Guide
Do You Need a Permit to Remodel a Bathroom? Tile and Vanity No, Moved Plumbing Yes
Paint, tile, flooring and a new vanity cabinet need no permit. Moving a toilet or shower, adding a circuit or a fan, opening a wall or adding a bathroom does. Replacing a fixture in place depends on the city. The line item by item, with how Virginia, Jersey City, San Francisco, Boston, Portland, Chicago, Des Moines, Burlington, Las Vegas and Martin County draw it.
It depends on what the remodel touches. New paint, tile, carpet, cabinets and countertops need no permit under the model code. Moving a toilet, tub or shower, adding an outlet, a circuit or an exhaust fan, removing a wall, and adding a bathroom where there was none all need permits, usually one for each trade. Stripping the drywall off a whole wall is permit work in some cities and not in others.
Replacing a toilet, sink or tub in the same spot is the item that changes by city. Virginia exempts it statewide, and Jersey City, New Jersey lists it as ordinary maintenance. Boston lists a Plumbing Permit for it that only licensed contractors can apply for, and San Francisco says “You need a permit before renovating and replacing kitchen or bath fixtures.”
The next step: write down every item in your plan and sort it with the table below. If anything lands on the permit side, look up your building department in our verified index before demolition, because the trade permits may have to be pulled by a licensed contractor.
The short version, item by item
| Work | Permit? | Whose words |
|---|---|---|
| Paint, wallpaper, tile, new flooring | No | Model code: “Painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work” |
| New vanity cabinet, countertop, mirror, towel bars (the sink plumbed into the vanity is separate) | No | Jersey City: “cabinets, benches or seats, and bathroom accessories” |
| New faucet or shower head | No | Las Vegas: “Repair/replace Shower heads” |
| Replace a toilet, sink or tub in the same place | Depends on the city | See the next section |
| Replace a light fixture, switch or outlet | Depends on the city | Virginia exempts it. Las Vegas: “If a GFCI protected outlet is required by code, a permit is required” |
| Replace an existing exhaust fan | No in Jersey City; ask elsewhere | Jersey City exempts it if the fan “vents independently to the outdoors” |
| Add an exhaust fan, a new outlet or a new circuit | Yes | Las Vegas: “Install bathroom fans, dryer exhausts, kitchen range exhausts” |
| Move a toilet, sink, tub or shower | Yes | Las Vegas: “Alter piping inside a wall, ceiling or beneath a floor” |
| Take drywall off a whole wall or ceiling | Often yes | Des Moines: “Removing and replacing finishes on an entire wall or ceiling in a room” |
| Remove, move or add a wall | Yes | Henrico County: “the removal or addition of any wall, partition or portion thereof” |
| Add a bathroom where there was none | Yes | Henrico County: “Converting existing spaces for new intents (bathroom, bedroom, etc.)” |
What needs no permit
The International Residential Code, the model code that states and cities adopt and amend, exempts “Painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work.” Local lists follow it closely.
- Chicago exempts “Painting, wallpapering, tiling, carpeting, installing cabinets or countertops, or performing similar finish work, without plumbing or electrical connections.” The last five words are the limit: a vanity is finish work, and the sink plumbed into it is not.
- Martin County, Florida lists “Painting, papering, flooring, and similar finishing work,” “Cabinetry” and “Repair of Toilets, Sinks and Faucets” among work that needs no permit. The same page puts “Shower or tub enclosure replacements” on its permit list, so a new tub surround is not finish work there.
- Las Vegas lists “Resurfacing Shower walls” and repairing or replacing a faucet “if not concealed in a wall.”
- Jersey City counts “Exterior and interior painting,” new flooring, and “Refinishing of existing fixtures” as ordinary maintenance, with one exception that catches people who have a tub relined: “Relining of fixtures shall not be considered to be ordinary maintenance.”
New flooring is the one finish item with a recorded bathroom exception: San Francisco’s floor covering exemption covers “areas other than bathrooms.” Our flooring guide covers that and what changes when the subfloor or joists underneath need repair.
Exempt work still has to meet code. Prince William County, Virginia puts it at the top of its list: “although the work is not subject to permit requirements, the work must be performed in a manner meeting code requirements.” One accessory is an exception there: the county’s list of work that always needs a permit includes “Accessibility Upgrades (i.e., temporary ramps, permanent ramps, grab bars, widening doors and existing interior openings, wheelchair lifts).”
