Patio Permit in Portland, Oregon
It depends
Sometimes, depending on the project
Before adding or enlarging an attached patio cover, porch cover, or carport larger than 200 square feet, before enclosing an existing patio cover, and before pouring a patio slab more than 30 inches above adjacent grade or over a story or basement.
By Mario Bailey, verified against official sources
Quick answer
Portland does not require a building permit for a plain concrete patio poured on grade; the city instead tells you to contact Planning and Zoning to find out whether a zoning permit is needed. A building permit is required once a patio is covered and the attached patio cover, porch cover, or carport is larger than 200 square feet, or once an existing patio cover is enclosed. A patio slab also needs a permit if it sits more than 30 inches above adjacent grade or over any story or basement. Covers not over 200 square feet and supported by an exterior building wall are listed as work that does not need a building permit.
Typical threshold: area of an attached patio cover, porch cover, carport, or other open-sided roofed structure.

Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before adding or enlarging an attached patio cover, porch cover, or carport larger than 200 square feet, before enclosing an existing patio cover, and before pouring a patio slab more than 30 inches above adjacent grade or over a story or basement.
What a patio permit costs in Portland
How Portland compares in Oregon
Closest patio permit thresholds outside Oregon
Jurisdictions we cover whose limit sits nearest Portland's 200 sq ft.
- Corpus Christi, Texas, Every attached patio cover or carport needs a permit regardless of size; a detached patio cover or carport needs one once it is larger than 200 square feet.
- Dallas, Texas, detached patio covers of 200 sq ft or less on single-family or duplex premises are exempt; attached patio covers and those over 200 sq ft require a permit
- Gilbert, Arizona, Only one-story detached non-habitable accessory structures up to 200 square feet are exempt from permit; attached patio covers and larger structures require a building permit.
- Sacramento County, California, floor area of a detached, not fully enclosed patio cover, pergola, arbor or trellis that is also no taller than 12 feet and stands 5 feet or more from the property line
How to apply in Portland
Applying for a patio permit means submitting a site plan and framing plans for a roofed patio cover, since a cover is treated as its own permitted structure regardless of size. A plain concrete or paver patio slab at or near grade is, by contrast, often exempt from that same building permit requirement.
What most patio permit applications include:
- Filing a permit application with the local building department, which only the property owner or an authorized agent may sign, since a patio cover is treated as its own permitted structure regardless of size (IRC R105.1).
- A scaled site plan showing the new patio cover's size and location relative to the house and other existing structures, with dimensioned distances to all property lines so required setbacks can be verified before the permit is approved (IRC R106.2).
- Construction documents such as a framing plan and elevation, showing rafter or beam sizes and spacing, the distance between supporting posts, and the method of attachment to the house, drawn with enough clarity for the building official to confirm the work will conform to the code (IRC R106.1).
- For the roof structure itself, plans showing compliance with the patio cover appendix's structural limits, such as adequate footing sizes for the applied post loads, since a shallow slab on grade may substitute for a deeper footing only in limited cases up to about 750 pounds of load per post (IRC Appendix AH, Section AH105.2).
- By contrast, an at grade concrete or paver patio that is not attached to the dwelling and stays within the code's small flatwork thresholds, similar to a sidewalk, driveway, or low deck under 200 square feet and 30 inches high, commonly needs no building permit at all, so none of the plan review steps above apply (IRC R105.2).
General submittal guidance from 2021 International Residential Code (IRC), Sections R105 and R106, with Appendix AH Patio Covers (named Appendix H in the 2012, 2015, and 2018 editions). Source. Portland Permitting & Development sets the exact checklist for Portland.
Where to apply in Portland:
Portland Permitting & Development
- Development Services Center, 1900 SW Fourth Avenue, First floor lobby, Portland, OR 97201
- Phone: 503-823-7300
- Email: permittingservices@portlandoregon.gov
Inspections and closing out your permit
A permitted patio cover follows the same footing, frame, and final inspection sequence used for any small accessory structure, since the posts and roof framing have to be checked before they are covered and again once the work is done. An at grade patio slab that qualifies as exempt flatwork usually needs no building inspection at all, because inspections only attach to work that required a permit in the first place.
- A footing inspection once the excavation, forms, and any reinforcing steel are in place but before concrete is poured, confirming the posts supporting a patio cover will bear on adequate footings (IRC R109.1.1).
- A frame inspection after the rafters, beams, posts, and any required rough in work are in place but before the roof sheathing or covering material conceals them, since a solid patio cover roof cannot be signed off once it is covered without this check (IRC R109.1.4).
- A final inspection once all permitted work, including roofing and post anchorage, is complete, which the code requires before the structure may be used (IRC R109.1.6).
- An at grade concrete or paver patio that qualifies as exempt flatwork under the permit rules is not subject to any of these inspection stages, since the inspection sequence only attaches to work that required a permit in the first place (IRC R105.2).
- Each inspection has to be requested by the permit holder rather than happening automatically, and the approved plans and permit card need to be on site and available when the inspector arrives (IRC R109.3).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Portland permit portal or by phone at 503-823-7300.
Inspection sequence from 2021 International Residential Code (IRC), Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Patio Permit checklist for Portland
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: area of an attached patio cover, porch cover, carport, or other open-sided roofed structure. Usually needed: Before adding or enlarging an attached patio cover, porch cover, or carport larger than 200 square feet, before enclosing an existing patio cover, and before pouring a patio slab more than 30 inches above adjacent grade or over a story or basement.
