Minnesota / Saint Paul

HVAC Permit in Saint Paul, Minnesota

Permit required

Yes, a permit is required

Before installing, altering, reconstructing or repairing any heating, ventilating, cooling or refrigeration equipment, including a furnace or air conditioner changeout.

Quick answer

Sec. 33.03(c) of the Legislative Code requires a permit from the building official for any work on heating, ventilating, cooling, refrigeration equipment or process piping, with no dollar or capacity floor. In practice a furnace or air conditioner changeout takes more than one permit: DSI's Air Condition/Furnace/Boiler Installation page says air conditioner and furnace installations also require a Warm Air / Ventilation / General Sheet Metal permit and a Mechanical permit alongside the electrical permit, and gas piping to the appliance is picked up by the plumbing and gas permit. A homesteading owner of a single family dwelling may pull the warm air permit if they do the work themselves and file the homeowner's affidavit; residential properties of three or more units and commercial properties must use a warm air and ventilation contractor licensed by the City of Saint Paul, and Saint Paul licenses these trades itself rather than accepting a state license alone.

Issued by
City of Saint Paul Department of Safety and Inspections (DSI)
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

HVAC contractors usually pull this permit as part of the job. If you have not picked one yet, compare a few quotes before you commit.

Compare HVAC contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What an HVAC permit costs in Saint Paul

Fee basis
Project valuation
Fee schedule in force
Official scheduleRead .
Published in
Warm air, Sec. 33.04(g)(15)a and DSI's Warm Air Inspections and Fees page:
  • "For each warm air heating system, the permit fee is $85 for the first 100,000 input BTU per hour or fraction thereof, plus $15 for each additional 100,000 input BTU per hour or fraction thereof (output BTUs do not affect fee calculation)."
  • Ventilation, ductwork, bath exhaust and dryer exhaust are 1 percent of total valuation with an $85 minimum per dwelling unit.
  • Electrical for the same equipment is $15 per unit installed per circuit, $0 if it is done with other electrical work and needs no new circuit, with an $85 minimum and a $1 minimum state surcharge.
  • Gas burner and oil burner work is $85.00 for the first 100,000 BTU per hour input plus $15.00 for each additional 100,000, capped at $1,007.00 per appliance.
  • Refrigeration is 1 percent of the value of the work with an $85.00 minimum.
  • The state surcharge is $0.50 for valuations of $1 to $1,000, otherwise 0.0005 times the valuation.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Saint Paul

General guide, not specific to this office

What an HVAC permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an HVAC permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

City of Saint Paul Department of Safety and Inspections (DSI)

HVAC Permit in Saint Paul compared with nearby Minnesota localities

LocalityPermit needed?ThresholdWhat each Minnesota schedule saysVerified
Saint PaulPermit requiredAny sizeSee schedule
MinneapolisPermit requiredAny sizeExisting residential mechanical fee is tiered by scope: Level 1 misc HVAC work with no burner $84.20; the schedule has the rest

Permitting activity in Saint Paul

In 2025, Saint Paul authorized permits for 357 new residential housing units (100 single-family, 257 in multi-family buildings), valued at $100M, down from 404 the year before. That works out to about 1.2 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 306,717.

What else needs a permit in Saint Paul

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsheight of a deck or platform above grade, where it is also not attached to a structure with frost footings and does not act as a landing outside an exterior doorA deck building permit is priced from the valuation table in Sec. 33.04(a); the schedule has the rest
Electrical PermitPermit requiredAny sizeSec. 33.04(g)(4) sets a minimum permit fee of $85.00 for one-family dwelling electrical work
Fence PermitPermit requiredAny sizeSee schedule
Patio PermitIt dependsBefore roofing, enclosing or building over a patio, before any patio work in a heritage...See schedule
Plumbing PermitPermit requiredAny sizeDSI's Plumbing Application, Inspection and Fees page (last edited March 3, 2026) and Sec. 33.04(g)(7): initial permit fee $92; the schedule has the rest
Pool PermitIt dependswater capacity of an in-ground or above ground swimming pool; the prefabricated pool exemption additionally requires the pool to be no more than 24 inches deep and installed entirely above groundThe pool building permit is priced from the valuation table in Sec. 33.04(a); the schedule has the rest
Roof Replacement PermitPermit requiredAny sizeA reroof is a general building permit priced on valuation under Sec. 33.04(a); the schedule has the rest
Shed PermitIt dependsfloor area of a one-story detached accessory structure used as a tool or storage shed, playhouse or similar useA shed over 200 square feet is a general building permit priced from the valuation table in Sec. 33.04(a) of the Legislative Code; the schedule has the rest
Solar PermitPermit requiredAny sizeElectrical, Sec. 33.04(g)(4)k "Renewable energy (solar, wind, etc.)": $151.00 for 0 to 20 kW systems, $363.00 for 21 to 40 kW systems; the schedule has the rest

Frequently asked questions

Do you need an HVAC permit in Saint Paul?
Yes, before installing, altering, reconstructing or repairing any heating, ventilating, cooling or refrigeration equipment, including a furnace or air conditioner changeout. If you are unsure how that applies to your project, call the permit office at 651-266-8989 before you start.
How much does an HVAC permit cost in Saint Paul?
The fee wording from the official schedule is in the cost table on this page, as we read it on 15 Aug 2026. For the figure on your own project, call the permit office at 651-266-8989.
Where do you apply for an HVAC permit in Saint Paul?
You can apply through the Saint Paul permit portal or contact the City of Saint Paul Department of Safety and Inspections (DSI) directly. The links are listed on this page.
Can a homeowner pull an HVAC permit themselves in Saint Paul?
Under Minnesota law (Minn. Stat. 326B.805, subd. 6, clause (3)): Minnesota requires a license to work as a residential building contractor, remodeler, or roofer, but it exempts an owner who builds or improves their own residential real estate if the owner occupies it, or will occupy it, for residential purposes, or keeps it as a rental once the work is done. That exemption lets a homeowner act as their own contractor and pull permits without holding a contractor's license. The exemption does not apply to an owner building or improving property for resale or speculation, and the law presumes speculation if the owner builds or improves more than one property within any 24-month period, unless each property is retained for rental. This is a licensing exemption only; it does not remove the separate requirement to obtain a building permit for the work itself. Confirm how Saint Paul applies this before you apply.

From the Library

HVAC Permit in other Minnesota localities

Everything above, sourced

How this HVAC permit page for Saint Paul was verified. 2 official sources: stpaul.gov, library.municode.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Saint Paul Department of Safety and Inspections (DSI). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project