Replacing a fixture in place: where the rules split
Virginia exempts it statewide. The state building code lists as ordinary repairs the “Replacement of plumbing fixtures and well pumps in all groups without alteration of the water supply and distribution systems, sanitary drainage systems, or vent systems.” It does the same for the electrical side of a bathroom: “Replacement of general use snap switches, dimmer and control switches, 125 volt-15 or 20 ampere receptacles, luminaires (lighting fixtures), and ceiling (paddle) fans” in houses and single dwelling units, along with “Installation or replacement of floor finishes,” “Installation or replacement of cabinetry or trim” and “Application of paint or wallpaper.” Counties repeat it. Prince William County: “Replacing existing plumbing fixtures (water closets, tubs, sinks, garbage disposals, etc.) where no alteration to the supply or drain/waste/vent systems are involved.” See Henrico County and Prince William County.
The Virginia exemption is for replacement, not first installation. Henrico County states the other half: “Permits are required for the initial installation of fixtures and appliances permanently connected to the electrical, mechanical, gas and/or plumbing system(s),” and its list includes “Bathtubs,” “Showers,” “Sinks,” “Toilets” and “Fans, attic/ceiling/exhaust.” Adding a second sink is new work, not a replacement.
Jersey City, New Jersey draws the same line. Jersey City lists as ordinary maintenance “Replacements of faucets or working parts of faucets” and “Replacement of fixtures with a similar fixture provided that no change in the piping arrangement is made.” Electrical swaps are covered too: “The replacement of any receptacle, switch, or lighting fixture, or part thereof, not containing emergency battery packs with a like or similar item.” So is “The replacement of bathroom exhaust fans in dwelling units, provided that the fan vents independently to the outdoors.”
Boston lists a permit for the swap itself. Its fixture page lists a Plumbing Permit “For replacing or installing a sink, toilet, shower, or bathtub when no other work needs to be done, such as opening up walls,” and that permit is one “that only licensed contractors can apply for.” See Boston.
San Francisco requires one before fixture work. “You need a permit before renovating and replacing kitchen or bath fixtures.” The page points to the exemptions in San Francisco Building Code Section 106a.2. See San Francisco.
Burlington, Vermont draws its line on the surfaces, by dollar amount. The rule below covers building work; plumbing and electrical go through the city’s separate trades permit, and we did not read a fixture rule for it. “A Building Permit is required for all non-mechanical/electrical/plumbing work in Burlington with the exception of the following: carpeting; painting; nonsolid fences; storm doors and/or storm windows; and ONLY in-kind repair work costing $1,000.00 or less.” Tile is not on that list. Read literally, retiling needs a permit there unless it is an in-kind repair under that amount, so ask the division before you rely on either reading. The page adds that “A Building Permit is also required for any demolition work in Burlington and in most cases asbestos testing will be needed.” See Burlington.
What always needs a permit
The model code requires a permit to “construct, enlarge, alter, repair, move, demolish” a building or to “erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system.” Its repair exemption does not reach “the cutting away of any wall, partition or portion thereof” or the “replacement or relocation of any water supply, sewer, drainage” piping or “electric wiring.” In a bathroom that means four things.
Moving a fixture. A toilet moved a foot needs a new drain connection under the floor. Las Vegas requires a permit to “Alter piping inside a wall, ceiling or beneath a floor,” and to “Remodel or add on to your home when existing plumbing is to be relocated.” Prince William County lists “any work involving alterations to the house plumbing, electrical, or heating and air conditioning (mechanical) systems.”
New electrical work. Prince William County requires a permit for “Installing a new electrical circuit, fixture, or receptacle.” A vanity light where there was no box and an added outlet both fall here. Our guide to electrical work that needs a permit covers the line between replacing and adding.
A new exhaust fan. Las Vegas requires a mechanical permit to “Install bathroom fans.” Henrico County lists exhaust fans among fixtures whose “initial installation” needs a permit.
Walls. Henrico County requires a permit for work involving “the removal or addition of any wall, partition or portion thereof.” Whether the wall carries load does not change that; our guide to removing a wall without a permit explains why.
