Yes, a permit is required

Before building a deck, including a deck attached to the house or one serving a required exit door.

From an official source Verified Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department

By Mario Bailey, verified against official sources

Quick answer

Franklin County lists 'Building Deck' outright among the activities that require a building permit, and its Residential Zoning Compliance application separately covers a patio or deck, so a deck project needs both a county building permit and a zoning approval. The Residential Code of Ohio does carve out one narrow case: a deck is exempt from building department approval only if it is no larger than 200 square feet, no more than 30 inches above grade at any point, not attached to the dwelling, and does not serve the required exit door. Even a deck that meets all four conditions still needs the zoning approval, so a permit of some kind is required either way.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before building a deck, including a deck attached to the house or one serving a required exit door.

What a deck permit costs in Franklin County

Line item
deck permitBy formulaFranklin County EDP Fee Schedule, 'Effective Jan. 1, 2014', Building Permit Fees: 'Decks, Under 1000 sq ft $75.00', '1000 sq ft and over $120.00', 'Plus: Base fee + $10 per each 100 sq ft $10.00'; footnote '* Does not include 1% State Building Permit Surcharge'. Zoning Fees: 'Certificate of Zoning Compliance, Residential $75.00'.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Franklin County compares in Ohio

No Ohio jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
CincinnatiPermit requiredFee Schedule effective July 1, 2026: building permit fees run off project...
ClevelandPermit requiredThe General Fee Schedule effective January 2, 2014 has no deck line item.
ColumbusPermit requiredFlat $350 fee for a 1-2-3 family deck permit covering three inspections, per...
Franklin Countythis pagePermit requiredFranklin County EDP Fee Schedule, 'Effective Jan.

How to apply in Franklin County

A residential deck permit application is a set of construction documents that show what will be built and prove it meets the IRC deck provisions. In practice that means a scaled site plan locating the deck and its setbacks, plus deck plans and structural details covering the footings, posts, beams, joists, ledger, guards, and stairs.

What most deck permit applications include:

  • A permit application identifying the work, the deck's size (square footage), and whether electrical work such as lights or receptacles is included, submitted for plan review before construction begins (IRC R106).
  • A scaled site plan (for example 1/4 inch to 1 foot) showing the new deck's location relative to the house, its overall length and width, and dimensioned distances from the deck to all property lines and other structures so required setbacks can be verified (IRC R106.1.1).
  • A deck plan drawn to scale showing overall dimensions and the framing layout: joist size, spacing, span, and species; beam size and span; post size and height; and footing or pier size and depth (IRC R507.4 posts, R507.5 beams, R507.6 joists, R507.3 footings).
  • A section or side elevation with connection details showing the ledger attachment to the house band joist with flashing, the fastener or bolt schedule, joist hangers, post-to-beam and post-to-footing connections, and the required lateral load connection (IRC R507.9 ledger connection, R507.9.2 lateral connection, R507.2.4 flashing).
  • Footing sizing derived from tributary area, the soil bearing value, and design loads per IRC Table R507.3.1, with footings shown bearing on undisturbed soil at the frost depth required by the jurisdiction (IRC R507.3).
  • Details for the guards required where the walking surface is more than 30 inches above grade, and for the stairs and handrails, showing guard height and opening limits, stair riser and tread dimensions, and handrail location (IRC R312 guards, R311.7 stairs and handrails).
  • For designs that fall outside the prescriptive R507 tables (for example multi-story or stacked decks, or a ledger attached to a cantilever), engineered and stamped structural plans are submitted in place of the prescriptive details (IRC R507.1 and R301).

General submittal guidance from IRC R106.1.1 (construction documents) and IRC R507 (exterior decks), 2021 IRC. Source. Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department sets the exact checklist for Franklin County.

Where to apply in Franklin County:

Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department

  • Franklin County Building Department, 142 S. Front St., Columbus, OH 43215 (the Economic Development and Planning Department offices, where zoning applications are filed, are at 150 South Front Street, FSL Suite 10, Columbus, OH 43215-7104)
  • Phone: 614-525-3166
  • Email: building@franklincountyohio.gov

Inspections and closing out your permit

Deck work is inspected in sequence as it is built: the footings before concrete is placed, the framing before the decking boards go down, and a final inspection once the deck is complete. Each stage checks the items that would be hidden or unsafe if missed.

