Ohio / Cleveland

Electrical Permit in Cleveland, Ohio

It depends

Sometimes, depending on the project

Before any electrical wiring or equipment is installed, altered or repaired, including temporary installations and new or repaired illuminated sign connections. Not needed for changing light bulbs or fuses, repairs to portable equipment such as lamps and fans, or servicing and like for like replacement of existing equipment at existing terminal connections.

From an official source Verified City of Cleveland Department of Building and Housing, Division of Construction Permitting

By Mario Bailey, verified against official sources

Quick answer

Cleveland requires a separate electrical permit, and its Electrical Permits page says permits are required for electrical work and electrical fixtures along with electrical equipment and devices, both new and temporary. Codified Ordinance 3137.05 carries the requirement and the only real carve outs: minor repair, defined as installing or replacing light bulbs or fuses and repairing portable utilization equipment, and maintenance, defined as servicing existing equipment and replacing electrical equipment with equipment of like type and capacity connected to existing terminal connections. Neither covers changes or repairs to permanent wiring or extensions of terminal connections. Contractors must be bonded, insured, licensed with the State of Ohio and registered with the City; homeowners may apply with a notarized homeowner's affidavit and do not need to be registered contractors. The permit is also the route to getting power turned on: the FAQ says an electrical permit is required, the inspector named on the permit does the inspection, and once approved the city calls the power company.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before any electrical wiring or equipment is installed, altered or repaired, including temporary installations and new or repaired illuminated sign connections. Not needed for changing light bulbs or fuses, repairs to portable equipment such as lamps and fans, or servicing and like for like replacement of existing equipment at existing terminal connections.

What an electrical permit costs in Cleveland

Line item
electrical permitBy formulaElectrical Wiring and Equipment fee schedule effective January 2, 2014: "the minimum fee for any permit shall be $50.00". New construction, additions and alterations to existing buildings are $50.00 for each 1,000 square feet or part thereof; repairs to existing electrical fixtures and/or systems are $50.00; a blanket electrical permit is $200.00 for each year for each premises. Add the 1 percent State of Ohio surcharge for 1, 2 and 3 family dwelling units. A special inspection where the work is not ready or the address is wrong costs $40.00, and an inspection outside regular working hours costs $100.00.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Cleveland compares in Ohio

No Ohio jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
CincinnatiIt dependsThe City of Cincinnati fee schedule carries no electrical line item because...
Clevelandthis pageIt dependsElectrical Wiring and Equipment fee schedule effective January 2, 2014: "the...
ColumbusPermit requiredStandard electrical trade permit is $275 with 2 inspections, dropping to $140...
Franklin CountyPermit requiredConfirm the current fee with the City of Columbus before relying on county...

How to apply in Cleveland

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Cleveland Department of Building and Housing, Division of Construction Permitting sets the exact checklist for Cleveland.

Where to apply in Cleveland:

City of Cleveland Department of Building and Housing, Division of Construction Permitting

  • Department of Building and Housing, Division of Construction Permitting, Cleveland City Hall, 601 Lakeside Ave., Room 505, Cleveland, OH 44114
  • Phone: 216.664.2910
  • Email: BHpermits@clevelandohio.gov

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Cleveland permit portal or by phone at 216.664.2910.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in Cleveland?
Cleveland requires a separate electrical permit, and its Electrical Permits page says permits are required for electrical work and electrical fixtures along with electrical equipment and devices, both new and temporary. Codified Ordinance 3137.05 carries the requirement and the only real carve outs: minor repair, defined as installing or replacing light bulbs or fuses and repairing portable utilization equipment, and maintenance, defined as servicing existing equipment and replacing electrical equipment with equipment of like type and capacity connected to existing terminal connections. Neither covers changes or repairs to permanent wiring or extensions of terminal connections. Contractors must be bonded, insured, licensed with the State of Ohio and registered with the City; homeowners may apply with a notarized homeowner's affidavit and do not need to be registered contractors. The permit is also the route to getting power turned on: the FAQ says an electrical permit is required, the inspector named on the permit does the inspection, and once approved the city calls the power company. Always confirm with the City of Cleveland Department of Building and Housing, Division of Construction Permitting before starting.
How much does an electrical permit cost in Cleveland?
Electrical Wiring and Equipment fee schedule effective January 2, 2014: "the minimum fee for any permit shall be $50.00". New construction, additions and alterations to existing buildings are $50.00 for each 1,000 square feet or part thereof; repairs to existing electrical fixtures and/or systems are $50.00; a blanket electrical permit is $200.00 for each year for each premises. Add the 1 percent State of Ohio surcharge for 1, 2 and 3 family dwelling units. A special inspection where the work is not ready or the address is wrong costs $40.00, and an inspection outside regular working hours costs $100.00. See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Cleveland?
You can apply through the Cleveland permit portal or contact the City of Cleveland Department of Building and Housing, Division of Construction Permitting directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Cleveland?
Under Ohio law (OAC 4101:8-1-01 Section 105.1; R.C. 3791.04(A)(1)(b); R.C. Chapter 4740): Ohio has no statewide general contractor license, so the Residential Code of Ohio names the property owner directly as an authorized permit applicant: an owner or authorized agent who intends to construct, alter, repair, or change the occupancy of a residential building must first make application to the local certified building department and obtain approval, meaning a homeowner may pull their own permit and act as their own contractor. Certain specialty trades, HVAC, refrigeration, and hydronics contractors, are separately licensed statewide under R.C. Chapter 4740, and no homeowner exemption from that licensing requirement could be found in the chapter's text. In a county, township, or municipality with no residential building department certified by the state Board of Building Standards, R.C. 3791.04(A)(1)(b) and the Residential Code of Ohio's administrative rule both say the owner is not required to submit construction documents, seek approval, request inspections, or obtain a certificate of occupancy at all, which removes the state permitting framework, and with it the owner-builder question, in those jurisdictions. Confirm how Cleveland applies this before you apply.

From the Library

What else needs a permit in Cleveland

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedThe General Fee Schedule effective January 2, 2014 has no deck line item.
Fence PermitIt dependsshare of an existing fence repaired or replaced within any twelve month period, where foundations and footers are unchangedGeneral Fee Schedule effective January 2, 2014, item C(2) "Fences, guardrails, or...
HVAC PermitPermit requiredNot specifiedHVAC permit fee schedule effective January 2, 2014: "One, two and three family...
Plumbing PermitIt dependsNot specifiedPlumbing Fixtures, Appliance and Piping fee schedule effective January 2, 2014: "The...
Pool PermitIt dependswater capacity of a private swimming pool; a depth of more than two feet also triggers the permitGeneral Fee Schedule effective January 2, 2014, item C(4) "Swimming pools...
Roof Replacement PermitIt dependsshare of the roof whose shingles are replaced, where the replacement is in the same materialThe General Fee Schedule effective January 2, 2014 has no roofing line item.
Shed PermitPermit requiredNot specifiedGeneral Fee Schedule effective January 2, 2014, item C(1) "Private garages, tool sheds...
Solar PermitPermit requiredNot specifiedCleveland's Solar Panel Guide publishes a residential table: residential building permit...

Electrical Permit in other Ohio localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Cleveland documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Cleveland Department of Building and Housing, Division of Construction Permitting. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across Ohio localities

It depends
Get quotes