Gutting to the studs
A remodel that only changes surfaces can turn into permit work when the drywall comes off, and cities measure that differently.
- Des Moines exempts “Sheetrock and plaster repair,” with “Patching holes in wall finishes” and “Replacing a 64 square foot area of damaged drywall” as examples. Its examples of work that does require a permit are “Removing and replacing finishes on an entire wall or ceiling in a room” and “Complete removal of interior finishes.” See Des Moines.
- Chicago is more generous: no building permit for “Removing and replacing up to 1,000 square feet of drywall or plaster, without alteration of any mechanical, electrical, or plumbing device or system.” See Chicago.
If your tile job means taking the tub surround back to bare studs, ask about this by name. Des Moines and Chicago show how far apart the answers can be; our guide to replacing drywall compares more of these limits, from Wichita’s 100 square feet to Virginia’s statewide exemption.
How five places handle a full remodel
San Francisco sets a minimum project value for the application: “Minimum valuations are $24,663 per kitchen and $20,552 per bathroom, according to DBI’s cost schedule.” You can apply online only when the work “Will not involve removing or moving walls (does not require plans),” “Is for an R-3 residential building, or a unit in an R-2 apartment building” and “Is for remodeling a legally-permitted kitchen or bath.” Electrical and plumbing permits are separate, and the order matters at the end: “You will not be able to schedule final inspections for the kitchen or bath remodel until the electrical and plumbing work has passed final inspection.”
Boston: “You will need several permits if you are planning to renovate a bathroom or kitchen.” The building permit is a Short-Form Permit “For renovating an existing bathroom when no other structural changes need to be made, such as cutting into a wall,” or a Long-Form Permit “For moving any structural walls or egresses while performing the work, such as expanding the size of the bathroom or kitchen, creating a new window, or creating or removing a doorway.”
Portland, Oregon separates a remodel from a new bathroom. “Doing a bathroom remodel? You may just need trade permits (electrical, mechanical, and plumbing permits).” A new bathroom needs a building permit, and the city runs a faster route for simple ones, described below.
Martin County, Florida lists “Kitchen and Bathroom remodels” among the projects that require a permit. See Martin County.
Virginia counties work from the statewide list above: replacements are ordinary repairs, and anything that alters piping, wiring or walls is permit work.
Adding a bathroom
A bathroom in a space that was a closet, a bedroom corner or a basement is a different project from a remodel. Henrico County lists “Converting existing spaces for new intents (bathroom, bedroom, etc.)” among home improvements that require a permit.
Portland’s Simple Bathroom Permit shows what a city looks at. It lets you add “a new full or half bathroom” without drawing plans “if all of the following apply”:
- “Interior only; no exterior alterations”
- “No changes to load-bearing framing”
- “The property can have no more than three toilets total, including the one in the new bathroom.”
- “Located in a permitted structure in the primary residence (not in a detached accessory structure)”
The page warns that “Other criteria may apply,” and gives party sewers and code violations on the property as examples. The city says “We review applications within five business days.” Projects that do not qualify go through the standard permit with plans.
Who can do the work
- Boston: “If you are a homeowner trying to complete one or both these projects, you’ll need to hire a contractor who will apply for the permits and perform the work.” Homeowners can apply for the Short-Form or Long-Form permit, but “Only a contractor with a valid, non-expired Massachusetts trade license may apply for a Plumbing Permit, Electrical, or Sheet Metal permit.”
- San Francisco: “For R-3 single-family homes, homeowners can only apply to do sheetrock, drywall, or cabinetry themselves if the home is their primary residence. They can only do their own electrical or plumbing work after speaking to an inspector.” And whoever applies carries the risk: “property owners and their authorized agents are held liable for any construction work done on the permit.”
- Portland: “If the homeowner is performing the work, complete a State of Oregon construction responsibilities form.”
Our guides to who pulls the permit and to whether a homeowner can pull an electrical permit cover the state rules behind these.
Inspections: before the tile goes up
The inspection to plan around is the rough-in, because it happens while the work can still be seen. The model code requires that “Rough inspection of plumbing, mechanical, gas and electrical systems shall be made prior to covering or concealment, before fixtures or appliances are set or installed.” In practice that means the new drain, supply lines and wiring are looked at while the walls and floor are open, and backer board and tile wait until they pass. Our guide to plumbing permits and inspections walks through the rough-in and the final.
