Electrical Permit in Boise, Idaho
Permit required
Yes, a permit is required
Before installing, changing or repairing any hard-wired electrical work.
Issued byCity of Boise Planning and Development Services, Building Division
By Mario Bailey, verified against official sources
Quick answer
Boise requires an electrical permit, issued by the City, to install, change or repair any hard-wired electrical system, run additional wiring, add an outlet, switch or light fixture, or change a fuse box to circuit breakers. Low-voltage outdoor lighting does not need a permit; 110-volt lighting does. Homeowners may do their own work on a primary residence; anyone else must hold a State of Idaho electrical license.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before installing, changing or repairing any hard-wired electrical work.
What an electrical permit costs in Boise
How to apply in Boise
In Boise, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- For Boise, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- For Boise, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Boise Planning and Development Services, Building Division sets the exact checklist for Boise.
Where to apply in Boise:
City of Boise Planning and Development Services, Building Division
- 150 N Capitol Blvd, Boise, ID 83702
- Phone: (208) 608-7070
Inspections and closing out your permit
In Boise, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- In Boise: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- In Boise: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- In Boise: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- In Boise: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- In Boise: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- In Boise: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- In Boise: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Boise permit portal or by phone at (208) 608-7070.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Boise
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing, changing or repairing any hard-wired electrical work.
- Budget the fee. Single branch circuit: $57.00 (Table 2-b); more than one branch circuit for an addition, alteration, repair or fixture replacement: $114.00 (Table 3-a). FY27 Electrical Code Fee Schedule, Oct. 2026. Official fee schedule.
- Apply. In Boise, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Boise permit portal.
- Keep the office details handy. City of Boise Planning and Development Services, Building Division. Phone: (208) 608-7070. Address: 150 N Capitol Blvd, Boise, ID 83702.
- Plan for inspections. In Boise, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in Boise?
- Boise requires an electrical permit, issued by the City, to install, change or repair any hard-wired electrical system, run additional wiring, add an outlet, switch or light fixture, or change a fuse box to circuit breakers. Low-voltage outdoor lighting does not need a permit; 110-volt lighting does. Homeowners may do their own work on a primary residence; anyone else must hold a State of Idaho electrical license. Always confirm with the City of Boise Planning and Development Services, Building Division before starting.
- How much does an electrical permit cost in Boise?
- Single branch circuit: $57.00 (Table 2-b); more than one branch circuit for an addition, alteration, repair or fixture replacement: $114.00 (Table 3-a). FY27 Electrical Code Fee Schedule, Oct. 2026. See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in Boise?
- You can apply through the Boise permit portal or contact the City of Boise Planning and Development Services, Building Division directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in Boise?
- Under Idaho law (Idaho Code 54-5205(2)(l); 54-5209; 54-1016(2)(a); 54-2602(1)(a); 54-5002(1)(a)): Idaho homeowners may do their own work. The Idaho Contractor Registration Act exempts an owner building on their own residential property, whether or not they live there. That exemption does not cover an owner who builds in order to promptly sell, unless they have lived in the home as their primary residence for at least 12 months before the sale. The trade laws carry their own owner exemptions: a property owner may do noncommercial electrical work in their own primary or secondary residence (54-1016(2)(a)), and an owner or contract purchaser may do their own plumbing (54-2602(1)(a)) and HVAC work (54-5002(1)(a)) in a single-family home or duplex, but must still meet the code and get the permit. A permit issued to an exempt owner is marked "no contractor registration provided" (54-5209). Confirm how Boise applies this before you apply.
From the Library
What else needs a permit in Boise
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before removing wall coverings to the framing, building a wall, relocating fixtures, or... | Plumbing: $33.00 base fee plus $12.50 per fixture (FY27 Plumbing Code Fee Schedule) |
| Deck Permit | It depends | deck height above grade at any point | Building permit fee from Table No. 1-A by valuation (e.g |
| EV Charger Permit | Permit required | Any size | ...but not limited to, wall heaters, residential electric car outlets" $57.00 (Table... |
| Fence Permit | It depends | fence height | Building permit fee from Table No. 1-A by valuation (e.g |
| HVAC Permit | Permit required | Any size | ...or appliance (including furnaces, air conditioners, mini-split systems): $57.00... |
| Patio Permit | It depends | concrete patio height above grade | Building permit fee from Table No. 1-A by valuation (e.g |
| Plumbing Permit | Permit required | Any size | $33.00 base permit fee plus $12.50 each per fixture (e.g |
| Pool Permit | It depends | prefabricated pools only; in-ground and deeper pools need a permit | Building permit fee from Table No. 1-A by valuation (e.g |
| Roof Replacement Permit | Permit required | Any size | Building permit fee from Table No. 1-A by valuation (e.g |
| Shed Permit | It depends | floor area of a one-story detached accessory structure | Building permit fee from Table No. 1-A by valuation (e.g |
| Solar Permit | Permit required | Any size | ...Solar Photovoltaic Systems plan review/inspections building permit fee: $171, plus... |
| Water Heater Permit | Permit required | Any size | Plumbing: $33.00 base fee plus "Water heaters $12.50 Each" (FY27 Plumbing Code Fee... |
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Boise documents; the office above sets the local rules.
How this electrical permit page for Boise was verified. 1 official source: cityofboise.org; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Boise Planning and Development Services, Building Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Idaho localities