Yes, a permit is required
Before constructing any fence anywhere in the city, at any height. A fence plan review is always required; a fence over seven feet tall additionally requires a permit from the building official.
By Mario Bailey, verified against official sources
Quick answer
Saint Paul is unusual in that no fence is exempt: Sec. 33.07(b) of the Legislative Code requires a fence plan review from the building official for every fence in the city, and Sec. 33.07(a) adds a permit on top of that for any fence greater than seven feet in height. What changes at seven feet is which application you file, not whether you need one, and PAULIE reflects that with separate "Residential Fence 7 Feet and Under Permit" and "Residential Fence Over 7 Feet High Permit" applications for both homeowners and contractors. Height caps are four feet in a front yard, seven feet in side and rear yards, and two feet inside the ten foot triangle at the corner of a corner lot unless the fence is more than eighty percent open. A fence inspection is not required for most installations, but fences over seven feet, swimming pool fences and barbed wire fences must be inspected, and every fence in a heritage preservation district also needs Heritage Preservation Commission design review before the plan review can be approved.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before constructing any fence anywhere in the city, at any height. A fence plan review is always required; a fence over seven feet tall additionally requires a permit from the building official.
What a fence permit costs in Saint Paul
How to apply in Saint Paul
Most residential fences fall under the model code's 7-foot building-permit exemption, so the real approval step is a lightweight zoning or land-use permit built around a simple site plan showing the fence's location, height, and material, checked against setbacks and any corner-lot sight-triangle rule. A fence that will serve as a required swimming-pool barrier is the exception, since barrier fences carry life-safety requirements of their own.
What most fence permit applications include:
- A fence 7 feet or under is exempt from the model code's building permit, the same threshold the IRC uses for other small projects (IRC 2021 R105.2).
- That exemption only removes the building-code permit. It does not authorize skipping a jurisdiction's own zoning approval, which is why an exempt fence can still need its own land-use or zoning permit rather than a building permit (IRC 2021 R105.2).
- Whatever your jurisdiction calls that approval, the application centers on a basic site plan: a drawing of the property showing the fence's location, height, and material, and how it relates to the property lines (common local zoning practice).
- The same plan is checked against required setbacks and, on corner lots or near intersections, a sight-triangle rule that caps fence height so it does not block sightlines for drivers (common local zoning practice).
- A fence that will serve as a required swimming-pool barrier is handled as life-safety work rather than the light zoning process, and at least one state's adopted residential code requires a building permit for barrier fences regardless of the general fence exemption (Oregon Residential Specialty Code 2021, R101.2.2).
General submittal guidance from International Residential Code (IRC), 2021 edition, Section R105.2. Source. City of Saint Paul Department of Safety and Inspections (DSI) sets the exact checklist for Saint Paul.
Where to apply in Saint Paul:
City of Saint Paul Department of Safety and Inspections (DSI)
- Department of Safety and Inspections, 375 Jackson Street, Suite 220, Saint Paul, MN 55101-1806
- Phone: 651-266-8989
- Email: DSI-BuildingPlanReview@ci.stpaul.mn.us
Inspections and closing out your permit
Inspection follows the permit: a fence that never needed one gets no inspection at all under the model code, and a permitted fence typically gets a single final check rather than the staged inspections used for a house. The exception is a fence serving as a swimming-pool barrier, which gets its own dedicated barrier inspection covering height, gaps, and gate hardware.
- Inspection duty attaches only to work for which a permit is required, so a fence that qualified for the permit exemption carries no inspection obligation under the model code (IRC 2021 R109.1).
- Where a fence permit was issued, the process skips the staged foundation, frame, and rough-in inspections used for buildings and goes straight to one final inspection once the fence is finished (IRC 2021 R109.1.6).
- That single check is typically a zoning compliance inspection rather than a structural review, confirming the fence matches the approved height and site plan (common local practice).
- A fence built as a swimming-pool barrier breaks that light-touch pattern: it is separately inspected for barrier compliance, commonly required before the pool itself can be signed off (ISPSC 305; local pool-barrier inspection programs).
- That barrier inspection checks dimensional rules from the swimming pool and spa code rather than ordinary fence rules, including the minimum 48 inch barrier height and limits on openings and gaps a young child could pass through (ISPSC 305).
- Gate hardware is inspected too: a self-closing, self-latching gate is part of the barrier requirement, since an unlatched gate defeats the fence's purpose as a barrier (ISPSC 305).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Saint Paul permit portal or by phone at 651-266-8989.
Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109, and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Fence Permit checklist for Saint Paul
- Confirm the requirement. Yes, a permit is required. Usually needed: Before constructing any fence anywhere in the city, at any height. A fence plan review is always required; a fence over seven feet tall additionally requires a permit from the building official.
- Budget the fee. Saint Paul Legislative Code Sec. 33.04(g)(17), line item "Fences permit/plan review": "Forty-five dollars ($45.00) for the first two hundred (200) lineal feet or fraction thereof erected and fifteen dollars ($15.00) for each additional one hundred (100) lineal feet or fraction thereof." Sec. 33.04 was last amended by Ord 25-41, Sec. 2, effective 8-6-25. The DSI fence page publishes the same figures: "Fee ($45 for the first 200 lineal feet or fraction thereof and $15 for each additional 100 lineal feet or fraction thereof)". A fence height or corner clearance variance is a separate nonrefundable $85.00 application fee per request under Sec. 33.07(d). Official fee schedule.
