Wisconsin / Madison

Electrical Permit in Madison, Wisconsin

It depends

Sometimes, depending on the project

Before starting any electrical installation, wiring, alteration or change other than minor repair work. In an after-hours emergency work may start without a permit number if the number is obtained the morning of the next business day and the application and fees follow within ten days.

Confirmed on official page Verified City of Madison Building Inspection Division, Department of Planning and Community and Economic Development

By Mario Bailey, verified against official sources

Quick answer

Madison requires an electrical permit for all electrical work except a short list of minor repairs, and the Development Services Center chart lists "Electrical Work, All" as Yes. MGO 19.09(2) defines the exemption narrowly: "Minor repair work shall be construed to mean the replacement of broken or defective sockets, snap, push or toggle switches, convenience outlets, lighting fixtures and portable electric appliances." Anything beyond swapping a broken device, including adding outlets or replacing a service panel, needs a permit. The permit must be taken out by a person licensed for the category of work under MGO 19.08 and all applications must be signed by the license holder, but an owner occupant working on an alteration or addition in a single family home can get building and mechanical permits for their own home.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before starting any electrical installation, wiring, alteration or change other than minor repair work. In an after-hours emergency work may start without a permit number if the number is obtained the morning of the next business day and the application and fees follow within ten days.

What an electrical permit costs in Madison

Line item
electrical permitBy formulaMGO 19.11, Group IV, Alterations And Special Fees (repealed and recreated by ORD-21-00026, 3-26-21): "$25.00 first ten (10) openings, $1.00 each additional opening ... Openings include switches, convenience outlets, fixtures, and fixed appliance connections", and "Electric Service Replacement: $50.00 per service panel". New residential wiring is $.09 per sq. ft. with a $25.00 minimum.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Madison

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Madison Building Inspection Division, Department of Planning and Community and Economic Development sets the exact checklist for Madison.

Where to apply in Madison:

City of Madison Building Inspection Division, Department of Planning and Community and Economic Development

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Madison permit portal or by phone at 608-266-4551.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in Madison?
Madison requires an electrical permit for all electrical work except a short list of minor repairs, and the Development Services Center chart lists "Electrical Work, All" as Yes. MGO 19.09(2) defines the exemption narrowly: "Minor repair work shall be construed to mean the replacement of broken or defective sockets, snap, push or toggle switches, convenience outlets, lighting fixtures and portable electric appliances." Anything beyond swapping a broken device, including adding outlets or replacing a service panel, needs a permit. The permit must be taken out by a person licensed for the category of work under MGO 19.08 and all applications must be signed by the license holder, but an owner occupant working on an alteration or addition in a single family home can get building and mechanical permits for their own home. Always confirm with the City of Madison Building Inspection Division, Department of Planning and Community and Economic Development before starting.
How much does an electrical permit cost in Madison?
MGO 19.11, Group IV, Alterations And Special Fees (repealed and recreated by ORD-21-00026, 3-26-21): "$25.00 first ten (10) openings, $1.00 each additional opening ... Openings include switches, convenience outlets, fixtures, and fixed appliance connections", and "Electric Service Replacement: $50.00 per service panel". New residential wiring is $.09 per sq. ft. with a $25.00 minimum. See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Madison?
You can apply through the Madison permit portal or contact the City of Madison Building Inspection Division, Department of Planning and Community and Economic Development directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Madison?
Under Wisconsin law (Wis. Stat. 101.654(1)(a) and (1)(b); Wis. Admin. Code SPS 305.31(1), SPS 320.09(9)(a)2., 3. and 4.; Wis. Stat. 101.65(1m) and (1r); Wis. Stat. 101.862(4)(a); Wis. Stat. 145.06(4)(a)): A Wisconsin homeowner may pull the permit and do the work on their own dwelling. The general rule is that nobody may obtain a building permit for a one- or two-family dwelling without a DSPS dwelling contractor certification plus a dwelling contractor qualifier credential, but the statute exempts an owner of a dwelling who resides or will reside in the dwelling and who applies for a building permit to perform work on that dwelling. Neither the statute nor the implementing rule places any cap on how often that exemption may be used, and Wisconsin has no counterpart to Florida's one-year resale restriction. The trade-off is a disclosure: the permit issuer must have the owner sign a statement warning that if the owner hires a contractor who is not bonded or insured, the owner may be held liable for injury or property damage arising from the work and may be unable to collect damages from that contractor. Trade licensing carries its own homeowner carve-outs, both defeasible by local ordinance: a residential property owner may do electrical wiring on premises the owner owns and occupies as a residence, and a property owner may do plumbing work in a one-family building owned and occupied as the owner's home. Confirm how Madison applies this before you apply.

From the Library

What else needs a permit in Madison

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedThe deck page states: "The permit fee for most decks under 250 square feet is $75." The...
Fence PermitNo permit neededNot specifiedNo fence permit is issued, so there is no permit fee.
HVAC PermitIt dependsNot specifiedMGO 30.01(5)(a), Group IV, Alterations and Special Fees (amended by ORD-21-00016...
Patio PermitNo permit neededNot specifiedNo patio permit is issued, so there is no permit fee.
Plumbing PermitIt dependsNot specifiedMGO 18.09, Group IV, Alterations And Special Fees (repealed and recreated by...
Pool PermitPermit requiredNot specified"Private in-the-ground swimming pools: $25.00 each permit" (MGO 29.09(3)(a), Group IV...
Roof Replacement PermitPermit requiredNot specified"Alterations and repairs to existing structures: $11.00 for each $1,000 value or...
Shed PermitIt dependsshed or accessory building floor area; heated sheds and sheds within ten feet of dwelling units on the property need a permit at any size"Accessory buildings or detached garage serving a single or two family residential...
Solar PermitPermit requiredNot specified"Solar panels or collector system: $21.00 each permit" (MGO 29.09(3)(a), Group IV

Electrical Permit in other Wisconsin localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Madison documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Madison Building Inspection Division, Department of Planning and Community and Economic Development. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page