It depends

Sometimes, depending on the project

Before building a fence in unincorporated Alameda County that is taller than 7 feet in light materials, or taller than 5 feet 9 inches in concrete, masonry, or similar heavy materials

Quick answer

Alameda County's adopted building ordinance exempts fences from a building permit only up to a height limit that depends on the material: 7 feet for light materials and 5 feet 9 inches for concrete, masonry, or similar heavy materials. A taller fence needs a building permit from the Public Works Agency Building Inspection Department. The county warns separately that approval from other county agencies, such as the Planning Department, Environmental Health, the Fire Department, and Road Encroachment, may still be required even when the work is exempt from a building permit. These rules cover the unincorporated county only: the county's own Cities page states the incorporated cities are Alameda, Albany, Berkeley, Dublin, Emeryville, Fremont, Hayward, Livermore, Newark, Oakland, Piedmont, Pleasanton, San Leandro, and Union City, and each runs its own building department, while the Building Inspection Department serves unincorporated communities including Ashland, Castlewood, Castro Valley, Cherryland, Fairview, Happy Valley, Hillcrest Knolls, San Lorenzo, and Sunol.

Diagram of the 7 ft fence height threshold for a fence permit in Alameda County, California
Threshold illustrated: 7 ft. Whether Alameda County requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-08-15.
Typical threshold
Permit exemption height limit: 7 feet for fences of light materials, 5 feet 9 inches for fences of concrete, masonry, or similar heavy materials
Issued by
Alameda County Public Works Agency, Building Inspection Department
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Fence installers usually handle any required permit as part of the job. Compare a few bids before you commit.

Compare fence installer quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What a fence permit costs in Alameda County

Fee basis
Project valuation
Fee schedule in force
Official scheduleRead .

No fence line item appears in the Building Inspection Department Service Fee Schedule (Schedule A, effective July 1, 2024).

A fence permit is priced from construction valuation using the Schedule A building permit fee table, which starts at a '$140.00 minimum permit issuance fee' for total valuation of $1.00 to $1,000.00, plus a $20.00 permit processing fee for a single permit, plus a stormwater fee of 4% of building permit fees.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Alameda County compares in California

Across the California jurisdictions we have verified, the same threshold runs from 6 to 7, so a project that is exempt here may still need a permit one county over.

JurisdictionPermit needed?Threshold
Alameda Countythis pageIt dependsPermit exemption height limit: 7 feet for fences of light materials, 5 feet 9 inches for fences of concrete, masonry, or similar heavy materials
Contra Costa CountyIt dependsheight of a fence, with concrete and masonry walls treated as walls rather than fences
Fresno CountyIt dependsFences not over 7 feet high are on the county's published list of work exempt from a building permit
Los Angeles CountyIt dependsheight of a fence or freestanding block wall measured from the lowest adjacent grade; a masonry or concrete fence must also be set back from a public way at least a distance equal to its height to stay exempt
Orange CountyIt dependsFences and freestanding walls over six feet in height require a building permit; fences not over six feet are exempt unless a permit was required as a condition of project approval
Riverside CountyIt dependsFences 7 feet or less in height are exempt from a building permit, except block walls, which are exempt only up to 4 feet in height
San Diego CountyIt dependsFences and freestanding masonry walls over 6 feet in height need a building permit; open fences up to 8 feet are also exempt if the uppermost two feet is only barbed or razor wire on angled supports.

How to apply in Alameda County

General guide, not specific to this office

What a fence permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a fence permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Alameda County Public Works Agency, Building Inspection Department

  • 399 Elmhurst Street, Room 141, Hayward, CA 94544-1395
  • Phone: 510-670-5440
  • Email: permitbid@acpwa.org

Permitting activity in Alameda County

In 2025, Alameda County authorized permits for 2,778 new residential housing units (1,117 single-family, 1,661 in multi-family buildings), valued at $829M, up from 1,743 the year before. That works out to about 1.7 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 1,636,630.

What else needs a permit in Alameda County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsHeight of a raised deck above adjacent grade at which the building permit exemption stops, and only where the deck is not over a basement or story below and is not part of an accessible routeSee schedule
Electrical PermitPermit requiredAny sizeSee schedule
HVAC PermitPermit requiredAny sizeSee schedule
Patio PermitIt dependsTotal area of each sunshade structure, including any roofed area, at which the building permit exemption stops; the exemption also requires an average height of not more than 10 feetSee schedule
Plumbing PermitPermit requiredAny sizeSee schedule
Pool PermitIt dependsDepth of a prefabricated pool at which the building permit exemption stops; the exemption also requires the pool to hold no more than 5,000 gallons and to be installed entirely above groundA pool permit is priced from construction valuation on the Schedule A table; the schedule has the rest
Roof Replacement PermitIt dependsAggregate roof area repaired on a previously permitted roof, at which the building permit exemption stopsA re-roof permit is priced from construction valuation on the Schedule A building permit fee table; the schedule has the rest
Shed PermitIt dependsFloor area of a one-story detached tool or storage shed accessory to a house, at which the building permit exemption stopsA shed permit is priced from construction valuation using the Schedule A table and the Schedule B square-foot valuation table; the schedule has the rest
Solar PermitPermit requiredAny sizeSee schedule

Frequently asked questions

Do you need a fence permit in Alameda County?
It depends on the project. Permit exemption height limit: 7 feet for fences of light materials, 5 feet 9 inches for fences of concrete, masonry, or similar heavy materials. If you are unsure how that applies to your project, call the Alameda County Public Works Agency, Building Inspection Department at 510-670-5440 before you start.
How much does a fence permit cost in Alameda County?
The fee wording from the official schedule is in the cost table on this page, as we read it on 15 Aug 2026. For the figure on your own project, call the Alameda County Public Works Agency, Building Inspection Department at 510-670-5440.
Where do you apply for a fence permit in Alameda County?
You can apply through the Alameda County permit portal or contact the Alameda County Public Works Agency, Building Inspection Department directly. The links are listed on this page.
Can a homeowner pull a fence permit themselves in Alameda County?
Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner from contractor licensing under section 7044 when they personally perform all the work on their own property, or any work they do not perform themselves is done by their own employees paid only wages, and none of the improvements are intended or offered for sale. It also exempts an owner who directly contracts with licensed contractors for each trade, as long as no more than four of the single-family residential structures involved are intended or offered for sale in a calendar year; this route does not apply if the owner instead contracts with a general contractor for the construction. A homeowner may also improve their own principal residence without a license, as long as the work is done before any sale, they have actually resided there for the 12 months before completion, and they have not used this exemption on more than two structures more than once in any three-year period. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a civil penalty of up to $500. Confirm how Alameda County applies this before you apply.

From the Library

Fence Permit in other California localities

Everything above, sourced

How this fence permit page for Alameda County was verified. 2 official sources: acpwa.org, acgovt.sharepoint.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Alameda County Public Works Agency, Building Inspection Department. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

It depends
Check my project