Electrical Permit in Saint Paul, Minnesota
Permit required
Yes, a permit is required
Before any new electrical installation in construction, remodeling, replacement or repair, other than minor repair work as defined by the state.
By Mario Bailey, verified against official sources
Quick answer
Saint Paul issues and inspects its own electrical permits, which is the exception rather than the rule in Minnesota: Minn. Stat. 326B.36 subd. 1 sends electrical inspection to the state commissioner "Except where any political subdivision has by ordinance provided for electrical inspection similar to that herein provided," and Saint Paul has done exactly that in Sec. 33.03(d) of its Legislative Code. So a Saint Paul homeowner applies to DSI, not to the Department of Labor and Industry, and DSI's own Electrical Inspection Department at 651-266-9003 does the inspection. The only carve out is minor repair work as defined by the state, meaning the adjustment or replacement of worn or defective parts, which covers essentially no household project. The city enforces the 2023 National Electrical Code on all permits obtained on or after July 1, 2023, and a homesteading owner occupant may pull a residential electrical permit with a homeowner's affidavit.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before any new electrical installation in construction, remodeling, replacement or repair, other than minor repair work as defined by the state.
What an electrical permit costs in Saint Paul
How to apply in Saint Paul
In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Saint Paul Department of Safety and Inspections (DSI) sets the exact checklist for Saint Paul.
Where to apply in Saint Paul:
City of Saint Paul Department of Safety and Inspections (DSI)
- Department of Safety and Inspections, 375 Jackson Street, Suite 220, Saint Paul, MN 55101-1806
- Phone: 651-266-8989
- Email: DSI-BuildingPlanReview@ci.stpaul.mn.us
Inspections and closing out your permit
Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Saint Paul permit portal or by phone at 651-266-8989.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Saint Paul
- Confirm the requirement. Yes, a permit is required. Usually needed: Before any new electrical installation in construction, remodeling, replacement or repair, other than minor repair work as defined by the state.
- Budget the fee. Sec. 33.04(g)(4) sets a minimum permit fee of $85.00 for one-family dwelling electrical work. Line items: new service, change of service, temporary service, or addition, alteration or repair on primary or secondary service up to 600v is $85.00; new circuits and feeder additions, alterations or repairs up to 600v are $15.00 each; electric space heating is $22.00 for 0 to 4,000 watts and $31.00 for 4,001 watts and up; swimming pools are $85.00 plus circuit charge; renewable energy is $151.00 for 0 to 20 kW. Where the fee cannot be determined from the schedule it is 1 percent of the total valuation with an $85.00 minimum. Sec. 33.04 was last amended by Ord 25-41 effective 8-6-25. DSI's per-page tables show a $1.00 minimum state surcharge. Official fee schedule.
- Apply. In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Saint Paul permit portal.
- Keep the office details handy. City of Saint Paul Department of Safety and Inspections (DSI). Phone: 651-266-8989. Address: Department of Safety and Inspections, 375 Jackson Street, Suite 220, Saint Paul, MN 55101-1806.
- Plan for inspections. Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in Saint Paul?
- Saint Paul issues and inspects its own electrical permits, which is the exception rather than the rule in Minnesota: Minn. Stat. 326B.36 subd. 1 sends electrical inspection to the state commissioner "Except where any political subdivision has by ordinance provided for electrical inspection similar to that herein provided," and Saint Paul has done exactly that in Sec. 33.03(d) of its Legislative Code. So a Saint Paul homeowner applies to DSI, not to the Department of Labor and Industry, and DSI's own Electrical Inspection Department at 651-266-9003 does the inspection. The only carve out is minor repair work as defined by the state, meaning the adjustment or replacement of worn or defective parts, which covers essentially no household project. The city enforces the 2023 National Electrical Code on all permits obtained on or after July 1, 2023, and a homesteading owner occupant may pull a residential electrical permit with a homeowner's affidavit. Always confirm with the City of Saint Paul Department of Safety and Inspections (DSI) before starting.
- How much does an electrical permit cost in Saint Paul?
- Sec. 33.04(g)(4) sets a minimum permit fee of $85.00 for one-family dwelling electrical work. Line items: new service, change of service, temporary service, or addition, alteration or repair on primary or secondary service up to 600v is $85.00; new circuits and feeder additions, alterations or repairs up to 600v are $15.00 each; electric space heating is $22.00 for 0 to 4,000 watts and $31.00 for 4,001 watts and up; swimming pools are $85.00 plus circuit charge; renewable energy is $151.00 for 0 to 20 kW. Where the fee cannot be determined from the schedule it is 1 percent of the total valuation with an $85.00 minimum. Sec. 33.04 was last amended by Ord 25-41 effective 8-6-25. DSI's per-page tables show a $1.00 minimum state surcharge. See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in Saint Paul?
- You can apply through the Saint Paul permit portal or contact the City of Saint Paul Department of Safety and Inspections (DSI) directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in Saint Paul?
- Under Minnesota law (Minn. Stat. 326B.805, subd. 6, clause (3)): Minnesota requires a license to work as a residential building contractor, remodeler, or roofer, but it exempts an owner who builds or improves their own residential real estate if the owner occupies it, or will occupy it, for residential purposes, or keeps it as a rental once the work is done. That exemption lets a homeowner act as their own contractor and pull permits without holding a contractor's license. The exemption does not apply to an owner building or improving property for resale or speculation, and the law presumes speculation if the owner builds or improves more than one property within any 24-month period, unless each property is retained for rental. This is a licensing exemption only; it does not remove the separate requirement to obtain a building permit for the work itself. Confirm how Saint Paul applies this before you apply.
From the Library
What else needs a permit in Saint Paul
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | height of a deck or platform above grade, where it is also not attached to a structure with frost footings and does not act as a landing outside an exterior door | A deck building permit is priced from the valuation table in Sec. |
| Fence Permit | Permit required | Not specified | Saint Paul Legislative Code Sec. |
| HVAC Permit | Permit required | Not specified | Warm air, Sec. |
| Patio Permit | It depends | Not specified | There is no patio line item in the fee schedule. |
| Plumbing Permit | Permit required | Not specified | DSI's Plumbing Application, Inspection and Fees page (last edited March 3, 2026) and Sec. |
| Pool Permit | It depends | water capacity of an in-ground or above ground swimming pool; the prefabricated pool exemption additionally requires the pool to be no more than 24 inches deep and installed entirely above ground | The pool building permit is priced from the valuation table in Sec. |
| Roof Replacement Permit | Permit required | Not specified | A reroof is a general building permit priced on valuation under Sec. |
| Shed Permit | It depends | floor area of a one-story detached accessory structure used as a tool or storage shed, playhouse or similar use | A shed over 200 square feet is a general building permit priced from the valuation table... |
| Solar Permit | Permit required | Not specified | Two fees. |
Electrical Permit in other Minnesota localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Saint Paul documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with City of Saint Paul Department of Safety and Inspections (DSI). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Minnesota localities