Ohio / Franklin County

Solar Permit in Franklin County, Ohio

Permit required

Yes, a permit is required

Before installing a roof mounted or ground mounted photovoltaic system on a residential property.

From an official source Verified Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department

By Mario Bailey, verified against official sources

Quick answer

Franklin County requires a permit for any PV system installation, with no size floor. The county folds three approvals into one submission: the PV Systems Form acts as a building permit, an electrical permit and a Certificate of Zoning Compliance at once, and the three underlying fees are charged separately on the same application. Roof mounted systems are only accepted on lightweight roof types such as composition, lightweight masonry or metal. Two inspections follow, a rough inspection during the build and a final on completion.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a roof mounted or ground mounted photovoltaic system on a residential property.

What a solar permit costs in Franklin County

Line item
solar permitBy formulaSummary of PV Systems Form Fees, published by Franklin County EDP: Certificate of Zoning Compliance, Residential, 'Roof Mounted $25.00' and 'Ground Mounted $75.00' (Commercial $275.00); Building Permit '$120.00' with 'Plus: Each 100 sq. ft. thereafter $10.00'; 'Electric Permit $60.00'; 'Plan Review Fee $50.00'. The sheet adds: 'Note: There is a 1% building permit surcharge as required by the State of Ohio.' It also states 'Fees are not being raised in order to accommodate PV Systems Permits.'.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Franklin County compares in Ohio

No Ohio jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
CincinnatiPermit requiredBuilding permit fees are based on project valuation under the Department of...
ClevelandPermit requiredCleveland's Solar Panel Guide publishes a residential table: residential...
ColumbusPermit requiredRooftop solar uses the standard electrical permit fee with no separate...
Franklin Countythis pagePermit requiredSummary of PV Systems Form Fees, published by Franklin County EDP: Certificate...

How to apply in Franklin County

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department sets the exact checklist for Franklin County.

Where to apply in Franklin County:

Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department

  • Franklin County Building Department, 142 S. Front St., Columbus, OH 43215 (the Economic Development and Planning Department offices, where zoning applications are filed, are at 150 South Front Street, FSL Suite 10, Columbus, OH 43215-7104)
  • Phone: 614-525-3166
  • Email: building@franklincountyohio.gov

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Franklin County permit portal or by phone at 614-525-3166.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Franklin County?
Franklin County requires a permit for any PV system installation, with no size floor. The county folds three approvals into one submission: the PV Systems Form acts as a building permit, an electrical permit and a Certificate of Zoning Compliance at once, and the three underlying fees are charged separately on the same application. Roof mounted systems are only accepted on lightweight roof types such as composition, lightweight masonry or metal. Two inspections follow, a rough inspection during the build and a final on completion. Always confirm with the Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department before starting.
How much does a solar permit cost in Franklin County?
Summary of PV Systems Form Fees, published by Franklin County EDP: Certificate of Zoning Compliance, Residential, 'Roof Mounted $25.00' and 'Ground Mounted $75.00' (Commercial $275.00); Building Permit '$120.00' with 'Plus: Each 100 sq. ft. thereafter $10.00'; 'Electric Permit $60.00'; 'Plan Review Fee $50.00'. The sheet adds: 'Note: There is a 1% building permit surcharge as required by the State of Ohio.' It also states 'Fees are not being raised in order to accommodate PV Systems Permits.'. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Franklin County?
You can apply through the Franklin County permit portal or contact the Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Franklin County?
Under Ohio law (OAC 4101:8-1-01 Section 105.1; R.C. 3791.04(A)(1)(b); R.C. Chapter 4740): Ohio has no statewide general contractor license, so the Residential Code of Ohio names the property owner directly as an authorized permit applicant: an owner or authorized agent who intends to construct, alter, repair, or change the occupancy of a residential building must first make application to the local certified building department and obtain approval, meaning a homeowner may pull their own permit and act as their own contractor. Certain specialty trades, HVAC, refrigeration, and hydronics contractors, are separately licensed statewide under R.C. Chapter 4740, and no homeowner exemption from that licensing requirement could be found in the chapter's text. In a county, township, or municipality with no residential building department certified by the state Board of Building Standards, R.C. 3791.04(A)(1)(b) and the Residential Code of Ohio's administrative rule both say the owner is not required to submit construction documents, seek approval, request inspections, or obtain a certificate of occupancy at all, which removes the state permitting framework, and with it the owner-builder question, in those jurisdictions. Confirm how Franklin County applies this before you apply.

From the Library

What else needs a permit in Franklin County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Electrical PermitPermit requiredNot specifiedConfirm the current fee with the City of Columbus before relying on county figures.
Fence PermitPermit requiredNot specifiedFranklin County Economic Development and Planning Department Fee Schedule, 'Effective Jan.
HVAC PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Patio PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Plumbing PermitPermit requiredNot specifiedFranklin County Public Health publishes no figure on its plumbing page beyond 'The costs...
Pool PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Roof Replacement PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Shed PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.

Solar Permit in other Ohio localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Franklin County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page