HVAC Permit in Madison, Wisconsin

It depends

Sometimes, depending on the project

Before installing, altering, repairing or replacing a furnace, boiler, central air conditioner, ductless split system, exhaust system or ventilating system. In a genuine emergency the contractor may start work and file the application within 24 hours, Sundays and city holidays excepted.

Confirmed on official page Verified City of Madison Building Inspection Division, Department of Planning and Community and Economic Development

By Mario Bailey, verified against official sources

Quick answer

Madison requires an HVAC permit for essentially all heating, ventilating and air conditioning work, with one narrow published exemption: no heating permit is needed to install electric baseboard or bathroom heaters used as auxiliary heat to supplement an existing system already sized for the space. The Development Services Center chart lists both "Central Air Conditioner - install" and "Furnace - install" as Yes. The permit application must be submitted by someone holding a valid HVAC certification under Wis. Stat. 101.178(3)(a), except that an owner may do HVAC work in a single-family residence they themselves occupy. A plot plan showing the location of the condensing unit is required with an air conditioning application, and the condenser may not sit in a required front or side yard.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing, altering, repairing or replacing a furnace, boiler, central air conditioner, ductless split system, exhaust system or ventilating system. In a genuine emergency the contractor may start work and file the application within 24 hours, Sundays and city holidays excepted.

What an HVAC permit costs in Madison

Line item
HVAC permitBy formulaMGO 30.01(5)(a), Group IV, Alterations and Special Fees (amended by ORD-21-00016, 3-8-21): "Replacement Heating Equipment: Up to 100,000 BTU $25; 100,001 to 165,000 BTU $50; 165,001 and greater BTU $75"; "Air Conditioning Unit $25 ... The fee applies to any new or replacement air conditioning unit. This fee does not apply to temporary window units"; "Ductless Split System or Wall Pack Unit $25". New residential HVAC is $.09 per sq. ft. with a $25 minimum, and alterations and repairs to existing structures are $11 for each $1,000 of value.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Madison

A residential HVAC (mechanical) permit application must identify the covered equipment and scope of work, since installing, altering, or replacing a heating or cooling system is regulated work that cannot start until the application is submitted and the permit issued. The equipment itself must be picked by a real sizing calculation rather than a rule of thumb.

What most HVAC permit applications include:

  • A mechanical permit is required before anyone may install, alter, repair, remove, convert, or replace a heating, ventilating, or air conditioning system regulated by the code, and the work may not begin until the application is submitted and the permit is issued (IRC R105.1).
  • The application identifies the specific equipment being installed, such as a furnace, heat pump, or air conditioner, since the unit must be installed according to its listing and the manufacturer's installation instructions (IRC M1401.1).
  • The proposed equipment location must leave the clearances needed to clean coils and replace filters, blowers, motors, and controls after installation (IRC M1401.2).
  • The application carries the equipment sizing basis: ACCA Manual J building loads and Manual S equipment selection, or another approved sizing method, not a rule of thumb (IRC M1401.3).
  • For a split system, the work covered by the permit includes refrigerant suction line insulation, since the piping is inspected against that standard once installed (IRC M1411.6).

General submittal guidance from International Residential Code (IRC), 2021 edition, Chapter 1 (Permits) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. City of Madison Building Inspection Division, Department of Planning and Community and Economic Development sets the exact checklist for Madison.

Where to apply in Madison:

City of Madison Building Inspection Division, Department of Planning and Community and Economic Development

Inspections and closing out your permit

Mechanical work gets a rough in inspection after the ductwork, refrigerant lines, and gas piping are in but before they are covered or concealed, followed by a final inspection that confirms the equipment operates correctly and its clearances, combustion air, and condensate disposal are in place. A straight equipment changeout with no new ductwork commonly gets a single final inspection instead of a separate rough in trip.

  1. Rough inspection of the mechanical and gas systems must be made before the work is covered or concealed, before fixtures or appliances are set or installed, and before the framing inspection (IRC R109.1.2).
  2. Where a cooling coil is added to an existing warm air furnace, the rough in confirms the coil is not installed upstream of the heat exchanger unless the furnace is listed for it, and that the blower can handle the added static pressure (IRC M1411.2).
  3. The rough in and final both confirm the appliance access opening and working space are large enough to service the unit (IRC M1305.1).
  4. At final inspection, the inspector verifies the equipment has adequate combustion air, with openings kept clear for the distance the code requires (IRC M1402.3).
  5. Final inspection also checks that the condensate line drains to an approved point of disposal with the required slope and does not create a nuisance (IRC M1411.3).
  6. For a straight equipment changeout with no new ductwork, many permit offices require only a single final inspection, while a new installation still gets a rough in inspection before the final (common local inspection practice).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Madison permit portal or by phone at 608-266-4551.

Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109 (Required Inspections) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an HVAC permit in Madison?
Madison requires an HVAC permit for essentially all heating, ventilating and air conditioning work, with one narrow published exemption: no heating permit is needed to install electric baseboard or bathroom heaters used as auxiliary heat to supplement an existing system already sized for the space. The Development Services Center chart lists both "Central Air Conditioner - install" and "Furnace - install" as Yes. The permit application must be submitted by someone holding a valid HVAC certification under Wis. Stat. 101.178(3)(a), except that an owner may do HVAC work in a single-family residence they themselves occupy. A plot plan showing the location of the condensing unit is required with an air conditioning application, and the condenser may not sit in a required front or side yard. Always confirm with the City of Madison Building Inspection Division, Department of Planning and Community and Economic Development before starting.
How much does an HVAC permit cost in Madison?
MGO 30.01(5)(a), Group IV, Alterations and Special Fees (amended by ORD-21-00016, 3-8-21): "Replacement Heating Equipment: Up to 100,000 BTU $25; 100,001 to 165,000 BTU $50; 165,001 and greater BTU $75"; "Air Conditioning Unit $25 ... The fee applies to any new or replacement air conditioning unit. This fee does not apply to temporary window units"; "Ductless Split System or Wall Pack Unit $25". New residential HVAC is $.09 per sq. ft. with a $25 minimum, and alterations and repairs to existing structures are $11 for each $1,000 of value. See the official fee schedule for current amounts.
Where do you apply for an HVAC permit in Madison?
You can apply through the Madison permit portal or contact the City of Madison Building Inspection Division, Department of Planning and Community and Economic Development directly. The links are listed on this page.
Can a homeowner pull an HVAC permit themselves in Madison?
Under Wisconsin law (Wis. Stat. 101.654(1)(a) and (1)(b); Wis. Admin. Code SPS 305.31(1), SPS 320.09(9)(a)2., 3. and 4.; Wis. Stat. 101.65(1m) and (1r); Wis. Stat. 101.862(4)(a); Wis. Stat. 145.06(4)(a)): A Wisconsin homeowner may pull the permit and do the work on their own dwelling. The general rule is that nobody may obtain a building permit for a one- or two-family dwelling without a DSPS dwelling contractor certification plus a dwelling contractor qualifier credential, but the statute exempts an owner of a dwelling who resides or will reside in the dwelling and who applies for a building permit to perform work on that dwelling. Neither the statute nor the implementing rule places any cap on how often that exemption may be used, and Wisconsin has no counterpart to Florida's one-year resale restriction. The trade-off is a disclosure: the permit issuer must have the owner sign a statement warning that if the owner hires a contractor who is not bonded or insured, the owner may be held liable for injury or property damage arising from the work and may be unable to collect damages from that contractor. Trade licensing carries its own homeowner carve-outs, both defeasible by local ordinance: a residential property owner may do electrical wiring on premises the owner owns and occupies as a residence, and a property owner may do plumbing work in a one-family building owned and occupied as the owner's home. Confirm how Madison applies this before you apply.

From the Library

What else needs a permit in Madison

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedThe deck page states: "The permit fee for most decks under 250 square feet is $75." The...
Electrical PermitIt dependsNot specifiedMGO 19.11, Group IV, Alterations And Special Fees (repealed and recreated by...
Fence PermitNo permit neededNot specifiedNo fence permit is issued, so there is no permit fee.
Patio PermitNo permit neededNot specifiedNo patio permit is issued, so there is no permit fee.
Plumbing PermitIt dependsNot specifiedMGO 18.09, Group IV, Alterations And Special Fees (repealed and recreated by...
Pool PermitPermit requiredNot specified"Private in-the-ground swimming pools: $25.00 each permit" (MGO 29.09(3)(a), Group IV...
Roof Replacement PermitPermit requiredNot specified"Alterations and repairs to existing structures: $11.00 for each $1,000 value or...
Shed PermitIt dependsshed or accessory building floor area; heated sheds and sheds within ten feet of dwelling units on the property need a permit at any size"Accessory buildings or detached garage serving a single or two family residential...
Solar PermitPermit requiredNot specified"Solar panels or collector system: $21.00 each permit" (MGO 29.09(3)(a), Group IV

HVAC Permit in other Wisconsin localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Madison documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Madison Building Inspection Division, Department of Planning and Community and Economic Development. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare HVAC Permit requirements across Wisconsin localities

Look up an existing Madison permit record

It depends
Get quotes