What Is a Certificate of Occupancy? When You Need One and How to Get It

A certificate of occupancy is the building department saying a finished building may be used. When the code requires one, what it has to state, how to get it after the final inspection, and what a temporary one allows, quoted from the model code and two state rules.

A certificate of occupancy, usually shortened to CO, is the building department’s written statement that a finished building, or a finished part of one, has passed its inspections and may be lived in or used. You need one before you move into a new house. For most other projects you need a passed final inspection, which some offices record as a CO and others as a “certificate of completion”.

If you are waiting on one right now, the next step is the same everywhere: make sure every inspection on the permit, including the final, shows as passed, then ask the office that issued the permit how it issues the certificate. If you are buying a house and want to know whether one exists, look up the permit history first.

What the code actually says

Most states and cities build their residential rules on the International Residential Code. Its Section R110.1 is short and absolute: “A building or structure shall not be used or occupied in whole or in part, and a change of occupancy of a building or structure or portion thereof shall not be made, until the building official has issued a certificate of occupancy therefor as provided herein.”

Two exceptions follow, and they matter for most homeowner projects:

  1. “Certificates of occupancy are not required for work exempt from permits under Section R105.2.” That is the model code’s list of work that needs no permit at all, such as a small detached shed or painting.
  2. “Accessory buildings or structures.” A detached garage, a shed or a similar outbuilding does not get its own CO under the model text, even when it needed a permit.

So the model code ties the certificate to the main building being used: a new house, an addition people will live in, or a change in how a building is used. Your local code can add to that, as the examples below show.

When you need one, project by project

ProjectUnder the model codeWhat changes locally
New houseYes, before anyone moves inPittsburgh does not require one for houses (below)
Addition you will live inYes, it is part of the building being occupiedTennessee’s state rules set a size line (below)
Interior remodelNot addressed separately; ask the office whether it issues a new oneMichigan sets a 30-day limit (below)
Shed or detached garageNo: accessory buildings are exceptedA permit and final inspection may still be required
DeckNo separate CO in the model textGwinnett County, Georgia issues a Certificate of Completion
PoolNo separate CO in the model textGwinnett County issues a CO before the pool may be used

An accessory dwelling unit is a dwelling of its own, so it goes through the full permit and final sequence; whether you may build one at all is a zoning question our guide to ADU permits and state ADU laws answers.

Two state rules show how much the edges move.

Tennessee (where the state, not a city or county, enforces the residential code): a new home, or “any additions thereto of thirty (30) square feet or more of interior space,” built after the dates in the rule, “shall not be occupied until the Division has issued a certificate of occupancy.” The certificate “shall be issued after the passage of all inspections required by this chapter and passage of the final electrical inspection.”

Michigan writes the alteration case into statute. A building that is altered “shall not be used or occupied until such a certificate has been issued, except that a use or occupancy in an already existing building or structure that was not discontinued during its alteration may be continued for 30 days after completion of the alteration without issuance of a certificate of use and occupancy.” In plain terms: you can keep living in the house while the kitchen is redone, but the certificate is due within 30 days of finishing.

And one city that goes the other way: Pittsburgh’s permit office states that “Single-family dwellings and townhouses do not require Certificates of Occupancy.” Permitted work on a house there is still inspected; the city just does not require the certificate for that building type.

Pools and decks show that the word changes even inside one county. Gwinnett County’s pool requirements say the listed inspections “must be successfully passed and a Certificate of Occupancy (CO) issued prior to pool use or occupancy,” while its deck requirements call for a final inspection and “a Certificate of Completion” before use. Both are the same thing in practice: written proof the final inspection passed.

For the permits an addition needs before it gets that far, including zoning, septic and the flood-zone 50 percent rule, see our guide to home addition permits.

How to get a certificate of occupancy

The certificate is the last step of the permit you already have, not a separate project. Some offices issue it once the final passes; others, as in Michigan, act on a written request.

  1. Pass every inspection on the permit. The model code’s final inspection rule is one sentence: “Final inspection shall be made after the permitted work is complete and prior to occupancy.” Trade permits count too: Tennessee will not issue the certificate until the final electrical inspection has passed.
  2. Clear anything the inspector wrote up. A certificate cannot issue over an open correction. Our guide to a failed inspection covers what to do with a correction notice.
  3. Request the certificate if your office requires a request. Michigan’s statute puts a clock on the office: when a building qualifies, the agency “shall issue a certificate of use and occupancy within 5 business days after receipt of a written application,” and it must give the owner “at least 12 hours’ notice of the time of any final inspection.”
  4. Expect the utilities to wait for it on new construction. The model code says no one may connect power, fuel, water or sewer to a building that needs a permit “until approved by the building official.” On a new house, ask the office how its utility release and its certificate fit together, so you are not scheduling movers around a meter that cannot be set.

When the certificate issues, the model code lists what it has to state: the permit number, the address, the owner, a description of the portion covered, a statement that it was inspected for compliance, the building official’s name, the code edition the permit was issued under, whether an automatic sprinkler system is provided and required, and any special conditions of the permit. Keep a copy with your house records: it is the one document that shows the finished work was accepted.

