Electrical Permit in Portland, Oregon

It depends

Sometimes, depending on the project

Before adding a light fixture or outlet, changing a fuse box to circuit breakers, installing an air conditioner, installing, changing or repairing a hard-wired electrical system, installing or modifying low-voltage systems, replacing a service panel, or running new wiring.

Quick answer

Portland requires a residential electrical permit for essentially all fixed wiring work, including adding a light fixture or outlet, running new wiring, replacing a service panel, changing a fuse box to circuit breakers, and installing or modifying low-voltage systems such as security alarms, stereo, computer, and phone systems. The city publishes a short exemption list: fixing appliance cords, replacing a fuse, and replacing an existing appliance such as a garbage disposal or dishwasher. An electrical permit is still required even if a building permit is not, and each unit of a new townhouse project needs its own electrical permit.

Issued by
Portland Permitting & Development
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What an electrical permit costs in Portland

Fee schedule in force
Official scheduleRead .
  • Electrical Permit Fee Schedule for the City of Portland, effective July 10, 2026.
  • Residential Square Foot Wiring Packages for New and Remodels, single or multi-family per dwelling unit, garage and service included: 1,000 square feet or less $408.00, each additional 500 square feet or portion thereof $93.00.
  • Services or Feeders, installation, alteration or relocation: 200 amps $212.00, 201 to 400 amps $298.00, reconnect only $190.00.
  • Branch Circuits, new, alteration or extension per panel: $21.00 with the purchase of a service or feeder fee;
  • without one, $174.00 first branch circuit and $21.00 each additional.
  • A 12% State of Oregon surcharge applies.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Portland

General guide, not specific to this office

What an electrical permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an electrical permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Portland Permitting & Development

Electrical Permit in Portland compared with nearby Oregon localities

LocalityPermit needed?ThresholdWhat each Oregon schedule saysVerified
PortlandIt dependsBefore adding a light fixture or outlet, changing a fuse box to circuit breakers...See schedule
EugenePermit requiredAny sizeSee schedule

Permitting activity in Portland

In 2025, Portland authorized permits for 1,223 new residential housing units (703 single-family, 520 in multi-family buildings), valued at $319M, down from 1,700 the year before. That works out to about 1.9 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 654,033.

What else needs a permit in Portland

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsheight of the deck walking surface above adjacent grade, taken 36 inches out from the edge of the deckBuilding and Other Permits Fee Schedule for the City of Portland, effective July 10, 2026: Building Permit Fee is valuation based; the schedule has the rest
Fence PermitIt dependswood and similar materials; 4 feet for masonry or concrete, 8 feet for woven wire or chain link, and any barrier around a swimming poolBuilding and Other Permits Fee Schedule for the City of Portland, effective July 10, 2026: Building Permit Fee is valuation based; the schedule has the rest
HVAC PermitPermit requiredAny sizeMechanical Permit Fee Schedule for the City of Portland, effective July 10, 2026, One & Two Family Dwelling Fees: minimum fee $167.00
Patio PermitIt dependsarea of an attached patio cover, porch cover, carport, or other open-sided roofed structureBuilding and Other Permits Fee Schedule for the City of Portland, effective July 10, 2026: Building Permit Fee is valuation based; the schedule has the rest
Plumbing PermitIt dependsBefore repairing, replacing, or moving plumbing pipes, adding new piping, capping pipes...Per fixture or item: water heater $63.00, water closet $63.00, tubs, shower or shower pan $63.00, sinks, basins or lavatories $63.00; the schedule has the rest
Pool PermitIt dependsdepth of water in a structure used for swimming or recreational bathingBuilding and Other Permits Fee Schedule for the City of Portland, effective July 10, 2026: Building Permit Fee is valuation based; the schedule has the rest
Roof Replacement PermitIt dependsBefore reroofing a dwelling in a Wildfire Zone, reroofing a townhouse, installing...See schedule
Shed PermitIt dependsin area, or a height over 15 feet from the grade plane to the average height of the highest roof surface; on lots over 2 acres the area trigger rises to 400 square feet when the structure is at least 20 feet from property lines and other structuresBuilding and Other Permits Fee Schedule for the City of Portland, effective July 10, 2026: Building Permit Fee is valuation based; the schedule has the rest
Solar PermitPermit requiredAny sizeSee schedule

Frequently asked questions

Do you need an electrical permit in Portland?
Sometimes: before adding a light fixture or outlet, changing a fuse box to circuit breakers, installing an air conditioner, installing, changing or repairing a hard-wired electrical system, installing or modifying low-voltage systems, replacing a service panel, or running new wiring. If you are unsure how that applies to your project, call the Portland Permitting & Development at 503-823-7300 before you start.
How much does an electrical permit cost in Portland?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Aug 2026. For the figure on your own project, call the Portland Permitting & Development at 503-823-7300.
How long does an electrical permit take in Portland?
The city states the form takes 15 minutes to complete and permits are issued within 24 hours after payment. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for an electrical permit in Portland?
You can apply through the Portland permit portal or contact the Portland Permitting & Development directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Portland?
Under Oregon law (ORS 701.010(7); ORS 701.325(1), (2), (3)): A homeowner may pull the permit and do the work. ORS 701.010(7) exempts from Construction Contractors Board licensing a person performing work on property that person owns, or on that person's own residence whether or not they own it, so no CCB license is needed to act as your own builder. That exemption does not cover someone working in the pursuit of an independent business with intent to offer the structure for sale. Oregon does require a signed disclosure at the counter: ORS 701.325(1) makes every city, county, or state permit office collect a written statement signed by the applicant, and an applicant claiming a licensing exemption must state the basis for it. ORS 701.325(2) requires the office to give the applicant the Information Notice to Property Owners About Construction Responsibilities and withhold the residential building permit until the applicant signs a statement, one option of which is that they are performing work on property they own or a residence they live in or will live in, and that any contractors they hire will be CCB licensed and properly endorsed. The Information Notice itself is a CCB rule form under ORS 701.325(3) covering payroll tax, workers' compensation, and liability and property damage insurance responsibilities. Confirm how Portland applies this before you apply.

From the Library

Electrical Permit in other Oregon localities

Everything above, sourced

How this electrical permit page for Portland was verified. 2 official sources: portland.gov, portland.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Portland Permitting & Development. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

It depends
Check my project