Louisiana / New Orleans

Electrical Permit in New Orleans, Louisiana

Permit required

Yes, a permit is required

Before installing, repairing, replacing, or altering any electrical apparatus or equipment.

Confirmed on official page Verified

Issued byCity of New Orleans Department of Safety and Permits

By Mario Bailey, verified against official sources

Permit fee
$40
from the published schedule

Quick answer

New Orleans requires an electrical permit for any installation, repair, replacement, or alteration of electrical apparatus or equipment, with the only carve-out being replacement of light bulbs and fuses. There is no dollar value, circuit count, or voltage threshold below which the permit is waived. The permit can only be obtained by an electrical contractor holding a Class A Electrical License from the City of New Orleans, so a homeowner cannot apply for it. A building permit may also be required for some electrical permits.

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before installing, repairing, replacing, or altering any electrical apparatus or equipment.

What an electrical permit costs in New Orleans

Line item
electrical permit$40$40 application fee plus $3 per new circuit plus $0.30 per service amperage. $40 per construction loop. $60 per elevator, moving stair, dumbwaiter, man lift installation / modification. $40 per sign, indoors or outdoors. Electrical Permit page, last updated 5/11/2026.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in New Orleans

In New Orleans, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • For New Orleans, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • For New Orleans, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of New Orleans Department of Safety and Permits sets the exact checklist for New Orleans.

Where to apply in New Orleans:

City of New Orleans Department of Safety and Permits

  • 1340 Poydras Street, Suite 800, New Orleans, LA 70112
  • Phone: (504) 658-7200
  • Email: permitinfo@nola.gov

Electrical Permit in New Orleans compared with nearby Louisiana localities

LocalityPermit needed?ThresholdWhat each Louisiana schedule saysVerified
New OrleansPermit requiredAny size$40 application fee plus $3 per new circuit plus $0.30 per service amperage
Baton RougeIt dependsBefore adding, replacing or extending any electrical circuit, and before replacing a......page: "Residential Mechanical, Electrical or Plumbing, Gas Trade Permits $125.00"...

Inspections and closing out your permit

In New Orleans, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. In New Orleans: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. In New Orleans: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. In New Orleans: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. In New Orleans: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. In New Orleans: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. In New Orleans: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. In New Orleans: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the New Orleans permit portal or by phone at (504) 658-7200.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in New Orleans?
New Orleans requires an electrical permit for any installation, repair, replacement, or alteration of electrical apparatus or equipment, with the only carve-out being replacement of light bulbs and fuses. There is no dollar value, circuit count, or voltage threshold below which the permit is waived. The permit can only be obtained by an electrical contractor holding a Class A Electrical License from the City of New Orleans, so a homeowner cannot apply for it. A building permit may also be required for some electrical permits. Always confirm with the City of New Orleans Department of Safety and Permits before starting.
How much does an electrical permit cost in New Orleans?
$40 application fee plus $3 per new circuit plus $0.30 per service amperage. $40 per construction loop. $60 per elevator, moving stair, dumbwaiter, man lift installation / modification. $40 per sign, indoors or outdoors. Electrical Permit page, last updated 5/11/2026. See the official fee schedule for current amounts.
Where do you apply for an electrical permit in New Orleans?
You can apply through the New Orleans permit portal or contact the City of New Orleans Department of Safety and Permits directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in New Orleans?
Under Louisiana law (La. R.S. 37:2157(A)(2), (A)(13), (A)(15)(a), (B); La. R.S. 37:2160(B) and (C)): Yes. R.S. 37:2157(A)(13) exempts an owner who supervises or takes charge of construction, alteration or repair of his own personal residence from the contractor licensing law, but caps the exemption at one residence per year, with the year running from the date the certificate of occupancy issues; the cap lifts only where a change in the owner's legal marital status, or a change in employment forcing a move more than 50 miles from his residence, requires a second home. A separate exemption at R.S. 37:2157(A)(2) covers an owner who takes charge of work on his own property for his own use, where the result will not be for sale or rent and the owner controls access. A residential property owner who physically performs home improvement work on his own residence is also exempt from home improvement licensure under R.S. 37:2157(A)(15)(a). The exemption is not self-executing at the permit counter: R.S. 37:2157(A)(13) requires an affidavit of exemption on a board form in order to obtain the building permit, and R.S. 37:2160(C) obliges the local permit official to collect that affidavit before the permit issues. R.S. 37:2157(B) adds that none of these exemptions waives local or state health and life safety code requirements, so an exempt homeowner still owes the permit and the inspections. Confirm how New Orleans applies this before you apply.

From the Library

What else needs a permit in New Orleans

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsdeck area, with the exemption also requiring the deck be uncovered, no more than thirty inches high from grade at any point, detached from the dwelling unit, and not serving an exit doorBuilding permit fee is $60 plus $5 per $1,000 of work to be performed (job value x .005...
Fence PermitIt dependsheight of the fence, with the exemption also requiring compliance with the Comprehensive Zoning OrdinanceBuilding permit fee is $60 plus $5 per $1,000 of work to be performed (job value x .005...
HVAC PermitPermit requiredAny sizeSee schedule
Patio PermitIt dependsBefore adding a roof or cover over a patio, and before any paving that does not comply...Where a permit is required, the building permit fee is $60 plus $5 per $1,000 of work to...
Plumbing PermitPermit requiredAny sizeSee schedule
Pool PermitPermit requiredAny size$60 plus $5 per $1,000 of work to be performed
Roof Replacement PermitIt dependsshare of the roof replaced, for single and two-family homesBase Fee: $60
Shed PermitPermit requiredAny size$60 plus $5 per $1,000 of work to be performed
Solar PermitPermit requiredAny size...for rooftop solar are classified as Electrical Permits with associated costs of $40...

Electrical Permit in other Louisiana localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not New Orleans documents; the office above sets the local rules.

How this electrical permit page for New Orleans was verified. 2 official sources: nola.gov, nola.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of New Orleans Department of Safety and Permits. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across Louisiana localities

Electrical permit rules nationwide

Permit required $40
Get quotes