Temporary certificates of occupancy

A temporary certificate of occupancy, or TCO, lets you move into part of a building before every item on the permit is done. The model code allows it “provided that such portion or portions shall be occupied safely,” and the building official “shall set a time period during which the temporary certificate of occupancy is valid.”

Michigan’s version is issued “on request of a holder of a building permit,” when the finished parts can be used “without endangering the health or safety of the occupants or users.” Tennessee’s state program charges for it: “The fee for a consultation inspection or a temporary certificate of occupancy shall be one hundred dollars ($100.00).”

A TCO is a deadline, not a finish line. When it lapses, the occupancy it allowed lapses with it, so put the expiry date somewhere you will see it.

Living in a house without one

The model code makes it unlawful to “occupy any building, structure or equipment regulated by this code” in violation of the code, and an unissued certificate is exactly that. What follows is the same sequence as any other violation: a written notice, then, if it is ignored, the building official may ask the jurisdiction’s lawyer to go to court “to require the removal or termination of the unlawful occupancy.” Fines are “as prescribed by law,” which means by your state or local code, not the model text.

The building official can also take a certificate back: Section R110.4 allows suspending or revoking it when it “is issued in error, or on the basis of incorrect information supplied,” or when the building is found in violation.

What the penalty is in your state, and whether a permit can be obtained after the fact, is on each state page in our unpermitted work guides, for example Michigan and Tennessee.

If your house never had a certificate of occupancy

Everything in the section above is about a building that needed a certificate and never got one. Many houses are in a different position: no certificate was ever required, or the office records the same approval under another name. A missing certificate in a file search is a question to ask, not proof of a violation.

There are three common reasons a house has none, and each office we read shows one of them:

  1. The house is older than the rule. New York City says it plainly: “Buildings built before 1938 aren’t required to have a Certificate of Occupancy,” unless “later alterations changed its use, egress or occupancy.” Michigan’s statute is written forward from the day it took effect: “A building or structure hereafter constructed shall not be used or occupied in whole or in part until a certificate of use and occupancy has been issued.”
  2. The office does not issue one for houses. Pittsburgh: “Single-family dwellings and townhouses do not require Certificates of Occupancy.” There, a passed final inspection on each permit is the record that matters.
  3. It goes by another name. Sacramento County: “Your signed job card for final is your Certificate of Occupancy for Residential projects only.” New York City issues “a Letter of Completion” for minor alterations that need no new or amended certificate.

Where a buyer, lender or insurer wants proof that an old house’s use is legal, some offices issue a letter instead of a certificate. New York City’s is the Letter of No Objection: for “buildings built or altered prior to 1938 and a CO was not required at that time, a Letter of No Objection may be issued to confirm the legal use of the building,” requested from the borough office. We have not surveyed which other offices issue an equivalent letter. The same page lists what blocks a new certificate there: “To obtain a CO there cannot be any open applications or violations on the property.”

What to do with an older house and no certificate on file:

  1. Pull the permit history for the address (our guide to finding out whether a permit was pulled covers how).
  2. Check the dates: work after the house was built (an addition, a converted garage, a finished basement) should each show a permit with a passed final.
  3. Ask the office what document it uses for a house of that age. You can send:

For [address], built about [year], please tell me whether a certificate of occupancy was issued or required. If none was required, do you issue a letter confirming the legal use of the building, and how do I request it?

If the history shows work with no final, that work, not the missing certificate, is the problem to solve. Our guides to what happens after unpermitted work is reported and after-the-fact permit fees walk through legalizing it.

Certificate of occupancy, certificate of completion, final inspection

These three names cover overlapping ground, and offices use them loosely:

  • Final inspection: the inspection itself, the last one on a permit.
  • Certificate of completion: a record that the work on a permit passed its final, typically for work on a building already in use, as Gwinnett County does for decks.
  • Certificate of occupancy: permission to use or occupy the building or part of it. Required by the model code for new buildings and changes of occupancy; some places, like Gwinnett County for pools, also use it for specific structures, and some, like Pittsburgh for houses, do not require it at all.

If a seller tells you the work “passed final,” ask for the record. Your jurisdiction’s permit office, portal and phone number are on its page in our verified index.

Method

Every quotation above was read on the official source listed below on November 5, 2026: the 2024 International Residential Code on ICC’s own digital codes site, the Michigan Legislature’s statute text, the Tennessee Secretary of State’s copy of the State Fire Marshal rules, and the Pittsburgh and Gwinnett County permit offices’ own pages and handouts. The section on houses that never had a certificate was added on November 18, 2026, from New York City’s Department of Buildings page, Michigan’s statute, Pittsburgh’s residential permits page and Sacramento County’s permit FAQ, each read on its official site that day. Your state may adopt a different edition of the model code or amend it; your local building department’s reading is the one that applies to your house.

Sources

Get rule-change alerts

We catch permit rule and fee changes in our verification passes and post them to the rule tracker. Get them by email instead.

We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.