New York / New York City

Solar Permit in New York City, New York

It depends

Sometimes, depending on the project

Before installing, altering or removing a rooftop or site solar photovoltaic or solar thermal system. Only solar landscape lights are exempt.

Quick answer

DOB states that no solar work may be performed without a work permit, a Licensed Contractor and a Registered Design Professional, the single exception being solar landscape lights, which a building owner may install. A licensed Professional Engineer or Registered Architect must prepare and submit the construction documents, including a structural analysis showing the existing structure can carry the added panel weight, and must perform the final inspection. Since November 15, 2023 solar filings must be made in DOB NOW: Build as an Alteration with work type Solar, and every solar filing needs an associated electrical filing by a licensed electrician using category Sustainable Energy Installs and sustainable type Photo Voltaic. DOB will not issue the solar permit until the electrical permit has been issued. The New York State property tax abatement is now requested inside the same DOB NOW filing rather than on a separate PTA4 form.

Typical threshold
solar landscape lights are the only solar work DOB exempts from permit
Issued by
New York City Department of Buildings (DOB)
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?

New York's owner-builder rule (Inside New York City: NYC Admin. Code 28-104.1, 28-105.1, 28-105.4, 28-105.5.1, 28-401.3 (definition of "general contractor"). Outside New York City: N.Y. Exec. Law 381(2); 19 NYCRR 1203.3(a)(1).) sets what you may do on your own home without hiring anyone. Read the statute.

What a solar permit costs in New York City

Fee schedule in force
Official scheduleRead .
  • Solar Panels is work type SL, an alteration priced on construction cost and requiring a PW3 statement of cost per DOB's "Fee Structure & List of Applications Requiring a PW3" (Rev. 04/25).
  • For a one-, two- or three-family dwelling that means Table 28-112.2 item 11: minimum filing fee $170.00 for Alteration Type 1 or $130.00 for Alteration Type 2 or Type 3, being the "Minimum filing fee for the first $5,000, or fraction thereof, of the cost of alteration; plus $2.60 for each $1,000, or fraction thereof, of cost of alterations in excess of $5,000."
  • The mandatory companion electrical permit is billed separately under 1 RCNY 101-03.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How New York City compares in New York

No New York jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
BuffaloPermit requiredResidential building permit fee schedule flat fee line "Alternative energy systems" $75.00 on top of the $25.00 application fee, EFFECTIVE 7/1/2025
New York Citythis pageIt dependsSee schedule
RochesterPermit requiredThe Solar JULY 2026 packet states "Unified Fee $100" by check or money order payable to the City Treasurer; the schedule has the rest
Town of BrookhavenPermit requiredTown of Brookhaven Building Division Fee Schedule 2026, Construction table: "Solar Panel (Residential) $135"
Town of HempsteadPermit requiredSee schedule

How to apply in New York City

General guide, not specific to this office

What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

New York City Department of Buildings (DOB)

  • 280 Broadway, New York, NY 10007
  • Phone: (212) 566-5000

What else needs a permit in New York City

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeSee schedule
Electrical PermitIt dependsBefore any new installation, alteration or repair of electric wires, wiring apparatus...See schedule
Fence PermitIt dependsfences accessory to one- and two-family dwellings, measured from the higher of the two adjoining gradesSee schedule
HVAC PermitIt dependspackaged air-conditioning units installed in an existing one- or two-family dwelling that are not part of an alteration otherwise requiring a permit; the same exemption is capped at 3 tons in all other buildingsSee schedule
Plumbing PermitIt dependsdirect replacement of an existing fixture or faucet that does not alter the hot and cold shutoff valves or the fixture trapTable 28-112.2 item 11 sets the one-, two- or three-family LAA minimum filing fee at $130.00; the schedule has the rest
Pool PermitIt dependsoutdoor in-ground or above-ground pools accessory to a one- or two-family dwelling, where the distance from the edge of an in-ground pool to any building or lot line exceeds the depth of the deepest part of the pool and a slop sink for indirect waste already exists or is installed under a plumbing permitSee schedule
Roof Replacement PermitIt dependsthe permit requirement turns on whether the roof deck or sheathing is replaced, and on whether the NYC Energy Conservation Code calls for additional thermal insulationSee schedule
Shed PermitIt dependstemporary portable freestanding sheds accessory to a one- or two-family dwelling that are also no more than 7 feet 6 inches high, at least 3 feet from every lot line, used for household storage, do not obstruct a required window, and are the only such shed on the tax lotSee schedule

Frequently asked questions

Do you need a solar permit in New York City?
It depends on the project. Solar landscape lights are the only solar work DOB exempts from permit. If you are unsure how that applies to your project, call the permit office at (212) 566-5000 before you start.
How much does a solar permit cost in New York City?
The fee wording from the official schedule is in the cost table on this page, as we read it on 15 Aug 2026. For the figure on your own project, call the permit office at (212) 566-5000.
Where do you apply for a solar permit in New York City?
You can apply through the New York City permit portal or contact the New York City Department of Buildings (DOB) directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in New York City?
Under New York law (Inside New York City: NYC Admin. Code 28-104.1, 28-105.1, 28-105.4, 28-105.5.1, 28-401.3 (definition of "general contractor"). Outside New York City: N.Y. Exec. Law 381(2); 19 NYCRR 1203.3(a)(1).): New York State sets no owner-builder rule at all outside New York City. Executive Law 381(2) puts administration and enforcement in the hands of each local government, and 19 NYCRR 1203.3(a)(1) only requires each authority having jurisdiction to make building permits mandatory for work that must conform to the codes, leaving who may apply to local law. The state licenses no general contractors and imposes no owner-builder affidavit, disclosure form or post-permit sale restriction of the kind Florida uses, so whether a homeowner may pull the permit is a question for the specific city, town, village or county. New York City is the genuine outlier. Administrative Code 28-105.1 makes the work itself unlawful without a written permit, and Administrative Code 28-104.1 bars the department from issuing that permit until it approves the required construction documents, which must be prepared by or under the supervision of a registered design professional, meaning a licensed architect or engineer, as required by the code. A homeowner therefore cannot self-prepare and file the plans for permit-requiring work in New York City even though Administrative Code 28-105.5.1 defines the permit applicant as the person who performs the work or retains a subcontractor, and even though the general contractor registration definition in Administrative Code 28-401.3 expressly excludes an individual who constructs a residential structure of no more than three dwelling units for his or her own occupancy. Note that Administrative Code 28-105.4 exempts minor alterations and ordinary repairs from the permit requirement entirely, so the design professional bottleneck applies only to work that needs a permit in the first place. Confirm how New York City applies this before you apply.

From the Library

Solar Permit in other New York localities

Everything above, sourced

How this solar permit page for New York City was verified. 2 official sources: nyc.gov, nyc.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with New York City Department of Buildings (DOB). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page