $44.00), $23.00 for $1,001 to $2,000.00, $30.00 for $2,001 to $3,000.00, and "$10.00 per thousand estimated construction cost or fraction thereof" above $3,000.00. Fees are non-refundable. See the official fee schedule for current amounts.
Where do you apply for a patio permit in St. Louis?
You can apply through the St. Louis permit portal or contact the City of St. Louis Building Division, Permit Section (Department of Public Safety) directly. The links are listed on this page.
Can a homeowner pull a patio permit themselves in St. Louis?
Under Missouri law (RSMo 701.055.1 and 701.055.2; RSMo 327.101.2(5)(a); RSMo 327.191.2(5)(a); RSMo 700.656.5): Missouri does not license general contractors at the state level and has no statewide owner-builder permit statute, disclosure affidavit, or resale restriction comparable to Florida's one year rule. Whether a homeowner may pull the permit and do the work is decided by the city or county that issues the permit. Where state law does speak, it is permissive: RSMo 327.101.2(5)(a) and RSMo 327.191.2(5)(a) let an unlicensed person render architectural and engineering services for the construction, remodeling or repair of a privately owned dwelling house, provided the drawings say the person is not licensed, so plans for a house do not have to be sealed by an architect or engineer. RSMo 701.055.1 expressly preserves a property owner's right to install, modify or repair their own on-site sewage disposal system as long as the state standard is met, and RSMo 701.055.2 adds that no permit or contractor registration is required simply to clean it. RSMo 700.656.5 exempts a person who installs a manufactured home on his or her own property for his or her own occupancy from the otherwise mandatory state installer license. None of these exemptions excuses a local permit where the local jurisdiction requires one. Confirm how St. Louis applies this before you apply.

From the Library

What else needs a permit in St. Louis

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsinches above adjacent grade for an uncovered wood deck or patio resting directly on the ground or a rock base with no permanent foundationCharged as a building permit on estimated construction cost: $25.00 application fee plus...
Electrical PermitIt dependsNot specifiedElectrical permit fees are established by City Ordinance 70802.
Fence PermitIt dependsNot specifiedA fence is permitted as a Miscellaneous Structures Permit under Section 109.2.3 of the...
HVAC PermitIt dependsNot specifiedMechanical permit fees are established by City Ordinance 70800.
Plumbing PermitIt dependsNot specifiedPlumbing permit fees are established by City Ordinance 71644.
Pool PermitIt dependsinches of water depth, applied together with a 250 square foot surface area testCharged as a building permit on estimated construction cost: $25.00 application fee plus...
Roof Replacement PermitIt dependspercent of roof sheathing removed and replaced during a like-material roof covering replacementCharged as a building permit for alterations and repairs on estimated construction cost:...
Shed PermitIt dependssquare feet of floor area for a detached accessory building, which must also keep the setbacks required by the Zoning OrdinanceCharged as a building permit on estimated construction cost: $25.00 application fee plus...
Solar PermitPermit requiredNot specifiedCharged as a building permit on estimated construction cost: $25.00 application fee plus...

Patio Permit in other Missouri localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not St. Louis documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of St. Louis Building Division, Permit Section (Department of Public Safety). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Patio Permit requirements across Missouri localities

It depends
Get quotes