Do You Need a Permit for Grading, Fill Dirt or Landscaping?

Planting and ordinary landscaping rarely need one. Moving earth does once you pass a line measured in cubic yards or square feet disturbed, and offices draw it anywhere from any fill at all (Anchorage) or 10 cubic yards (Boise, Portland) to half an acre (Jefferson County, Colorado). How to estimate your volume, the state erosion rules in Virginia, Maryland and Pennsylvania, Wisconsin's dig notice and what a grading permit costs in Wichita.

Not for planting beds, sod, mulch or a garden. Virginia’s erosion law spells that out, excusing “Minor land-disturbing activities, including home gardens and individual home landscaping, repairs, and maintenance work.” A permit comes in when you move enough soil: regrading a yard, hauling in fill to level it, cutting into a slope or digging a large hole. Most offices that regulate it use a number, either cubic yards of earth moved or square feet of ground disturbed, and the numbers are far apart; a few, such as Anchorage, require a grading permit for any fill or excavation.

Planting and ordinary landscaping
No permit in the rules we readVa. Code 62.1-44.15:34(F)(1) names it
Smallest triggers we found
Any fill (Anchorage); 10 cubic yardsBoise, Portland; Ann Arbor at 225 sq ft disturbed
Volume line in three offices
50 cubic yardsSaint Paul, Cheyenne, Kansas City (with conditions)
State erosion plan lines
2,500 to 10,000 sq ftVirginia; Maryland and Pennsylvania at 5,000
Before any digging
Call 811Wisconsin: at least 3 working days ahead

Work out your number before you call: measure the area you will change, multiply by the average depth of cut or fill in feet, and divide by 27 to get cubic yards. Raising a 20 by 30 foot area by 6 inches is 300 cubic feet, about 11 cubic yards; a 40 by 60 foot area raised a foot is about 89. Then ask the office: “I plan to [fill / regrade / excavate] about [area] square feet at [address], moving about [volume] cubic yards, with the deepest [cut / fill] at [depth] feet. Do I need a grading permit, a land disturbance or erosion control permit, or a stormwater review, and does any of the work fall in a floodplain or near a stream?”

Where offices draw the line

These are the triggers in rules we read, from the smallest to the largest. Anchorage, Boise, Saint Paul, Cheyenne, Kansas City, Ann Arbor, Lexington, Arlington County and Jefferson County are cited from their rows in our verified dataset; Portland’s page and the state rules were read today.

WhereWhat triggers review
Anchorage, AlaskaAll fill and excavation (grading permit)
Portland, Oregon”Move more than 10 cubic yards of earth” (site development)
Boise, IdahoExcavating more than 10 cubic yards (erosion and sediment control permit)
Saint Paul, MinnesotaMoving more than 50 cubic yards of fill (grading permit)
Cheyenne, WyomingMoving more than 50 cubic yards of material on a residential project
Kansas City, MissouriGrading outside nine exemptions, including a cut under 2 feet and a fill under 1 foot (or under 3 feet if no more than 50 cubic yards on the lot and not supporting a structure)
Ann Arbor, MichiganAny earth change, unless it disturbs less than 225 square feet in an isolated, self-contained area
Lexington, KentuckyGrading over 1,500 square feet (land disturbance permit; recorded for pools)
Arlington County, Virginia2,500 square feet of disturbance (2,000 to 2,499 needs a certification and perimeter controls)
Maryland, statewideAn erosion and sediment control plan for grading, except work that disturbs “less than 5,000 square feet of land area and disturb less than 100 cubic yards of earth” (COMAR 26.17.01.05); Montgomery County lists “Land Disturbance (greater than 5,000 square feet or 100 cubic yards or more of earth movement)” among work needing a permit
Pennsylvania, statewideA written E&S Plan at “a total earth disturbance of 5,000 square feet (464.5 square meters) or more” (25 Pa. Code 102.4(b)(2)(i))
Virginia, statewide10,000 square feet, “although the locality may reduce this regulatory threshold”; 2,500 square feet in a Chesapeake Bay Preservation Area, including for single-family homes
Jefferson County, ColoradoGrading more than half an acre (separate grading permit)

Two things stand out. First, a volume line and an area line catch different jobs: spreading 2 inches of topsoil over 6,000 square feet is only about 37 cubic yards but disturbs more than 5,000 square feet, so it passes Saint Paul’s 50 cubic yard test while landing on Maryland’s area line. Second, Maryland’s exemption needs both numbers under the limit: the regulation says the work must disturb “less than 5,000 square feet of land area and disturb less than 100 cubic yards of earth,” so a deep cut on a small footprint can still need a plan.

