Building Without a Permit Fees: What an After-the-Fact Permit Costs

The model code leaves the penalty to your local office, and offices charge anything from a flat $30 to many times the permit fee. The most common rule is double. The rules of 32 building departments read on their own schedules and codes, a worked example, the waivers that exist, and the costs beyond the fee.

You pay the permit fee you skipped, plus a penalty your local office sets. Usually the penalty equals the fee, so the permit costs twice as much as it would have. Some offices triple or quadruple it, a few charge a flat amount, and the work may have to be opened up so an inspector can see it, which often costs more than the fee itself.

Who sets the amount
Your city or countyThe model code names no figure
Most common rule
Double the permit fee
Highest we read
Nine times the issuance feeSan Francisco, plus the original permit fee
Lowest we read
A $30 processing feeBurlington, Vermont, on work costing $3,000 or less
Often costs more than the fee
Opening walls and finishes for inspection

The building code most states adopt does not name a number. The 2024 International Residential Code, Section R108.6: “Any person who commences work requiring a permit on a building, structure, electrical, gas, mechanical or plumbing system before obtaining the necessary permits shall be subject to a fee established by the applicable governing authority that shall be in addition to the required permit fees.” Every multiplier below is a local choice, which is why two neighboring counties can charge very differently.

The next step: open your own building department’s fee schedule and search it for “work commencing before permit issuance,” “investigation fee,” “work without permit” or “penalty.” That one line is your answer. The rest of this page shows what those lines say where we read them, so you know what you are looking for.

The rules, from the documents themselves

All of these were read on the office’s own schedule or code on November 13, 2026.

The penalty equals the fee: you pay twice

  • Los Angeles County, California: “Investigation fee for work done without a required permit shall be equal to the permit fee, but not less than” $504.47, or $252.23 for one or two family dwellings when the work is done by an owner-builder (schedule effective July 1, 2026).
  • Louisville, Kentucky: “If you start work without getting the required permit, you’ll be charged a penalty fee equal to the standard permit fee. For electrical work, the minimum penalty is $1,000.” The city’s electrical page says $1,000 “the first time and $2,000 for each time after that.”
  • Cincinnati, Ohio: “The inspection fee is equal to the applicable permit fee and is charged in addition to the permit fee,” up to a maximum of $1,695 (schedule effective July 1, 2026).
  • Arlington, Texas: “Penalty for Work Without a Permit (in addition to the permit fee charged),” equal to the permit fee (schedule effective October 1, 2026).
  • Cheyenne, Wyoming: “The investigation fee shall be in an amount equal to the permit fee” (City Code 15.10.020(H)).
  • Columbia, South Carolina: “a penalty of 100 percent of the usual permit fee in addition to the required permit fee” (Code Sec. 5-204(c)).
  • Miami-Dade County, Florida: “an additional fee of one hundred percent 100% of the usual permit fee in addition to the required permit fee established herein” (Implementing Order 4-63).

The fee is doubled

  • Birmingham, Alabama: “the fees herein specified shall be doubled” (Technical Code 2024, Sec. 104.2).
  • Lexington, Kentucky: “DOUBLE PERMIT FEES WILL BE IMPOSED FOR WORK STARTED WITHOUT A PERMIT.”
  • Greensboro, North Carolina: “BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT.”
  • Charleston, South Carolina: work “started or proceeded prior to obtaining said permit, the fees herein specified shall be doubled.”
  • Memphis and Shelby County, Tennessee: “WORK COMMENCING BEFORE PERMIT ISSUANCE- SHALL BE DOUBLE.”
  • Meridian, Idaho: “Double permit fees will be the minimum charge assessed” for building, electrical, mechanical and plumbing work begun without a permit.
  • Portland, Maine: building work “may be subject to double the permit fee, per Sec 6-92(d)”; for plumbing and electrical work the schedule says “will be subject.”
  • Pinellas County, Florida: “Normally, after-the-fact permits cost double.”
  • Harris County, Texas (unincorporated): “All permit applications submitted to abate violation(s) shall be subject to a double fee.”
  • Town of Hempstead, New York: a building permit for work begun first costs $400 for residential work up to $1,000 in cost, against $200 when the permit comes first, plus $36 rather than $18 for each additional $1,000 (Code Sec. 86-11C).
  • Hawaii County, Hawaii: “either $1,000 plus the fees specified by this code, or the fees specified by this code shall be doubled, whichever is greater” (Sec. 5-7-3(d)). On a small job, the $1,000 governs. Emergency work done when there was no time to get a permit is excepted.