  1. Footing or pier inspection: after the holes are dug and any forms or reinforcing are set but before concrete is placed, the inspector checks footing depth and diameter, a flat undisturbed bearing surface, and that the holes are free of water (IRC R109.1.1 foundation inspection; R507.3 footings).
  2. Framing inspection: after the deck is framed but before the decking conceals it, the inspector verifies the ledger attachment and its flashing, the fastener and bolt schedule, joist hangers and metal connectors, post-to-beam and post-to-footing connections, and the lateral load connection; call it before decking is installed (IRC R109.1.4 frame inspection; R507.9 ledger and flashing).
  3. Final inspection: after the deck is complete and before it is used, the inspector confirms guard height and opening limits (a 4 inch sphere must not pass, 4 3/8 inch at stairs), stair riser and tread dimensions, handrail height and graspability where there are 4 or more risers, stair landings, and required stair lighting (IRC R109.1.6 final inspection; R312 guards, R311.7 stairs and handrails).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Franklin County permit portal or by phone at 614-525-3166.

Inspection sequence from IRC R109 (inspections: R109.1.1 footing before concrete, R109.1.4 frame, R109.1.6 final), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a deck permit in Franklin County?
Franklin County lists 'Building Deck' outright among the activities that require a building permit, and its Residential Zoning Compliance application separately covers a patio or deck, so a deck project needs both a county building permit and a zoning approval. The Residential Code of Ohio does carve out one narrow case: a deck is exempt from building department approval only if it is no larger than 200 square feet, no more than 30 inches above grade at any point, not attached to the dwelling, and does not serve the required exit door. Even a deck that meets all four conditions still needs the zoning approval, so a permit of some kind is required either way. Always confirm with the Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department before starting.
How much does a deck permit cost in Franklin County?
Franklin County EDP Fee Schedule, 'Effective Jan. 1, 2014', Building Permit Fees: 'Decks, Under 1000 sq ft $75.00', '1000 sq ft and over $120.00', 'Plus: Base fee + $10 per each 100 sq ft $10.00'; footnote '* Does not include 1% State Building Permit Surcharge'. Zoning Fees: 'Certificate of Zoning Compliance, Residential $75.00'. See the official fee schedule for current amounts.
How long does a deck permit take in Franklin County?
Building permits are issued 7 to 10 days after full plan approval for properties with access to public water and sewer. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a deck permit in Franklin County?
You can apply through the Franklin County permit portal or contact the Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department directly. The links are listed on this page.
Can a homeowner pull a deck permit themselves in Franklin County?
Under Ohio law (OAC 4101:8-1-01 Section 105.1; R.C. 3791.04(A)(1)(b); R.C. Chapter 4740): Ohio has no statewide general contractor license, so the Residential Code of Ohio names the property owner directly as an authorized permit applicant: an owner or authorized agent who intends to construct, alter, repair, or change the occupancy of a residential building must first make application to the local certified building department and obtain approval, meaning a homeowner may pull their own permit and act as their own contractor. Certain specialty trades, HVAC, refrigeration, and hydronics contractors, are separately licensed statewide under R.C. Chapter 4740, and no homeowner exemption from that licensing requirement could be found in the chapter's text. In a county, township, or municipality with no residential building department certified by the state Board of Building Standards, R.C. 3791.04(A)(1)(b) and the Residential Code of Ohio's administrative rule both say the owner is not required to submit construction documents, seek approval, request inspections, or obtain a certificate of occupancy at all, which removes the state permitting framework, and with it the owner-builder question, in those jurisdictions. Confirm how Franklin County applies this before you apply.

From the Library

What else needs a permit in Franklin County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Electrical PermitPermit requiredNot specifiedConfirm the current fee with the City of Columbus before relying on county figures.
Fence PermitPermit requiredNot specifiedFranklin County Economic Development and Planning Department Fee Schedule, 'Effective Jan.
HVAC PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Patio PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Plumbing PermitPermit requiredNot specifiedFranklin County Public Health publishes no figure on its plumbing page beyond 'The costs...
Pool PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Roof Replacement PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Shed PermitPermit requiredNot specifiedFranklin County EDP Fee Schedule, 'Effective Jan.
Solar PermitPermit requiredNot specifiedSummary of PV Systems Form Fees, published by Franklin County EDP: Certificate of Zoning...

Deck Permit in other Ohio localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Franklin County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Franklin County Building Department (Division of Building), Franklin County Economic Development and Planning Department. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Deck Permit requirements across Ohio localities

Permit required
Get quotes