Michigan / Ann Arbor

HVAC Permit in Ann Arbor, Michigan

Permit required

Yes, a permit is required

Before installing or replacing a furnace, boiler, air conditioner, rooftop unit, ductwork, gas piping, water heater venting or exhaust fan.

Confirmed on official page Verified City of Ann Arbor Building, Rental and Inspection Services (Construction and Building), with zoning review by Planning and Development Services

By Mario Bailey, verified against official sources

Quick answer

Mechanical work in Ann Arbor takes its own permit, separate from any building permit for the same project. The Building Department issues mechanical permits through STREAM and prices them per appliance and per system rather than on project valuation. Furnace, water heater, boiler and air conditioner reconnects also pull an electrical permit, which the mechanical contractor must obtain if no electrical contractor is already engaged. Trade permits tied to a building project are not released until the building permit is approved, and the permit must be posted on the job site.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing or replacing a furnace, boiler, air conditioner, rooftop unit, ductwork, gas piping, water heater venting or exhaust fan.

What an HVAC permit costs in Ann Arbor

Line item
HVAC permitBy formulaMechanical Permit Fees (effective July 1, 2017): $15 base application fee required for all permits, non refundable with no inspections, plus $35 each inspection. Residential line items include "Heating Appliances ... $50", "Distribution System - Duct ... $40", "Gas Distribution System lines ... $15", "Water Heater Regular and Tankless ... $15" and refrigeration or AC units at $40 for 2 HP or less, $55 for 2.25 to 5 HP and $75 for 5.25 to 50 HP. Mechanical contractor registration or re-registration is $15. Work without a permit is $130.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Ann Arbor compares in Michigan

No Michigan jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Ann Arborthis pagePermit requiredMechanical Permit Fees (effective July 1, 2017): $15 base application fee...
DetroitIt dependsBSEED Fee Schedule effective January 1, 2024, modified 7/18/2025, GAS FIRED...
Grand RapidsIt dependsFY 2027 Planning, Design and Development Fee Schedule effective July 1, 2026...
Sterling HeightsPermit requiredMechanical Permit Application 2026-2027: non-refundable application fee...

How to apply in Ann Arbor

A residential HVAC (mechanical) permit application must identify the covered equipment and scope of work, since installing, altering, or replacing a heating or cooling system is regulated work that cannot start until the application is submitted and the permit issued. The equipment itself must be picked by a real sizing calculation rather than a rule of thumb.

What most HVAC permit applications include:

  • A mechanical permit is required before anyone may install, alter, repair, remove, convert, or replace a heating, ventilating, or air conditioning system regulated by the code, and the work may not begin until the application is submitted and the permit is issued (IRC R105.1).
  • The application identifies the specific equipment being installed, such as a furnace, heat pump, or air conditioner, since the unit must be installed according to its listing and the manufacturer's installation instructions (IRC M1401.1).
  • The proposed equipment location must leave the clearances needed to clean coils and replace filters, blowers, motors, and controls after installation (IRC M1401.2).
  • The application carries the equipment sizing basis: ACCA Manual J building loads and Manual S equipment selection, or another approved sizing method, not a rule of thumb (IRC M1401.3).
  • For a split system, the work covered by the permit includes refrigerant suction line insulation, since the piping is inspected against that standard once installed (IRC M1411.6).

General submittal guidance from International Residential Code (IRC), 2021 edition, Chapter 1 (Permits) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. City of Ann Arbor Building, Rental and Inspection Services (Construction and Building), with zoning review by Planning and Development Services sets the exact checklist for Ann Arbor.

Where to apply in Ann Arbor:

City of Ann Arbor Building, Rental and Inspection Services (Construction and Building), with zoning review by Planning and Development Services

  • City Hall, 301 E. Huron St., Ann Arbor, MI 48104. Mailing: P.O. Box 8647, Ann Arbor, MI 48107-8647
  • Phone: 734.794.6263 ext. 0
  • Email: building@a2gov.org

Inspections and closing out your permit

Mechanical work gets a rough in inspection after the ductwork, refrigerant lines, and gas piping are in but before they are covered or concealed, followed by a final inspection that confirms the equipment operates correctly and its clearances, combustion air, and condensate disposal are in place. A straight equipment changeout with no new ductwork commonly gets a single final inspection instead of a separate rough in trip.

  1. Rough inspection of the mechanical and gas systems must be made before the work is covered or concealed, before fixtures or appliances are set or installed, and before the framing inspection (IRC R109.1.2).
  2. Where a cooling coil is added to an existing warm air furnace, the rough in confirms the coil is not installed upstream of the heat exchanger unless the furnace is listed for it, and that the blower can handle the added static pressure (IRC M1411.2).
  3. The rough in and final both confirm the appliance access opening and working space are large enough to service the unit (IRC M1305.1).
  4. At final inspection, the inspector verifies the equipment has adequate combustion air, with openings kept clear for the distance the code requires (IRC M1402.3).
  5. Final inspection also checks that the condensate line drains to an approved point of disposal with the required slope and does not create a nuisance (IRC M1411.3).
  6. For a straight equipment changeout with no new ductwork, many permit offices require only a single final inspection, while a new installation still gets a rough in inspection before the final (common local inspection practice).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Ann Arbor permit portal or by phone at 734.794.6263 ext. 0.

Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109 (Required Inspections) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an HVAC permit in Ann Arbor?
Mechanical work in Ann Arbor takes its own permit, separate from any building permit for the same project. The Building Department issues mechanical permits through STREAM and prices them per appliance and per system rather than on project valuation. Furnace, water heater, boiler and air conditioner reconnects also pull an electrical permit, which the mechanical contractor must obtain if no electrical contractor is already engaged. Trade permits tied to a building project are not released until the building permit is approved, and the permit must be posted on the job site. Always confirm with the City of Ann Arbor Building, Rental and Inspection Services (Construction and Building), with zoning review by Planning and Development Services before starting.
How much does an HVAC permit cost in Ann Arbor?
Mechanical Permit Fees (effective July 1, 2017): $15 base application fee required for all permits, non refundable with no inspections, plus $35 each inspection. Residential line items include "Heating Appliances ... $50", "Distribution System - Duct ... $40", "Gas Distribution System lines ... $15", "Water Heater Regular and Tankless ... $15" and refrigeration or AC units at $40 for 2 HP or less, $55 for 2.25 to 5 HP and $75 for 5.25 to 50 HP. Mechanical contractor registration or re-registration is $15. Work without a permit is $130. See the official fee schedule for current amounts.
How long does an HVAC permit take in Ann Arbor?
Minimum 24 to 48 hours for review and processing; trade permit reviews typically completed within 2 to 3 business days. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for an HVAC permit in Ann Arbor?
You can apply through the Ann Arbor permit portal or contact the City of Ann Arbor Building, Rental and Inspection Services (Construction and Building), with zoning review by Planning and Development Services directly. The links are listed on this page.
Can a homeowner pull an HVAC permit themselves in Ann Arbor?
Under Michigan law (MCL 339.2403(b), (c); MCL 339.2401(a)(iii), (b)(ii)(A); MCL 339.5737(3)(g); MCL 339.6107(2)(d); MCL 339.5819): Yes. A Michigan homeowner may pull the building permit and do the work on their own home without a residential builder license, because the licensing article both defines the trade to exclude them and exempts them outright. MCL 339.2401(a)(iii) says a residential builder is a person that erects a residential structure except for the person's own use and occupancy on the person's property, and MCL 339.2403(b) exempts an owner of property with reference to a structure on the property for the owner's own use and occupancy. Own use and occupancy is the condition, so the exemption does not cover building to sell, and MCL 339.2403(c) limits owners of rental property to maintenance and alteration of that property. The statute sets no cap on how many times a homeowner may use the exemption; the only frequency rule in the article catches purchase, substantial rehabilitation, and resale of the same structure more than twice in 1 calendar year, and MCL 339.2401(b)(ii)(A) exempts work for the person's own use and occupancy from even that. Homeowners can also pull their own trade permits: electrical work in a single family home and accompanying outbuildings owned and occupied or to be occupied by the person doing the work (MCL 339.5737(3)(g)), their own plumbing, building sewer, or private sewer in their single-family dwelling if a permit is secured (MCL 339.6107(2)(d)), and a heating or refrigerating system if the owner affirms in the permit application that they are or will become the owner and occupant (MCL 339.5819). Confirm how Ann Arbor applies this before you apply.

From the Library

What else needs a permit in Ann Arbor

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedBuilding Permit Fees (effective October 2019, revised 7/15/2025): $15 base application...
Electrical PermitPermit requiredNot specifiedElectrical Permit Fees (effective January 2020): $15 base application fee for all...
Fence PermitPermit requiredNot specifiedThe Planning Services Fence Guidelines handout (revised 3/3/2025) states a flat Fence...
Patio PermitIt dependsNot specifiedNo patio specific line item is published.
Plumbing PermitPermit requiredNot specifiedPlumbing Permit Fees (effective July 1, 2017): $15 base application fee required for all...
Pool PermitPermit requiredNot specifiedBuilding Permit Fees (effective October 2019, revised 7/15/2025) carries a flat line...
Roof Replacement PermitIt dependsNot specifiedNo roofing line item is published.
Shed PermitPermit requiredNot specifiedBuilding Permit Fees (effective October 2019, revised 7/15/2025), under the Zoning...
Solar PermitPermit requiredNot specifiedFor expedited residential solar the Solar Photovoltaic (PV) System Permitting Checklist...

HVAC Permit in other Michigan localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Ann Arbor documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Ann Arbor Building, Rental and Inspection Services (Construction and Building), with zoning review by Planning and Development Services. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page