Pennsylvania / Philadelphia

Solar Permit in Philadelphia, Pennsylvania

By Mario Bailey Last checked 2026-06-18 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

Both an electrical permit and a building permit are required for residential solar installations in Philadelphia. Systems of 10 kW or less on 1-2 family homes not on the Historic Registry qualify for an EZ permit (electrical permit only; no building permit or plans needed). All solar installations require submitting a private interconnection application to PECO before applying for permits.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Philadelphia, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before installing any residential solar PV system

What solar permit costs in Philadelphia

Flat $200 building permit fee for the solar panel structure plus a separate electrical permit at $25 per $1,000 of cost, per the city's solar permit page.

Official fee schedule

How to apply in Philadelphia

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Department of Licenses and Inspections sets the exact checklist for Philadelphia.

Where to apply in Philadelphia:

Department of Licenses and Inspections

  • 1401 John F. Kennedy Blvd., MSB, Philadelphia, PA 19102
  • Phone: (215) 255-4040

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Philadelphia permit portal or by phone at (215) 255-4040.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Philadelphia

In 2024, Philadelphia authorized permits for 2,962 new residential housing units (539 single-family, 2,423 in multi-family buildings), valued at $498M, down from3,863 the year before. That works out to about 1.9 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 1,578,487.

About Philadelphia

Philadelphia has about 739,725 housing units. The median home is valued at $232,400, against a median household income of $60,698. About 52% of homes are owner-occupied, and the typical home was built around 1949.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a solar permit in Philadelphia?
Both an electrical permit and a building permit are required for residential solar installations in Philadelphia. Systems of 10 kW or less on 1-2 family homes not on the Historic Registry qualify for an EZ permit (electrical permit only; no building permit or plans needed). All solar installations require submitting a private interconnection application to PECO before applying for permits. Always confirm with the Department of Licenses and Inspections before starting.
How much does a solar permit cost in Philadelphia?
Flat $200 building permit fee for the solar panel structure plus a separate electrical permit at $25 per $1,000 of cost, per the city's solar permit page. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Philadelphia?
You can apply through the Philadelphia permit portal or contact the Department of Licenses and Inspections directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Philadelphia?
Under Pennsylvania law (34 Pa. Code 403.62(a); Act 132 of 2008 (HICPA), Section 2 (73 P.S. 517.2)): Yes. 34 Pa. Code 403.62(a) provides that 'An owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a residential building or erect, install, enlarge, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system regulated by the Uniform Construction Code shall first apply to the building code official and obtain the required permit.' The owner is a permitted applicant. The Home Improvement Consumer Protection Act (Act 132 of 2008, 73 P.S. 517.1 et seq.) is a registration and consumer-protection law for contractors: its 'Contractor' definition covers a person 'who owns and operates a home improvement business or who undertakes, offers to undertake or agrees to perform any home improvement,' so it governs people doing home improvements for others, not homeowners doing their own work. Pennsylvania has no statewide trade licensing barring homeowner work; trade licensing, where it exists, is municipal. Confirm how Philadelphia applies this before you apply.

From the Library

What else needs a permit in Philadelphia

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsNot specifiedBilled as a plumbing alteration permit at $50 for the first 7 fixtures plus $22.50 per...
Deck PermitIt dependsresidential decks up to 216 sq ft (excluding roof decks) qualify for EZ permit without plans; larger decks require full building permit with plansNew decks fall under the accessory structure and addition bucket at $75 for the first 5...
Electrical PermitPermit requiredNot specified$100 filing fee (nonrefundable);
EV Charger PermitIt dependsNot specifiedCharged as a standard electrical permit at $25 per $1,000 of estimated cost with a $63...
Fence PermitIt dependspermit required if fence exceeds 6 feet tall, is masonry over 2 ft, is on Historic Registry, or is in the 100-year floodplainZoning permit $50-$632 by lot size;
HVAC PermitPermit requiredNot specified$100 filing fee (nonrefundable);
Patio PermitIt dependsconcrete or other hard-surface paving on grade (driveways, walkways, patios not used for parking) is exempt; covered or elevated patio structures require a permit, and paving in flood protection areas requires oneNo fee;
Plumbing PermitPermit requiredNot specified$100 filing fee (nonrefundable);
Pool PermitIt dependsprefabricated swimming pools or spas less than 24 inches deep AND less than 5000 gallons do not require a permit; all larger pools require a permitFlat $69 building permit fee for a pool or spa accessory to a one or two family dwellin...
Roof Replacement PermitPermit requiredNot specifiedFlat $69 building permit fee to replace the roof covering on a one or two family dwelli...
Shed PermitIt dependsdetached structures under 200 sq ft for one-or-two-family dwellings do not require a permitSheds 120 sq ft or less in the rear yard need no permit;
Water Heater PermitPermit requiredNot specifiedFlat $31 plumbing permit fee to replace a water heater in a one or two family dwelling,...

Official sources

Verified by a person against the sources above on 2026-06-18, not confirmed with Department of Licenses and Inspections. Rules change; confirm before you build. How we verify.