Shed Permit in Minneapolis, Minnesota

It depends

Sometimes, depending on the project

When building a shed that is 200 sq ft or larger or more than one story

Confirmed on official page Verified

Issued byCity of Minneapolis Community Planning and Economic Development

By Mario Bailey, verified against official sources

Quick answer

One-story tool and storage sheds under 200 square feet are exempt from a building permit in Minneapolis. Sheds at or above 200 square feet or more than one story require a building permit. Contact CPED at 612-673-3000 for project-specific requirements.

Typical threshold: one-story tool and storage sheds under 200 sq ft are exempt from a permit; sheds 200 sq ft or larger or more than one story require a permit.

Diagram of the 200 sq ft footprint area threshold for a shed permit in Minneapolis, Minnesota
Threshold illustrated: 200 sq ft. Whether Minneapolis requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-06-18.

Who is pulling this permit?

Hire it out

Sponsored

If a contractor builds or places your shed, they usually handle any required permit. Compare a few bids before you commit.

Compare contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

When building a shed that is 200 sq ft or larger or more than one story

What a shed permit costs in Minneapolis

Line item
shed permitBy formulaOne-story sheds under 200 sq ft need no permit or fee; larger sheds bill as a standard building permit valued by cost of work, minimum $84.20 plus 65% plan review and 0.05% state surcharge.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Minneapolis compares in Minnesota

Closest shed permit thresholds outside Minnesota

Jurisdictions we cover whose limit sits nearest Minneapolis's 200 sq ft.

  • Austin, Texas, one-story detached accessory structures used as tool or storage sheds with floor area no greater than 200 sq ft and no more than 15 ft in height and no plumbing and not in a floodplain are exempt
  • Baton Rouge, Louisiana, floor area of a detached accessory structure
  • Bellevue, Washington, detached storage sheds playhouses or gazebos with a floor area of 200 square feet or less do not require a building permit; structures over 200 square feet require a permit
  • Clark County, Nevada, sheds over 200 sq ft require a building permit; storage sheds 200 sq ft or under may be exempt under Building Administrative Code Section 22.02.190

How to apply in Minneapolis

In Minneapolis, a residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • For Minneapolis, a written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • For Minneapolis, a scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. City of Minneapolis Community Planning and Economic Development sets the exact checklist for Minneapolis.

Where to apply in Minneapolis:

City of Minneapolis Community Planning and Economic Development

Shed Permit in Minneapolis compared with nearby Minnesota localities

LocalityPermit needed?ThresholdWhat each Minnesota schedule saysVerified
MinneapolisIt dependsone-story tool and storage sheds under 200 sq ft are exempt from a permit; sheds 200 sq ft or larger or more than one story require a permitOne-story sheds under 200 sq ft need no permit or fee
Saint PaulIt dependsfloor area of a one-story detached accessory structure used as a tool or storage shed, playhouse or similar useA shed over 200 square feet is a general building permit priced from the valuation table...

Inspections and closing out your permit

In Minneapolis, a permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection in Minneapolis: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection in Minneapolis: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection in Minneapolis: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. In Minneapolis: for a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Minneapolis permit portal or by phone at 612-673-3000.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Minneapolis

In 2024, Minneapolis authorized permits for 452 new residential housing units (65 single-family, 387 in multi-family buildings), valued at $151M, down from 1,528 the year before. That works out to about 1 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 433,111.

About Minneapolis

Minneapolis has about 203,217 housing units. The median home is valued at $345,600, against a median household income of $80,269. About 48% of homes are owner-occupied, and the typical home was built around 1950.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a shed permit in Minneapolis?
One-story tool and storage sheds under 200 square feet are exempt from a building permit in Minneapolis. Sheds at or above 200 square feet or more than one story require a building permit. Contact CPED at 612-673-3000 for project-specific requirements. One-story tool and storage sheds under 200 sq ft are exempt from a permit; sheds 200 sq ft or larger or more than one story require a permit. Always confirm with the office before starting.
How much does a shed permit cost in Minneapolis?
One-story sheds under 200 sq ft need no permit or fee; larger sheds bill as a standard building permit valued by cost of work, minimum $84.20 plus 65% plan review and 0.05% state surcharge. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Minneapolis?
You can apply through the Minneapolis permit portal or contact the City of Minneapolis Community Planning and Economic Development directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Minneapolis?
Under Minnesota law (Minn. Stat. 326B.805, subd. 6, clause (3)): Minnesota requires a license to work as a residential building contractor, remodeler, or roofer, but it exempts an owner who builds or improves their own residential real estate if the owner occupies it, or will occupy it, for residential purposes, or keeps it as a rental once the work is done. That exemption lets a homeowner act as their own contractor and pull permits without holding a contractor's license. The exemption does not apply to an owner building or improving property for resale or speculation, and the law presumes speculation if the owner builds or improves more than one property within any 24-month period, unless each property is retained for rental. This is a licensing exemption only; it does not remove the separate requirement to obtain a building permit for the work itself. Confirm how Minneapolis applies this before you apply.

From the Library

What else needs a permit in Minneapolis

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsfreestanding decks less than 30 in above grade that are not attached with frost footings and do not serve the main entrance are exempt; all other decks require a permitBilled as a standard building permit valued by cost of work once the deck exceeds 30...
Electrical PermitPermit requiredNot specifiedNo city fee
Fence PermitIt dependsfences no more than 7 feet high are exempt from a permit; fences over 7 feet require a building permitNo fee for fences 7 feet or under since no permit is required
HVAC PermitPermit requiredNot specifiedExisting residential mechanical fee is tiered by scope: Level 1 misc HVAC work with no...
Patio PermitIt dependsfreestanding platforms less than 30 in above grade that are not attached with frost footings and do not serve the main entrance are exempt; others may require a permitNo permit fee
Plumbing PermitPermit requiredNot specifiedMinimum plumbing permit fee is $85.20 including the $1 state surcharge, with per-item...
Pool PermitPermit requiredNot specifiedNo separate pool schedule
Roof Replacement PermitPermit requiredNot specifiedBilled as a standard building permit valued by cost of work, minimum $84.20 plus 65%...
Solar PermitPermit requiredNot specifiedThe building permit portion uses the valuation-based schedule, minimum $84.20 plus 65%...

Shed Permit in other Minnesota localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Minneapolis documents; the office above sets the local rules.

How this shed permit page for Minneapolis was verified. 2 official sources: minneapolismn.gov, minneapolismn.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Minneapolis Community Planning and Economic Development. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Shed Permit requirements across Minnesota localities

Shed permit rules nationwide

It depends
Get quotes