Three times or more

  • Little Rock, Arkansas and Kansas City, Missouri: the fee “shall be tripled.”
  • Cambridge, Massachusetts (mechanical): “Triple the permit fee.”
  • Tulsa, Oklahoma: a penalty “in addition to the regular permit fee” of “Two Hundred Fourteen Dollars ($214.00) or three times (3x) the cost of the regular fee, whichever is greater.” In total you pay at least four times the fee.
  • Franklin County, Ohio (unincorporated): a $150 base penalty fee plus three times the fee.
  • Mecklenburg County (Charlotte), North Carolina: a “Fee for Work Started without a Permit” of the original permit fee times 3.75 (Fee Ordinance item 29, revised July 1, 2026). The ordinance does not say whether that replaces the permit fee or is charged on top of it, so ask.
  • Omaha, Nebraska: “When construction begins before the permit has been issued, the applicant shall pay a penalty fee. Said fee shall be quadruple the amount of the regular fee” (Sec. 43-91). The penalty is four times the fee, charged with the permit fee itself.
  • Milwaukee, Wisconsin: “the fees specified in this section may be quadrupled.” The word is may, so it is up to four times.
  • San Francisco, California: “For work without a building permit, the penalty is nine times the issuance fee plus the original permit fee.”

A flat charge or a sliding one

  • Baltimore County, Maryland (plumbing): “In addition to the regular permit fee, an investigation fee of $60.00 shall be collected.”
  • Montgomery County, Maryland: an “Initial Inspection of sites where working without a permit fee” of $186.55 (schedule effective July 1, 2026).
  • Ann Arbor, Michigan (electrical, mechanical and plumbing): “Work without permit,” $130, on schedules dated 2017 and 2020.
  • Burlington, Vermont: when an inspector’s enforcement results in a permit, an administrative processing fee of $30 where the work costs $3,000 or less, and 1 percent of the whole estimated cost on jobs of $3,000 or more (Sec. 8-28(f)).
  • Fargo, North Dakota: the permit fee doubles for work valued up to $50,000; from $50,001 to $500,000 the charge is 50 percent of the permit fee (minimum $550), and above $500,000 it is 25 percent (minimum $2,000).

A worked example: one $200 permit, eight offices

Say the permit you should have pulled for a deck would have cost $200. Here is what the same permit costs after the fact under each rule above, before any fines or code corrections:

OfficeRuleYou pay
Columbia, SCFee plus 100 percent$400
Cincinnati, OHFee plus an equal investigation fee$400
Birmingham, ALDoubled$400
Los Angeles County, CAFee plus an investigation fee of at least $504.47 ($252.23 for an owner-builder)$704.47, or $452.23 if you built it yourself
Kansas City, MOTripled$600
Tulsa, OKFee plus the greater of $214 or three times$800
Omaha, NEFee plus a penalty of four times the fee$1,000
Mecklenburg County, NCOriginal fee times 3.75$750, or $950 if charged on top of the fee

On a $200 permit, the penalty runs from $200 to $800. On a $2,000 addition permit, the same rules run from $1,695 (Cincinnati caps its charge there) to $8,000, which is why the multiplier matters most on big jobs.

Where the penalty is waived

A few rules forgive the penalty, and every one of them has conditions:

  • Kansas City does not triple the fee “In case the work is being done at a one-family dwelling by the person who owns and occupies such dwelling and the permit is applied for before the end of the workday following notification.”
  • Omaha imposes no quadruple fee for work “of an emergency nature” when a permit is applied for within 48 hours of the start of the work, and Hawaii County excepts emergency work done when there was no time to get a permit. Fargo’s HVAC and plumbing fee schedules say that in an emergency “a permit must be taken out within 48 hours after commencement of work,” without saying whether the double fee still applies.
  • Amnesty programs come and go. Miami Beach’s ran until April 30, 2026, and Pinellas County waived the penalty on storm repairs through June 30, 2026. Both have ended. Ask your office whether it runs one now; never assume.

The fee is rarely the expensive part

To approve finished work, an inspector has to see it, and much of it is behind drywall. Boulder, Colorado puts it plainly: “Unpermitted work didn’t have the benefit of inspections prior to installation of finishes, so components such as drywall, tile, trim, etc., will need to be removed to allow for inspection of framing, insulation, plumbing, mechanical and electrical work.”