Pennsylvania adds a duty that applies below its plan line. Even for work under 5,000 square feet, “The implementation and maintenance of E&S BMPs are required to minimize the potential for accelerated erosion and sedimentation.” In plain terms: silt fence, straw or a stabilized entrance is expected on any job, permit or not.

Fill dirt has rules of its own

Offices that regulate grading count soil you bring in, as Saint Paul’s 50 cubic yards of fill and Kansas City’s fill-depth limits show, and fill raises two extra questions. Where will the water go once the grade changes, and is the lot in a floodplain? Buffalo’s shed exemption, in our dataset, carries a condition worth applying to any yard work: an exempt structure still may not alter drainage to a neighbor’s detriment. St. Johns County, Florida’s floodplain management code, as recorded in our dataset, regulates fill in its Coastal High Hazard Areas and Coastal A Zones. If your lot is mapped in a flood zone, ask the floodplain administrator before any fill arrives, not after.

Digging: call first, whatever the size

Every excavation, even a fence post or a planting hole for a tree, can hit a buried line. Wisconsin’s statute requires an excavator to “Provide advance notice not less than 3 working days before the start of nonemergency excavation to the one-call system,” and Sterling Heights, Michigan, prints “Verify underground utilities - Call Miss Dig” on its shed and garage guide. The one-call notice is separate from any permit, and 811 is the number to start from.

What a grading permit costs

Wichita charges, in Tables D and E of its building code, no plan review fee and a $25.00 permit fee for 50 cubic yards or less, and a $25.00 plan review fee plus a $40.00 permit fee for 51 to 100 cubic yards, so an 80 cubic yard fill there costs $65 if it needs a permit. Whether a given job in Wichita needs one is set elsewhere in its rules; the tables only price it.

When it becomes a different project

  • A wall to hold the new grade is a retaining wall question; our guide to retaining wall height compares 12 rules.
  • A patio or slab on the new grade: see pouring a concrete slab, which covers the impervious surface reviews.
  • A driveway or a new curb cut: see our driveway permit guide.
  • A drain pipe, a sump discharge or a culvert: see our guide to French drains, sump pumps and culverts.
  • Taking out trees can need a tree permit, or in King County, Washington, a clearing permit for a hazard tree; see our guide to tree removal permits.
  • A pool: the excavation can need its own grading or erosion permit, as it does in Boise, Saint Paul, Lexington and Spotsylvania County, as recorded in our dataset; see why a pool permit is rarely one permit.
  • A pond: the depth can make it a pool case, and an earth bank across a stream can make it a dam under state law; see our pond guide.

Method

We read the Virginia statute, the Maryland and Pennsylvania regulations, the Wisconsin statute, Wichita’s fee tables, Montgomery County’s permit list, Portland’s residential permits page and Sterling Heights’ shed and garage guide on their official sites on November 18, 2026; they are the source of every quote and of the fee example. The other local triggers come from our verified dataset: 37 rows mention grading, excavation, an earth change, erosion control, land disturbance or a site development permit; Anchorage’s rule sits in its rows’ notes, and Buffalo, St. Johns County, Spotsylvania County and the pool rows are cited for drainage, flood and pool rules. Each office’s page here carries its read date. The volume examples are our arithmetic (27 cubic feet to a cubic yard). We did not read wetland, stream buffer or shoreland rules for this guide; work near water usually has its own permits, so ask the office about them.

Do You Need a Permit for Grading, Fill Dirt or Landscaping?: figures as of 28 Sep 2026, 137 jurisdictions. Now 178.

Sources

Get rule-change alerts

We catch permit rule and fee changes in our verification passes and post them to the rule tracker. Get them by email instead.

We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.