Wisconsin / Milwaukee

Solar Permit in Milwaukee, Wisconsin

Permit required

Yes, a permit is required

Before starting any solar installation; the permit must be approved and issued first, and a separate building permit is required if the roof structure has to be altered to carry the array

From an official source Verified City of Milwaukee Department of Neighborhood Services (DNS), Permit and Development Center

By Mario Bailey, verified against official sources

Quick answer

Every solar project in Milwaukee needs a solar permit, called an ESPV, and it must be approved and issued before installation begins; the Does It Need a Permit page gives the same one-word answer for Solar. The permit is an electrical permit in substance and is priced off system size in kilowatts, and for a house or duplex that needs no structural work there is no separate plan review or building permit fee on top. Residential projects can take an expedited route if the system is under 10 kilowatts, the panels are flush-mounted on the roof, and the total load is under 5 pounds per square foot. An installer with proper credentials compiles the submittal, files through LMS with a line diagram and spec sheets, a plan examiner reviews, fees are paid, and the permit issues. If the roof structure has to be altered to support the array, a building permit is required in addition.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before starting any solar installation; the permit must be approved and issued first, and a separate building permit is required if the roof structure has to be altered to carry the array

What a solar permit costs in Milwaukee

Line item
solar permitBy formulaThe Residential Solar Permit Process sheet (DNS soc 06/02/2021) states "Expedited solar permits cost $70 (with a $10 processing fee)" and lists Electrical Permit Fees for Solar PV of $70 for 0-20 kilowatts, $100 for 20.1-35 kW, $150 for 35.1-50 kW, $200 for 50.1-75 kW, $250 for 75.1-100 kW and $300 over 100 kW, plus a feeder fee of $40 up to 400 amps or $100 for 401-600 amps, each with a 1.6% IT fee and a $10.00 permit processing fee. It also says "There is no Plan Review fee or Building Permit fee for the installation of a solar PV system on 1 or 2-family dwellings not required to undergo structural reinforcement or alterations.".
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Milwaukee

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Milwaukee Department of Neighborhood Services (DNS), Permit and Development Center sets the exact checklist for Milwaukee.

Where to apply in Milwaukee:

City of Milwaukee Department of Neighborhood Services (DNS), Permit and Development Center

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Milwaukee permit portal or by phone at 414-286-8210.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Milwaukee?
Every solar project in Milwaukee needs a solar permit, called an ESPV, and it must be approved and issued before installation begins; the Does It Need a Permit page gives the same one-word answer for Solar. The permit is an electrical permit in substance and is priced off system size in kilowatts, and for a house or duplex that needs no structural work there is no separate plan review or building permit fee on top. Residential projects can take an expedited route if the system is under 10 kilowatts, the panels are flush-mounted on the roof, and the total load is under 5 pounds per square foot. An installer with proper credentials compiles the submittal, files through LMS with a line diagram and spec sheets, a plan examiner reviews, fees are paid, and the permit issues. If the roof structure has to be altered to support the array, a building permit is required in addition. Always confirm with the City of Milwaukee Department of Neighborhood Services (DNS), Permit and Development Center before starting.
How much does a solar permit cost in Milwaukee?
The Residential Solar Permit Process sheet (DNS soc 06/02/2021) states "Expedited solar permits cost $70 (with a $10 processing fee)" and lists Electrical Permit Fees for Solar PV of $70 for 0-20 kilowatts, $100 for 20.1-35 kW, $150 for 35.1-50 kW, $200 for 50.1-75 kW, $250 for 75.1-100 kW and $300 over 100 kW, plus a feeder fee of $40 up to 400 amps or $100 for 401-600 amps, each with a 1.6% IT fee and a $10.00 permit processing fee. It also says "There is no Plan Review fee or Building Permit fee for the installation of a solar PV system on 1 or 2-family dwellings not required to undergo structural reinforcement or alterations.". See the official fee schedule for current amounts.
Where do you apply for a solar permit in Milwaukee?
You can apply through the Milwaukee permit portal or contact the City of Milwaukee Department of Neighborhood Services (DNS), Permit and Development Center directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Milwaukee?
Under Wisconsin law (Wis. Stat. 101.654(1)(a) and (1)(b); Wis. Admin. Code SPS 305.31(1), SPS 320.09(9)(a)2., 3. and 4.; Wis. Stat. 101.65(1m) and (1r); Wis. Stat. 101.862(4)(a); Wis. Stat. 145.06(4)(a)): A Wisconsin homeowner may pull the permit and do the work on their own dwelling. The general rule is that nobody may obtain a building permit for a one- or two-family dwelling without a DSPS dwelling contractor certification plus a dwelling contractor qualifier credential, but the statute exempts an owner of a dwelling who resides or will reside in the dwelling and who applies for a building permit to perform work on that dwelling. Neither the statute nor the implementing rule places any cap on how often that exemption may be used, and Wisconsin has no counterpart to Florida's one-year resale restriction. The trade-off is a disclosure: the permit issuer must have the owner sign a statement warning that if the owner hires a contractor who is not bonded or insured, the owner may be held liable for injury or property damage arising from the work and may be unable to collect damages from that contractor. Trade licensing carries its own homeowner carve-outs, both defeasible by local ordinance: a residential property owner may do electrical wiring on premises the owner owns and occupies as a residence, and a property owner may do plumbing work in a one-family building owned and occupied as the owner's home. Confirm how Milwaukee applies this before you apply.

From the Library

What else needs a permit in Milwaukee

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsNot specifiedBilled as an alteration: "The fee for all alterations, remodeling, repairs and repairing...
Electrical PermitIt dependsNot specifiedElectrical permit fees are not reproduced in the Plan Review and Permit Fees schedule
Fence PermitPermit requiredNot specifiedThe Plan Review and Permit Fees schedule (As of January 1, 2025
HVAC PermitIt dependsNot specifiedHVAC Permit Fees, excerpted in the fee schedule from MCO 200-33-23: heating, incinerator...
Patio PermitNo permit neededNot specifiedNo permit and therefore no DNS permit fee.
Plumbing PermitIt dependsNot specifiedPlumbing permit fees are set by MCO 200-33 and are not reproduced in the Plan Review and...
Pool PermitIt dependspool at least 15 feet by 3 feet in size or holding 3,965 gallonsThe DNS Private Pool Instruction Sheet (soc 03/18/25) instructs applicants to "Submit a...
Roof Replacement PermitIt dependsNot specifiedNo permit fee for a one- or two-family re-roof, because no permit is required.
Shed PermitIt dependsdetached tool or storage sheds located in the rear yard and at least three feet from the property linesUnder Structures Accessory to One-and 2-family Dwellings in the Plan Review and Permit...

Solar Permit in other Wisconsin localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Milwaukee documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Milwaukee Department of Neighborhood Services (DNS), Permit and Development Center. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page