If the bathroom was already done without a permit
Two of the cities above publish a way back. Portland’s Simple Bathroom Permit can be used “to legalize an existing bathroom” that qualifies. San Francisco sends work that “is for legalizing unpermitted kitchens or baths” to an over-the-counter building permit with plans.
Portland also gives the reasons to do it: “If you plan to sell your home, unpermitted work can delay the sale. Buyers, realtors, or lenders often require that all work be properly permitted and inspected,” and “Some insurance companies may not cover homes with unpermitted work.” Our guide to selling a house with unpermitted work covers what that looks like at closing, and the state penalty pages list what each state charges.
Method
Every rule above was read on November 11, 2026 in the building department’s own page, policy or handout, in the Virginia Administrative Code, or in the 2024 International Residential Code on ICC’s digital codes site, all linked below. Each quotation was matched by machine against the text of the page it came from. For more places, the bathroom remodel permit index lists every jurisdiction where we have verified this project. Your state may enforce a different edition of the model code and your city may amend its exemption list, so the list your own building department publishes is the one that governs your bathroom.
Sources
- 2024 International Residential Code, Chapter 1, read on ICC Digital Codes: R105.1 (when a permit is required), R105.2 (work exempt from permit, Building item 6 on finish work and the plumbing exemptions), R105.2.2 (ordinary repairs) and R109.1.2 (rough inspection before concealment). (accessed )
- Virginia Uniform Statewide Building Code, 13VAC5-63-80, Section 108.2 item 14: the ordinary repairs exempt from permit statewide, including fixture replacement without altering piping, switches, receptacles and light fixtures, floor finishes, cabinetry and paint. (accessed )
- Henrico County, Virginia, When a Building Permit is Not Required: the ordinary repairs list as the county publishes it. (accessed )
- Henrico County, Virginia, When a Building Permit is Required: alterations to walls, piping and wiring, converting a space to a bathroom, and first-time installation of bathtubs, showers, sinks, toilets and fans. (accessed )
- Prince William County, Virginia, Do I Need a Permit?: work that always needs a permit and the fixture, cabinetry, floor finish and light fixture replacements that do not. (accessed )
- Jersey City, New Jersey, Ordinary Maintenance: work that needs no permit, including painting, flooring, cabinets and bathroom accessories, faucet and like-for-like fixture replacement, and bathroom exhaust fan replacement. (accessed )
- San Francisco Department of Building Inspection, Apply for a kitchen or bath remodel permit: a permit before renovating and replacing bath fixtures, the $20,552 minimum valuation per bathroom, the online route, the order of final inspections, and what homeowners may do themselves. (accessed )
- City of Boston, Renovate a Bathroom or Kitchen: several permits, Short-Form versus Long-Form, and the licensed-trades requirement. (accessed )
- City of Boston, Install or Replace a Sink, Toilet, Shower, or Bathtub: a Plumbing Permit even when no other work is done. (accessed )
- City of Portland, Oregon, Residential bathrooms: a remodel may need only trade permits, a new bathroom goes through the Simple Bathroom Program or the standard process, and why the city says to get a permit. (accessed )
- City of Portland, Oregon, Simple Bathroom Permits: the four criteria for a new or legalized bathroom without drawn plans, the owner form, and the five-business-day review. (accessed )
- City of Chicago Department of Buildings, What Types of Work Do Not Require a Building Permit?: finish work without plumbing or electrical connections, the 1,000 square foot drywall allowance, and the plumbing exemptions. (accessed )
- City of Des Moines, Iowa, permit exemption policy for minor maintenance and repair, effective 7-1-2023: sheetrock and plaster repair is exempt, removing finishes on an entire wall or ceiling is not. (accessed )
- City of Burlington, Vermont, Building and Trades Division: a building permit for all work except carpeting, painting and in-kind repair costing $1,000.00 or less. (accessed )
- City of Las Vegas Building and Safety, When Do I Need a Permit?: bathroom fans, concealed piping, and the fixture and shower repairs that need no permit. (accessed )
- Martin County, Florida, Do I Need a Permit?: kitchen and bathroom remodels require a permit; finishing work, cabinetry and repair of toilets, sinks and faucets do not. (accessed )
Get rule-change alerts