Solar Permit in Detroit, Michigan

Permit required

Yes, a permit is required

Before installing a rooftop or ground-mounted photovoltaic system, including systems already approved for interconnection by DTE.

Confirmed on official page Verified City of Detroit Buildings, Safety Engineering and Environmental Department (BSEED)

By Mario Bailey, verified against official sources

Quick answer

The City's Detroit Solar Toolkit FAQ states that a mechanical permit is not needed for rooftop panels but an electrical permit is one of the requirements, and that DTE interconnection approval does not replace Detroit permits. The BSEED fee schedule backs this up with a dedicated Part E, Renewable Energy Installations, which applies to all conductors and equipment installed to use solar, wind and fuel cells, and the C4 Electrical Permit Application carries the same Part E line items. Electrical permit exemptions published by BSEED cover only minor repair work, radio and television transmitting equipment and temporary testing systems, none of which reach a PV array.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a rooftop or ground-mounted photovoltaic system, including systems already approved for interconnection by DTE.

What a solar permit costs in Detroit

Line item
solar permitBy formulaBSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, PART E, RENEWABLE ENERGY INSTALLATIONS: "E1. Solar Photovoltaic systems (per visit): Systems with NO connection to utility grid, Per visit $165; Systems with utility grid connection per inverter connection, Per visit $278." The electrical PART A Base fee of $66 applies as well.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Detroit compares in Michigan

No Michigan jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Ann ArborPermit requiredFor expedited residential solar the Solar Photovoltaic (PV) System Permitting...
Detroitthis pagePermit requiredBSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, PART E...
Grand RapidsPermit requiredFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026...
Sterling HeightsPermit requiredBuilding Permit Application 26-27 fee chart: 'Solar Panels' $153.00, plus the...

How to apply in Detroit

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Detroit Buildings, Safety Engineering and Environmental Department (BSEED) sets the exact checklist for Detroit.

Where to apply in Detroit:

City of Detroit Buildings, Safety Engineering and Environmental Department (BSEED)

  • Development Resource Center, Coleman A. Young Municipal Center, 2 Woodward Avenue, Room 434, Detroit, MI 48226
  • Phone: (313) 224-2372
  • Email: DRC@detroitmi.gov

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Detroit permit portal or by phone at (313) 224-2372.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Detroit?
The City's Detroit Solar Toolkit FAQ states that a mechanical permit is not needed for rooftop panels but an electrical permit is one of the requirements, and that DTE interconnection approval does not replace Detroit permits. The BSEED fee schedule backs this up with a dedicated Part E, Renewable Energy Installations, which applies to all conductors and equipment installed to use solar, wind and fuel cells, and the C4 Electrical Permit Application carries the same Part E line items. Electrical permit exemptions published by BSEED cover only minor repair work, radio and television transmitting equipment and temporary testing systems, none of which reach a PV array. Always confirm with the City of Detroit Buildings, Safety Engineering and Environmental Department (BSEED) before starting.
How much does a solar permit cost in Detroit?
BSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, PART E, RENEWABLE ENERGY INSTALLATIONS: "E1. Solar Photovoltaic systems (per visit): Systems with NO connection to utility grid, Per visit $165; Systems with utility grid connection per inverter connection, Per visit $278." The electrical PART A Base fee of $66 applies as well. See the official fee schedule for current amounts.
How long does a solar permit take in Detroit?
In Detroit, a solar permit typically takes about 2 days for an electrical permit after the application is submitted. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a solar permit in Detroit?
You can apply through the Detroit permit portal or contact the City of Detroit Buildings, Safety Engineering and Environmental Department (BSEED) directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Detroit?
Under Michigan law (MCL 339.2403(b), (c); MCL 339.2401(a)(iii), (b)(ii)(A); MCL 339.5737(3)(g); MCL 339.6107(2)(d); MCL 339.5819): Yes. A Michigan homeowner may pull the building permit and do the work on their own home without a residential builder license, because the licensing article both defines the trade to exclude them and exempts them outright. MCL 339.2401(a)(iii) says a residential builder is a person that erects a residential structure except for the person's own use and occupancy on the person's property, and MCL 339.2403(b) exempts an owner of property with reference to a structure on the property for the owner's own use and occupancy. Own use and occupancy is the condition, so the exemption does not cover building to sell, and MCL 339.2403(c) limits owners of rental property to maintenance and alteration of that property. The statute sets no cap on how many times a homeowner may use the exemption; the only frequency rule in the article catches purchase, substantial rehabilitation, and resale of the same structure more than twice in 1 calendar year, and MCL 339.2401(b)(ii)(A) exempts work for the person's own use and occupancy from even that. Homeowners can also pull their own trade permits: electrical work in a single family home and accompanying outbuildings owned and occupied or to be occupied by the person doing the work (MCL 339.5737(3)(g)), their own plumbing, building sewer, or private sewer in their single-family dwelling if a permit is secured (MCL 339.6107(2)(d)), and a heating or refrigerating system if the owner affirms in the permit application that they are or will become the owner and occupant (MCL 339.5819). Confirm how Detroit applies this before you apply.

From the Library

What else needs a permit in Detroit

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsdeck areaBuilding permit fees are based on project cost under the BSEED Fee Schedule effective...
Electrical PermitIt dependselectrical alterations beyond replacing switches or receptaclesBSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, ELECTRICAL PART A:...
Fence PermitIt dependsfence height, for a fence outside a Special Review DistrictFence work is priced as a building permit on project cost under the BSEED Fee Schedule...
HVAC PermitIt dependsNot specifiedBSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, GAS FIRED EQUIPMENT:...
Plumbing PermitIt dependsplumbing alterations beyond the working parts of a faucet or valve or clearance of stoppagesBSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, PLUMBING INSTALLATION...
Pool PermitIt dependsprefabricated above-ground pool accessory to a Group R-3 occupancy holding not more than 5,000 gallonsBuilding permit fees are based on project cost under the BSEED Fee Schedule effective...
Roof Replacement PermitIt dependsroof-work beyond replacing a few shinglesBuilding permit fees are based on project cost under the BSEED Fee Schedule effective...
Shed PermitIt dependsfloor area of a one-story detached accessory structure in residential constructionBuilding permit fees are based on project cost under the BSEED Fee Schedule effective...

Solar Permit in other Michigan localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Detroit documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Detroit Buildings, Safety Engineering and Environmental Department (BSEED). Rules change; confirm before you build. How we verify.