Permit required

Yes, a permit is required

Before any electrical installation, alteration or service change, including the bonding work on a pool, spa or hot tub.

From an official source Verified Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department

By Mario Bailey, verified against official sources

Quick answer

An electrical permit is required, and it is a separate permit from the structural building permit, but the issuing body has changed. Franklin County's own Online Permit Center now tells residents that electrical permitting goes through the City of Columbus at 614-645-7433, alongside a matching note that plumbing goes through Franklin County Public Health. The county's older published pages still describe an in-house Franklin County electrical permit taken out by a contractor registered with the county or by a homeowner on affidavit. Whichever office issues it, a valid license is required to perform electrical work even though no license is needed to pull a structural building permit.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before any electrical installation, alteration or service change, including the bonding work on a pool, spa or hot tub.

What an electrical permit costs in Franklin County

Line item
electrical permitBy formulaConfirm the current fee with the City of Columbus before relying on county figures. The Franklin County EDP Fee Schedule, 'Effective Jan. 1, 2014', still lists Building Permit Fees: 'Electric Permit, Each outlet $1.50', 'Each amp $0.50', 'Minimum fee $60.00', 'Registration Fee $50.00', footnote '* Does not include 1% State Building Permit Surcharge'. The county's PV fee sheet lists 'Electric Permit $60.00'.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Franklin County compares in Ohio

No Ohio jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
CincinnatiIt dependsThe City of Cincinnati fee schedule carries no electrical line item because...
ClevelandIt dependsElectrical Wiring and Equipment fee schedule effective January 2, 2014: "the...
ColumbusPermit requiredStandard electrical trade permit is $275 with 2 inspections, dropping to $140...
Franklin Countythis pagePermit requiredConfirm the current fee with the City of Columbus before relying on county...

How to apply in Franklin County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department sets the exact checklist for Franklin County.

Where to apply in Franklin County:

Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department

  • Franklin County Building Department, 142 S. Front St., Columbus, OH 43215 (the Economic Development and Planning Department offices, where zoning applications are filed, are at 150 South Front Street, FSL Suite 10, Columbus, OH 43215-7104)
  • Phone: 614-525-3166
  • Email: building@franklincountyohio.gov

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Franklin County permit portal or by phone at 614-525-3166.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in Franklin County?
An electrical permit is required, and it is a separate permit from the structural building permit, but the issuing body has changed. Franklin County's own Online Permit Center now tells residents that electrical permitting goes through the City of Columbus at 614-645-7433, alongside a matching note that plumbing goes through Franklin County Public Health. The county's older published pages still describe an in-house Franklin County electrical permit taken out by a contractor registered with the county or by a homeowner on affidavit. Whichever office issues it, a valid license is required to perform electrical work even though no license is needed to pull a structural building permit. Always confirm with the Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department before starting.
How much does an electrical permit cost in Franklin County?
Confirm the current fee with the City of Columbus before relying on county figures. The Franklin County EDP Fee Schedule, 'Effective Jan. 1, 2014', still lists Building Permit Fees: 'Electric Permit, Each outlet $1.50', 'Each amp $0.50', 'Minimum fee $60.00', 'Registration Fee $50.00', footnote '* Does not include 1% State Building Permit Surcharge'. The county's PV fee sheet lists 'Electric Permit $60.00'. See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Franklin County?
You can apply through the Franklin County permit portal or contact the Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Franklin County?
Under Ohio law (OAC 4101:8-1-01 Section 105.1; R.C. 3791.04(A)(1)(b); R.C. Chapter 4740): Ohio has no statewide general contractor license, so the Residential Code of Ohio names the property owner directly as an authorized permit applicant: an owner or authorized agent who intends to construct, alter, repair, or change the occupancy of a residential building must first make application to the local certified building department and obtain approval, meaning a homeowner may pull their own permit and act as their own contractor. Certain specialty trades, HVAC, refrigeration, and hydronics contractors, are separately licensed statewide under R.C. Chapter 4740, and no homeowner exemption from that licensing requirement could be found in the chapter's text. In a county, township, or municipality with no residential building department certified by the state Board of Building Standards, R.C. 3791.04(A)(1)(b) and the Residential Code of Ohio's administrative rule both say the owner is not required to submit construction documents, seek approval, request inspections, or obtain a certificate of occupancy at all, which removes the state permitting framework, and with it the owner-builder question, in those jurisdictions. Confirm how Franklin County applies this before you apply.

From the Library

What else needs a permit in Franklin County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Fence PermitPermit requiredNot specifiedFranklin County Economic Development and Planning Department Fee Schedule, 'Effective Jan.
HVAC PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Patio PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Plumbing PermitPermit requiredNot specifiedFranklin County Public Health publishes no figure on its plumbing page beyond 'The costs...
Pool PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Roof Replacement PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Shed PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Solar PermitPermit requiredNot specifiedSummary of PV Systems Form Fees, published by Franklin County EDP: Certificate of Zoning...

Electrical Permit in other Ohio localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Franklin County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across Ohio localities

Permit required
Get quotes