- Budget the fee. Building and Other Permits Fee Schedule for the City of Portland, effective July 10, 2026: Building Permit Fee is valuation based, with a $167.00 minimum fee for total value of construction work of $1 to $500. The same schedule lists a Zoning Permit Fee, described as a fee for ensuring conformance of zoning code standards, at $48.00 for 1 and 2 family dwellings. A 12% State of Oregon surcharge applies to building permits. Official fee schedule.
- Apply. Applying for a patio permit means submitting a site plan and framing plans for a roofed patio cover, since a cover is treated as its own permitted structure regardless of size. A plain concrete or paver patio slab at or near grade is, by contrast, often exempt from that same building permit requirement. Start at the Portland permit portal.
- Keep the office details handy. Portland Permitting & Development. Phone: 503-823-7300. Address: Development Services Center, 1900 SW Fourth Avenue, First floor lobby, Portland, OR 97201.
- Plan for inspections. A permitted patio cover follows the same footing, frame, and final inspection sequence used for any small accessory structure, since the posts and roof framing have to be checked before they are covered and again once the work is done. An at grade patio slab that qualifies as exempt flatwork usually needs no building inspection at all, because inspections only attach to work that required a permit in the first place.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a patio permit in Portland?
- Portland does not require a building permit for a plain concrete patio poured on grade; the city instead tells you to contact Planning and Zoning to find out whether a zoning permit is needed. A building permit is required once a patio is covered and the attached patio cover, porch cover, or carport is larger than 200 square feet, or once an existing patio cover is enclosed. A patio slab also needs a permit if it sits more than 30 inches above adjacent grade or over any story or basement. Covers not over 200 square feet and supported by an exterior building wall are listed as work that does not need a building permit. Area of an attached patio cover, porch cover, carport, or other open-sided roofed structure. Always confirm with the office before starting.
- How much does a patio permit cost in Portland?
- Building and Other Permits Fee Schedule for the City of Portland, effective July 10, 2026: Building Permit Fee is valuation based, with a $167.00 minimum fee for total value of construction work of $1 to $500. The same schedule lists a Zoning Permit Fee, described as a fee for ensuring conformance of zoning code standards, at $48.00 for 1 and 2 family dwellings. A 12% State of Oregon surcharge applies to building permits. See the official fee schedule for current amounts.
- How long does a patio permit take in Portland?
- Portland Permitting & Development publishes a first review goal of 7 days for residential alterations and 15 days for residential additions. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a patio permit in Portland?
- You can apply through the Portland permit portal or contact the Portland Permitting & Development directly. The links are listed on this page.
- Can a homeowner pull a patio permit themselves in Portland?
- Under Oregon law (ORS 701.010(7); ORS 701.325(1), (2), (3)): A homeowner may pull the permit and do the work. ORS 701.010(7) exempts from Construction Contractors Board licensing a person performing work on property that person owns, or on that person's own residence whether or not they own it, so no CCB license is needed to act as your own builder. That exemption does not cover someone working in the pursuit of an independent business with intent to offer the structure for sale. Oregon does require a signed disclosure at the counter: ORS 701.325(1) makes every city, county, or state permit office collect a written statement signed by the applicant, and an applicant claiming a licensing exemption must state the basis for it. ORS 701.325(2) requires the office to give the applicant the Information Notice to Property Owners About Construction Responsibilities and withhold the residential building permit until the applicant signs a statement, one option of which is that they are performing work on property they own or a residence they live in or will live in, and that any contractors they hire will be CCB licensed and properly endorsed. The Information Notice itself is a CCB rule form under ORS 701.325(3) covering payroll tax, workers' compensation, and liability and property damage insurance responsibilities. Confirm how Portland applies this before you apply.
From the Library
What else needs a permit in Portland
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | height of the deck walking surface above adjacent grade, taken 36 inches out from the edge of the deck | Building and Other Permits Fee Schedule for the City of Portland, effective July 10... |
| Electrical Permit | It depends | Not specified | Electrical Permit Fee Schedule for the City of Portland, effective July 10, 2026. |
| Fence Permit | It depends | wood and similar materials; 4 feet for masonry or concrete, 8 feet for woven wire or chain link, and any barrier around a swimming pool | Building and Other Permits Fee Schedule for the City of Portland, effective July 10... |
| HVAC Permit | Permit required | Not specified | Mechanical Permit Fee Schedule for the City of Portland, effective July 10, 2026, One &... |
| Plumbing Permit | It depends | Not specified | Plumbing Permit Fee Schedule for the City of Portland, effective July 10, 2026. |
| Pool Permit | It depends | depth of water in a structure used for swimming or recreational bathing | Building and Other Permits Fee Schedule for the City of Portland, effective July 10... |
| Roof Replacement Permit | It depends | Not specified | Building and Other Permits Fee Schedule for the City of Portland, effective July 10... |
| Shed Permit | It depends | in area, or a height over 15 feet from the grade plane to the average height of the highest roof surface; on lots over 2 acres the area trigger rises to 400 square feet when the structure is at least 20 feet from property lines and other structures | Building and Other Permits Fee Schedule for the City of Portland, effective July 10... |
| Solar Permit | Permit required | Not specified | Portland Permitting & Development publishes solar permit fee estimates, noting 'The fees... |
Patio Permit in other Oregon localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Portland documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with Portland Permitting & Development. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page