Colorado / Jefferson County

Shed Permit in Jefferson County, Colorado

By Mario Bailey Last checked 2026-07-06 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

Every shed in unincorporated Jefferson County needs a permit of some kind. Sheds, mini-structures, and shipping containers of 120 square feet or less that sit at least 10 feet from an occupied structure and are no taller than 14 feet only need a Miscellaneous Permit from Planning and Zoning. Sheds larger than 120 square feet, taller than 14 feet, or within 10 feet of an occupied structure need a full Building Permit instead. There is no size at which a shed needs no permit at all.

Typical threshold: Sheds, mini-structures, and shipping containers 120 sq ft or less that sit at least 10 feet from any occupied structure and are no more than 14 feet tall need only a Miscellaneous Permit; anything larger, taller, or closer than 10 feet to an occupied structure needs a full Building Permit instead. Some permit is required at every size.

120 sq ftfootprint
Threshold illustrated: 120 sq ft. Whether Jefferson County requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-07-06.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Jefferson County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before placing any shed, mini-structure, or shipping container in unincorporated Jefferson County

What shed permit costs in Jefferson County

Sheds 120 sq ft or less and at least 10 feet from an occupied structure need only a $90 Miscellaneous Permit; sheds over 120 sq ft, over 14 feet tall, or within 10 feet of an occupied structure need a building permit on the valuation table with a $55 minimum.

Official fee schedule

How Jefferson County compares in Colorado

JurisdictionPermit needed?Threshold
DenverIt dependssheds up to 200 sq ft with 8 ft top plate and 14 ft max height do not require a building permit but may require a zoning permit in some zone districts
Jefferson Countythis pagePermit requiredSheds, mini-structures, and shipping containers 120 sq ft or less that sit at least 10 feet from any occupied structure and are no more than 14 feet tall need only a Miscellaneous Permit; anything larger, taller, or closer than 10 feet to an occupied structure needs a full Building Permit instead. Some permit is required at every size.

Closest shed permit thresholds outside Colorado

Jurisdictions we cover whose limit sits nearest Jefferson County's 120 sq ft.

  • Boston, Massachusetts, one-story detached accessory sheds used for tools or storage are exempt if floor area does not exceed 120 sq ft
  • Chandler, Arizona, One-story detached accessory structures (storage sheds, open-air ramadas) with floor area of 120 sq ft or less and height of 7 ft or less (up to 9 ft with 2 additional feet of setback per additional foot of height) are exempt if not connected to any electrical, gas, or water utility; exceeding either limit or connecting a utility requires a building permit.
  • Houston, Texas, one-story detached accessory structure under 120 sq ft does not require a permit
  • Los Angeles, California, one-story shed under 120 sq ft and under 12 ft in height with no electrical or plumbing does not require a permit

How to apply in Jefferson County

A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Jefferson County Planning & Zoning Division sets the exact checklist for Jefferson County.

Where to apply in Jefferson County:

Jefferson County Planning & Zoning Division

  • 100 Jefferson County Parkway, Suite 3550, Golden, CO 80419
  • Phone: 303-271-8700

Inspections and closing out your permit

A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Jefferson County permit portal or by phone at 303-271-8700.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a shed permit in Jefferson County?
Every shed in unincorporated Jefferson County needs a permit of some kind. Sheds, mini-structures, and shipping containers of 120 square feet or less that sit at least 10 feet from an occupied structure and are no taller than 14 feet only need a Miscellaneous Permit from Planning and Zoning. Sheds larger than 120 square feet, taller than 14 feet, or within 10 feet of an occupied structure need a full Building Permit instead. There is no size at which a shed needs no permit at all. Always confirm with the Jefferson County Planning & Zoning Division before starting.
How much does a shed permit cost in Jefferson County?
Sheds 120 sq ft or less and at least 10 feet from an occupied structure need only a $90 Miscellaneous Permit; sheds over 120 sq ft, over 14 feet tall, or within 10 feet of an occupied structure need a building permit on the valuation table with a $55 minimum. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Jefferson County?
You can apply through the Jefferson County permit portal or contact the Jefferson County Planning & Zoning Division directly. The links are listed on this page.

From the Library

What else needs a permit in Jefferson County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNo exemption by height or size: a Building Permit is required for new decks, deck expansions, replacement decks, and deck repairs. Only a ground-level concrete pad, rather than an elevated deck, avoids the permit.Billed as a building permit on the county valuation fee table starting at a $55 minimum...
Electrical PermitPermit requiredNot specifiedElectrical permits not tied to an active building permit bill on the countywide valuati...
Fence PermitNo permit neededNot specifiedNo permit for fences in unincorporated Jefferson County;
HVAC PermitPermit requiredNot specifiedMechanical permits not tied to an active building permit bill on the countywide valuati...
Patio PermitIt dependsGround-level concrete or paver patios are treated like the exempt concrete pads on the Decks page and do not need a Building Permit; patio covers, roofed patio structures, and patio enclosures (anything that adds a roof or walls) need a Building Permit.Not published
Plumbing PermitPermit requiredNot specifiedPlumbing permits not tied to an active building permit bill on the countywide valuation...
Pool PermitPermit requiredA Miscellaneous Permit is required for swimming pools of any size, in-ground or above-ground, and related structures such as diving boards and ladders; hot tubs and swim spas do not need this permit. Any electrical work for the pool needs a separate Building Safety electrical permit.Pools of any size need a Miscellaneous Permit priced at $90 on the 2026 zoning fee tabl...
Roof Replacement PermitPermit requiredA Building Permit is required for full roof replacement. Only minor roof repairs affecting less than 25% of the total roof area and no more than 2 squares are exempt; anything larger needs a permit plus a mid-roof and a final inspection.Full roof replacement bills as a building permit on the countywide valuation fee table...
Solar PermitPermit requiredRoof-mounted solar panels flush against the roof need no Planning and Zoning permit but always need an Electrical Permit. Panels raised up to 5 feet above the roof need a Miscellaneous Permit from Planning and Zoning in addition to the Electrical Permit. Ground-mount and commercial grid-sale systems have additional requirements.Solar permit fees are capped at $500 for residential systems, per the county Building P...

Shed Permit in other Colorado localities

Official sources

Verified by a person against the sources above on 2026-07-06, not confirmed with Jefferson County Planning & Zoning Division. Rules change; confirm before you build. How we verify.

Last checked: 2026-07-06Report an error on this page