What else offices ask for:

  • The current code, not the one in force when it was built. Boulder: “previously unpermitted work that is not in compliance with the current code cannot be grandfathered, approved through modifications requests or approved through variances.”
  • A licensed trade’s word. Boulder may accept “a letter from a licensed Colorado plumber that they have scoped the underground plumbing work.” Old Lyme, Connecticut requires that a licensed electrician “inspect the work and certify with an affidavit on their letterhead.”
  • Drawings of what exists. Miami Beach’s program asked for as-built plans and “an As-Built Certificate from a State of Florida duly licensed engineer or architect.”

And it does not expire. Fairfax County, Virginia: unpermitted construction rules apply “to all properties, even if they’ve changed owners or if the work was done years ago.” The same page adds the good news: “it is often a simple process to get permits for unpermitted work that is already completed, whether you are subject to a violation or not.”

Getting the permit for work that is already done

Yes, you can permit finished work, and the permit you get is the ordinary one, applied for late. Prince William County, Virginia, publishes the order it expects the steps in, and its last line is the one to aim for: “Code cases are closed after appropriate permits are issued, final inspection is approved, removal of structure in question, etc.” The same sequence applies whether or not anyone has reported the work.

  1. Find out what the office already has. A permit pulled years ago and never finaled is a different problem from no permit at all; our guide to finding out if a permit was pulled shows how to check.
  2. Clear the approvals that come before the building permit. In Prince William County’s list these can include zoning, the environmental office (for a structure in a Resource Protection Area), the health department (where a well or septic system is involved) and the fire marshal, each “when necessary”. A deck or shed that breaks a setback can stall here, before any inspector looks at the framing.
  3. Draw what exists. The plans for a finished project are drawings of what is already there. For a deck, Alexandria, Virginia’s checklist shows what one office’s deck permit asks for: a house location plat with the deck’s size and position, the “Size and location of all footings”, the size and type of lumber for the posts, railings, joists, decking and ledger, the height of the floor above grade, and the stairs and guards. On a built deck those are measurements you take from the deck itself. Some offices skip plans for simple work: Philadelphia lets a violation for working without a permit be cleared with an EZ Permit where the project qualifies, but “Projects involving retaining walls, or new window or door openings are not eligible for an EZ Permit.” San Francisco, as read for our dataset, does not take the simple route for a bathroom: legalizing an unpermitted one goes through the plans route rather than its online permit.
  4. Apply and pay. This is where the penalty rules above come in.
  5. Show the inspector what is hidden. On a finished room that means the wiring, plumbing, framing and insulation behind the walls (see the Boulder rule above). On a deck it means the footings and the ledger connection to the house. We found no office page that sets out how it inspects the footings of a deck already built, so ask before you dig: will the office accept a licensed engineer’s evaluation (Miami Beach’s program asked for an engineer’s or architect’s As-Built Certificate), or does it want a footing exposed?
  6. Pass the final and keep the record. The finaled permit is your proof that the work was approved.

One reason to finish the process even when no one is asking, in a rule as verified in our dataset: Riverside County, California, will not issue a solar permit while an unpermitted pool on the property is unresolved, because solar equipment may only serve construction that passed final inspection. Later permits can depend on earlier ones. If an inspector has already written to you, our guide to what happens after unpermitted work is reported covers the notice, the deadline and the appeal. The Prince William County, Philadelphia and Alexandria pages were read on November 18, 2026.

The fee is not the fine

A doubled fee is what the permit office charges to issue the permit late. It is separate from any fine for the violation itself. Birmingham’s code says so in the same sentence that doubles the fee: payment “shall not relieve any person from fully complying with the requirements of this Code in the execution of the work nor of any other penalties prescribed herein.” State law sets the fine in some states and leaves it to local ordinance in others; our penalties by state page has each state’s statute.

If a licensed contractor did the work without the permit, state licensing boards can discipline them for it; see our guide to what to do when a contractor skips the permit.

What to say when you call

You can ask without giving your address first. A useful script:

“I have work at my home that was done without a permit. What does your office charge to permit finished work, is there an investigation fee or a multiplier on the permit fee, and what will the inspector need to see?”

Ask three follow-ups: whether the work must meet today’s code, whether a licensed electrician’s or plumber’s letter can replace opening a wall, and whether coming forward before a complaint changes the fee. Then bring photos taken before the walls were closed, if you have them, and any receipts or contractor invoices.

Sources

Get rule-change alerts

We catch permit rule and fee changes in our verification passes and post them to the rule tracker. Get them by email instead.

We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.