- Apply. Most residential fences fall under the model code's 7-foot building-permit exemption, so the real approval step is a lightweight zoning or land-use permit built around a simple site plan showing the fence's location, height, and material, checked against setbacks and any corner-lot sight-triangle rule. A fence that will serve as a required swimming-pool barrier is the exception, since barrier fences carry life-safety requirements of their own. Start at the Saint Paul permit portal.
- Keep the office details handy. City of Saint Paul Department of Safety and Inspections (DSI). Phone: 651-266-8989. Address: Department of Safety and Inspections, 375 Jackson Street, Suite 220, Saint Paul, MN 55101-1806.
- Plan for inspections. Inspection follows the permit: a fence that never needed one gets no inspection at all under the model code, and a permitted fence typically gets a single final check rather than the staged inspections used for a house. The exception is a fence serving as a swimming-pool barrier, which gets its own dedicated barrier inspection covering height, gaps, and gate hardware.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a fence permit in Saint Paul?
- Saint Paul is unusual in that no fence is exempt: Sec. 33.07(b) of the Legislative Code requires a fence plan review from the building official for every fence in the city, and Sec. 33.07(a) adds a permit on top of that for any fence greater than seven feet in height. What changes at seven feet is which application you file, not whether you need one, and PAULIE reflects that with separate "Residential Fence 7 Feet and Under Permit" and "Residential Fence Over 7 Feet High Permit" applications for both homeowners and contractors. Height caps are four feet in a front yard, seven feet in side and rear yards, and two feet inside the ten foot triangle at the corner of a corner lot unless the fence is more than eighty percent open. A fence inspection is not required for most installations, but fences over seven feet, swimming pool fences and barbed wire fences must be inspected, and every fence in a heritage preservation district also needs Heritage Preservation Commission design review before the plan review can be approved. Always confirm with the City of Saint Paul Department of Safety and Inspections (DSI) before starting.
- How much does a fence permit cost in Saint Paul?
- Saint Paul Legislative Code Sec. 33.04(g)(17), line item "Fences permit/plan review": "Forty-five dollars ($45.00) for the first two hundred (200) lineal feet or fraction thereof erected and fifteen dollars ($15.00) for each additional one hundred (100) lineal feet or fraction thereof." Sec. 33.04 was last amended by Ord 25-41, Sec. 2, effective 8-6-25. The DSI fence page publishes the same figures: "Fee ($45 for the first 200 lineal feet or fraction thereof and $15 for each additional 100 lineal feet or fraction thereof)". A fence height or corner clearance variance is a separate nonrefundable $85.00 application fee per request under Sec. 33.07(d). See the official fee schedule for current amounts.
- Where do you apply for a fence permit in Saint Paul?
- You can apply through the Saint Paul permit portal or contact the City of Saint Paul Department of Safety and Inspections (DSI) directly. The links are listed on this page.
- Can a homeowner pull a fence permit themselves in Saint Paul?
- Under Minnesota law (Minn. Stat. 326B.805, subd. 6, clause (3)): Minnesota requires a license to work as a residential building contractor, remodeler, or roofer, but it exempts an owner who builds or improves their own residential real estate if the owner occupies it, or will occupy it, for residential purposes, or keeps it as a rental once the work is done. That exemption lets a homeowner act as their own contractor and pull permits without holding a contractor's license. The exemption does not apply to an owner building or improving property for resale or speculation, and the law presumes speculation if the owner builds or improves more than one property within any 24-month period, unless each property is retained for rental. This is a licensing exemption only; it does not remove the separate requirement to obtain a building permit for the work itself. Confirm how Saint Paul applies this before you apply.
From the Library
What else needs a permit in Saint Paul
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | height of a deck or platform above grade, where it is also not attached to a structure with frost footings and does not act as a landing outside an exterior door | A deck building permit is priced from the valuation table in Sec. |
| Electrical Permit | Permit required | Not specified | Sec. |
| HVAC Permit | Permit required | Not specified | Warm air, Sec. |
| Patio Permit | It depends | Not specified | There is no patio line item in the fee schedule. |
| Plumbing Permit | Permit required | Not specified | DSI's Plumbing Application, Inspection and Fees page (last edited March 3, 2026) and Sec. |
| Pool Permit | It depends | water capacity of an in-ground or above ground swimming pool; the prefabricated pool exemption additionally requires the pool to be no more than 24 inches deep and installed entirely above ground | The pool building permit is priced from the valuation table in Sec. |
| Roof Replacement Permit | Permit required | Not specified | A reroof is a general building permit priced on valuation under Sec. |
| Shed Permit | It depends | floor area of a one-story detached accessory structure used as a tool or storage shed, playhouse or similar use | A shed over 200 square feet is a general building permit priced from the valuation table... |
| Solar Permit | Permit required | Not specified | Two fees. |
Fence Permit in other Minnesota localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Saint Paul documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with City of Saint Paul Department of Safety and Inspections (DSI). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Fence Permit requirements across Minnesota localities