Solar Permit in Boise, Idaho
Permit required
Yes, a permit is required
Before installing rooftop or ground-mounted solar panels.
Quick answer
Boise requires a building permit for residential solar photovoltaic panels and modules, plus a separate electrical permit; no size exemption is published. Applications use the #406 Residential Photovoltaic Systems Submittal Checklist, and the City advertises expedited over-the-counter review, typically 3 days or less. Structural engineering may be required for ballasted systems, pre-1970 hand-stacked roofs, Foothills ground mounts, pergola mounts or racking adding more than 5 psf.
- Issued by
- City of Boise Planning and Development Services, Building Division
- Phone
- (208) 608-7070
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your Idaho Contractors Board (Idaho Division of Occupational and Professional Licenses) license active, and under which business name? Verify it on edopl.idaho.gov.
Idaho's owner-builder rule (Idaho Code 54-5205(2)(l); 54-5209; 54-1016(2)(a); 54-2602(1)(a); 54-5002(1)(a)) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Boise
- Fee schedule in force
- Official scheduleRead .
Residential Solar Photovoltaic Systems plan review/inspections building permit fee: $171, plus a separate electrical permit, "Installation of photovoltaic system: (up to two inspections)" $114.00.
Solar Photovoltaic Systems Fee Guide (10/2026) and FY27 Electrical Code Fee Schedule.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in Boise
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
City of Boise Planning and Development Services, Building Division
- 150 N Capitol Blvd, Boise, ID 83702
- Phone: (208) 608-7070
Solar Permit in Boise compared with nearby Idaho localities
| Locality | Permit needed? | Threshold | What each Idaho schedule says | Verified |
|---|---|---|---|---|
| Boise | Permit required | Any size | Residential Solar Photovoltaic Systems plan review/inspections building permit fee: $171, plus a separate electrical permit; the schedule has the rest | |
| Meridian | Permit required | Any size | $0.00 to $2,000: $40.00 base fee + 2.5% of value |
Your Solar Permit checklist for Boise
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: cityofboise.org: homeowners guide.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Boise permit portal.
- Keep the office details handy. City of Boise Planning and Development Services, Building Division. Phone: (208) 608-7070. Address: 150 N Capitol Blvd, Boise, ID 83702.
Compiled from the official sources on this page. Last checked .
Permitting activity in Boise
In 2025, Boise authorized permits for 955 new residential housing units (730 single-family, 225 in multi-family buildings), valued at $239M, up from 741 the year before. That works out to about 4.2 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 229,776.
What else needs a permit in Boise
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before removing wall coverings to the framing, building a wall, relocating fixtures, or... | Plumbing: $33.00 base fee plus $12.50 per fixture (FY27 Plumbing Code Fee Schedule) |
| Deck Permit | It depends | deck height above grade at any point | See schedule |
| Electrical Permit | Permit required | Any size | Single branch circuit: $57.00 (Table 2-b) |
| EV Charger Permit | Permit required | Any size | See schedule |
| Fence Permit | It depends | fence height | See schedule |
| HVAC Permit | Permit required | Any size | Single fixture or appliance (including furnaces, air conditioners, mini-split systems): $57.00 (Table B(3) Miscellaneous Residential Mechanical Fees) |
| Patio Permit | It depends | concrete patio height above grade | See schedule |
| Plumbing Permit | Permit required | Any size | See schedule |
| Pool Permit | It depends | prefabricated pools only; in-ground and deeper pools need a permit | See schedule |
| Roof Replacement Permit | Permit required | Any size | See schedule |
| Shed Permit | It depends | floor area of a one-story detached accessory structure | See schedule |
| Water Heater Permit | Permit required | Any size | See schedule |
Frequently asked questions
- Do you need a solar permit in Boise?
- Yes, before installing rooftop or ground-mounted solar panels. If you are unsure how that applies to your project, call the City of Boise Planning and Development Services, Building Division at (208) 608-7070 before you start.
- How much does a solar permit cost in Boise?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 3 Oct 2026. For the figure on your own project, call the City of Boise Planning and Development Services, Building Division at (208) 608-7070.
- How long does a solar permit take in Boise?
- Typically 3 days or less (expedited over-the-counter review, per the Solar Energy in Boise page). Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a solar permit in Boise?
- You can apply through the Boise permit portal or contact the City of Boise Planning and Development Services, Building Division directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Boise?
- Under Idaho law (Idaho Code 54-5205(2)(l); 54-5209; 54-1016(2)(a); 54-2602(1)(a); 54-5002(1)(a)): Idaho homeowners may do their own work. The Idaho Contractor Registration Act exempts an owner building on their own residential property, whether or not they live there. That exemption does not cover an owner who builds in order to promptly sell, unless they have lived in the home as their primary residence for at least 12 months before the sale. The trade laws carry their own owner exemptions: a property owner may do noncommercial electrical work in their own primary or secondary residence (54-1016(2)(a)), and an owner or contract purchaser may do their own plumbing (54-2602(1)(a)) and HVAC work (54-5002(1)(a)) in a single-family home or duplex, but must still meet the code and get the permit. A permit issued to an exempt owner is marked "no contractor registration provided" (54-5209). Confirm how Boise applies this before you apply.
From the Library
Solar Permit in other Idaho localities
Everything above, sourced
How this solar permit page for Boise was verified. 2 official sources: cityofboise.org, cityofboise.org; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Boise Planning and Development Services, Building Division. Rules change; confirm before you build. How we verify.