Shed Permit in Philadelphia, Pennsylvania

It depends

Sometimes, depending on the project

For sheds 200 sq ft or larger

Confirmed on official page Verified

Issued byDepartment of Licenses and Inspections

By Mario Bailey, verified against official sources

Quick answer

Philadelphia L&I does not require a permit for detached structures such as sheds that are under 200 square feet on one-or-two-family residential properties. Sheds of 200 square feet or larger require a building permit. Apply through the eCLIPSE portal.

Typical threshold: detached structures under 200 sq ft for one-or-two-family dwellings do not require a permit.

Diagram of the 200 sq ft footprint area threshold for a shed permit in Philadelphia, Pennsylvania
Threshold illustrated: 200 sq ft. Whether Philadelphia requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-06-18.

Who is pulling this permit?

Hire it out

Sponsored

If a contractor builds or places your shed, they usually handle any required permit. Compare a few bids before you commit.

Compare contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

For sheds 200 sq ft or larger

What a shed permit costs in Philadelphia

Line item
shed permitBy formulaSheds 120 sq ft or less in the rear yard need no permit; larger sheds pay the new accessory structure fee of $75 for the first 500 sq ft plus $56 per additional 100 sq ft, per the L&I construction fee schedule effective 1/1/2025.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Philadelphia compares in Pennsylvania

Closest shed permit thresholds outside Pennsylvania

Jurisdictions we cover whose limit sits nearest Philadelphia's 200 sq ft.

  • Austin, Texas, one-story detached accessory structures used as tool or storage sheds with floor area no greater than 200 sq ft and no more than 15 ft in height and no plumbing and not in a floodplain are exempt
  • Baton Rouge, Louisiana, floor area of a detached accessory structure
  • Bellevue, Washington, detached storage sheds playhouses or gazebos with a floor area of 200 square feet or less do not require a building permit; structures over 200 square feet require a permit
  • Clark County, Nevada, sheds over 200 sq ft require a building permit; storage sheds 200 sq ft or under may be exempt under Building Administrative Code Section 22.02.190

How to apply in Philadelphia

In Philadelphia, a residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • For Philadelphia, a written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • For Philadelphia, a scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Department of Licenses and Inspections sets the exact checklist for Philadelphia.

Where to apply in Philadelphia:

Department of Licenses and Inspections

  • 1401 John F. Kennedy Blvd., MSB, Philadelphia, PA 19102
  • Phone: (215) 255-4040

Shed Permit in Philadelphia compared with nearby Pennsylvania localities

LocalityPermit needed?ThresholdWhat each Pennsylvania schedule saysVerified
PhiladelphiaIt dependsdetached structures under 200 sq ft for one-or-two-family dwellings do not require a permitSheds 120 sq ft or less in the rear yard need no permit
PittsburghIt dependsfloor area of a one-story detached accessory structure accessory to a single-family or two-family dwelling2026 PLI Fee Schedule, effective 1/1/2026: "Base Permit Fee (Residential) $6.00 per...

Inspections and closing out your permit

In Philadelphia, a permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection in Philadelphia: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection in Philadelphia: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection in Philadelphia: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. In Philadelphia: for a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Philadelphia permit portal or by phone at (215) 255-4040.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Philadelphia

In 2024, Philadelphia authorized permits for 2,962 new residential housing units (539 single-family, 2,423 in multi-family buildings), valued at $498M, down from 3,863 the year before. That works out to about 1.9 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 1,578,487.

About Philadelphia

Philadelphia has about 739,725 housing units. The median home is valued at $232,400, against a median household income of $60,698. About 52% of homes are owner-occupied, and the typical home was built around 1949.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a shed permit in Philadelphia?
Philadelphia L&I does not require a permit for detached structures such as sheds that are under 200 square feet on one-or-two-family residential properties. Sheds of 200 square feet or larger require a building permit. Apply through the eCLIPSE portal. Detached structures under 200 sq ft for one-or-two-family dwellings do not require a permit. Always confirm with the office before starting.
How much does a shed permit cost in Philadelphia?
Sheds 120 sq ft or less in the rear yard need no permit; larger sheds pay the new accessory structure fee of $75 for the first 500 sq ft plus $56 per additional 100 sq ft, per the L&I construction fee schedule effective 1/1/2025. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Philadelphia?
You can apply through the Philadelphia permit portal or contact the Department of Licenses and Inspections directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Philadelphia?
Under Pennsylvania law (34 Pa. Code 403.62(a); Act 132 of 2008 (HICPA), Section 2 (73 P.S. 517.2)): Yes. 34 Pa. Code 403.62(a) provides that 'An owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a residential building or erect, install, enlarge, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system regulated by the Uniform Construction Code shall first apply to the building code official and obtain the required permit.' The owner is a permitted applicant. The Home Improvement Consumer Protection Act (Act 132 of 2008, 73 P.S. 517.1 et seq.) is a registration and consumer-protection law for contractors: its 'Contractor' definition covers a person 'who owns and operates a home improvement business or who undertakes, offers to undertake or agrees to perform any home improvement,' so it governs people doing home improvements for others, not homeowners doing their own work. Pennsylvania has no statewide trade licensing barring homeowner work; trade licensing, where it exists, is municipal. Confirm how Philadelphia applies this before you apply.

From the Library

What else needs a permit in Philadelphia

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsNot specifiedBilled as a plumbing alteration permit at $50 for the first 7 fixtures plus $22.50 per...
Deck PermitIt dependsresidential decks up to 216 sq ft (excluding roof decks) qualify for EZ permit without plans; larger decks require full building permit with plansNew decks fall under the accessory structure and addition bucket at $75 for the first...
Electrical PermitPermit requiredNot specified$100 filing fee (nonrefundable)
EV Charger PermitIt dependsNot specifiedCharged as a standard electrical permit at $25 per $1,000 of estimated cost with a $63...
Fence PermitIt dependspermit required if fence exceeds 6 feet tall, is masonry over 2 ft, is on Historic Registry, or is in the 100-year floodplainZoning permit $50-$632 by lot size
HVAC PermitPermit requiredNot specified$100 filing fee (nonrefundable)
Patio PermitIt dependsconcrete or other hard-surface paving on grade (driveways, walkways, patios not used for parking) is exempt; covered or elevated patio structures require a permit, and paving in flood protection areas requires oneNo fee
Plumbing PermitPermit requiredNot specified$100 filing fee (nonrefundable)
Pool PermitIt dependsprefabricated swimming pools or spas less than 24 inches deep AND less than 5000 gallons do not require a permit; all larger pools require a permitFlat $69 building permit fee for a pool or spa accessory to a one or two family...
Roof Replacement PermitPermit requiredNot specifiedFlat $69 building permit fee to replace the roof covering on a one or two family...
Solar PermitPermit requiredNot specifiedFlat $200 building permit fee for the solar panel structure plus a separate electrical...
Water Heater PermitPermit requiredNot specifiedFlat $31 plumbing permit fee to replace a water heater in a one or two family dwelling...

Shed Permit in other Pennsylvania localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Philadelphia documents; the office above sets the local rules.

How this shed permit page for Philadelphia was verified. 2 official sources: phila.gov, phila.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Department of Licenses and Inspections. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Shed Permit requirements across Pennsylvania localities

Shed permit rules nationwide

Look up an existing Philadelphia permit record

It depends