Solar Permit in Madison, Wisconsin
Permit required
Yes, a permit is required
Before installing a solar energy system. A building permit plus an electrical permit is the normal package; solar domestic hot water also pulls a plumbing permit and a heating permit.
By Mario Bailey, verified against official sources
Quick answer
Madison requires permits to install a solar energy system: the Development Services Center chart lists "Solar Energy System - install" as Yes with Building Inspection at 608-266-4551 ext. 2, and the fee schedule carries a dedicated $21.00 solar panel or collector system permit. The city's How to Go Solar guide walks through the building permit documents (structural drawings and calculations, a section of the existing roof showing the attachment, a catalog cut sheet with the panel weight, and a site and placement plan) and the trade permit documents (a UL-listed cut sheet for the PV device, and for solar hot water proof of a non-toxic transfer fluid or a double-walled heat exchanger). Calculations may be done by a knowledgeable person for residential buildings and commercial buildings up to 50,000 cubic feet; larger buildings need a licensed professional engineer or architect.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before installing a solar energy system. A building permit plus an electrical permit is the normal package; solar domestic hot water also pulls a plumbing permit and a heating permit.
What a solar permit costs in Madison
How to apply in Madison
A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.
What most solar permit applications include:
- Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
- The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
- Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
- The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
- The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
- Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
- Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).
General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Madison Building Inspection Division, Department of Planning and Community and Economic Development sets the exact checklist for Madison.
Where to apply in Madison:
City of Madison Building Inspection Division, Department of Planning and Community and Economic Development
- 215 Martin Luther King Jr. Blvd., Suite 017, Madison, WI 53703
- Phone: 608-266-4551
- Email: binspection@cityofmadison.com
Inspections and closing out your permit
Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
- Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
- The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
- PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
- Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
- At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
- Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Madison permit portal or by phone at 608-266-4551.
Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Solar Permit checklist for Madison
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing a solar energy system. A building permit plus an electrical permit is the normal package; solar domestic hot water also pulls a plumbing permit and a heating permit.
- Budget the fee. "Solar panels or collector system: $21.00 each permit" (MGO 29.09(3)(a), Group IV; amended by ORD-25-00034, 6-13-25). The electrical permit is billed separately at $25.00 for the first ten openings and $1.00 each additional opening (MGO 19.11, Group IV). Official fee schedule.
- Apply. A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit. Start at the Madison permit portal.
- Keep the office details handy. City of Madison Building Inspection Division, Department of Planning and Community and Economic Development. Phone: 608-266-4551. Address: 215 Martin Luther King Jr. Blvd., Suite 017, Madison, WI 53703.
- Plan for inspections. Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a solar permit in Madison?
- Madison requires permits to install a solar energy system: the Development Services Center chart lists "Solar Energy System - install" as Yes with Building Inspection at 608-266-4551 ext. 2, and the fee schedule carries a dedicated $21.00 solar panel or collector system permit. The city's How to Go Solar guide walks through the building permit documents (structural drawings and calculations, a section of the existing roof showing the attachment, a catalog cut sheet with the panel weight, and a site and placement plan) and the trade permit documents (a UL-listed cut sheet for the PV device, and for solar hot water proof of a non-toxic transfer fluid or a double-walled heat exchanger). Calculations may be done by a knowledgeable person for residential buildings and commercial buildings up to 50,000 cubic feet; larger buildings need a licensed professional engineer or architect. Always confirm with the City of Madison Building Inspection Division, Department of Planning and Community and Economic Development before starting.
- How much does a solar permit cost in Madison?
- "Solar panels or collector system: $21.00 each permit" (MGO 29.09(3)(a), Group IV; amended by ORD-25-00034, 6-13-25). The electrical permit is billed separately at $25.00 for the first ten openings and $1.00 each additional opening (MGO 19.11, Group IV). See the official fee schedule for current amounts.
- How long does a solar permit take in Madison?
- If all documents are complete and acceptable the permit is issued at the counter right away. A Planned Development alteration adds about two weeks plus the time needed to get the alder's signature. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a solar permit in Madison?
- You can apply through the Madison permit portal or contact the City of Madison Building Inspection Division, Department of Planning and Community and Economic Development directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Madison?
- Under Wisconsin law (Wis. Stat. 101.654(1)(a) and (1)(b); Wis. Admin. Code SPS 305.31(1), SPS 320.09(9)(a)2., 3. and 4.; Wis. Stat. 101.65(1m) and (1r); Wis. Stat. 101.862(4)(a); Wis. Stat. 145.06(4)(a)): A Wisconsin homeowner may pull the permit and do the work on their own dwelling. The general rule is that nobody may obtain a building permit for a one- or two-family dwelling without a DSPS dwelling contractor certification plus a dwelling contractor qualifier credential, but the statute exempts an owner of a dwelling who resides or will reside in the dwelling and who applies for a building permit to perform work on that dwelling. Neither the statute nor the implementing rule places any cap on how often that exemption may be used, and Wisconsin has no counterpart to Florida's one-year resale restriction. The trade-off is a disclosure: the permit issuer must have the owner sign a statement warning that if the owner hires a contractor who is not bonded or insured, the owner may be held liable for injury or property damage arising from the work and may be unable to collect damages from that contractor. Trade licensing carries its own homeowner carve-outs, both defeasible by local ordinance: a residential property owner may do electrical wiring on premises the owner owns and occupies as a residence, and a property owner may do plumbing work in a one-family building owned and occupied as the owner's home. Confirm how Madison applies this before you apply.
From the Library
What else needs a permit in Madison
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | The deck page states: "The permit fee for most decks under 250 square feet is $75." The... |
| Electrical Permit | It depends | Not specified | MGO 19.11, Group IV, Alterations And Special Fees (repealed and recreated by... |
| Fence Permit | No permit needed | Not specified | No fence permit is issued, so there is no permit fee. |
| HVAC Permit | It depends | Not specified | MGO 30.01(5)(a), Group IV, Alterations and Special Fees (amended by ORD-21-00016... |
| Patio Permit | No permit needed | Not specified | No patio permit is issued, so there is no permit fee. |
| Plumbing Permit | It depends | Not specified | MGO 18.09, Group IV, Alterations And Special Fees (repealed and recreated by... |
| Pool Permit | Permit required | Not specified | "Private in-the-ground swimming pools: $25.00 each permit" (MGO 29.09(3)(a), Group IV... |
| Roof Replacement Permit | Permit required | Not specified | "Alterations and repairs to existing structures: $11.00 for each $1,000 value or... |
| Shed Permit | It depends | shed or accessory building floor area; heated sheds and sheds within ten feet of dwelling units on the property need a permit at any size | "Accessory buildings or detached garage serving a single or two family residential... |
Solar Permit in other Wisconsin localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Madison documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with City of Madison Building Inspection Division, Department of Planning and Community and Economic Development. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Solar Permit requirements across Wisconsin localities
Permit office
City of Madison Building Inspection Division, Department of Planning and Community and Economic Development
608-266-4551Permit portal