South Carolina / Columbia

Solar Permit in Columbia, South Carolina

Permit required

Yes, a permit is required

Before installing rooftop or ground mounted solar panels at a residence in the city limits.

Quick answer

Columbia requires two permits for a residential solar installation, a building permit and an electrical permit, and says so on the face of its Solar Panel Installation checksheet. Submittals include a scaled site plan and layout at 8.5 by 11 inches minimum showing the address, tax map sheet number, building locations with setbacks, the location and dimensions of the proposed panels, electrical specifications and details, structural engineer certification and structural calculations, with the stamp of a registered surveyor, engineer or architect. Projects in a historic or design district must also obtain a Certificate of Design Approval, and projects in a floodplain or floodway carry supplementary requirements. There is no small system or kilowatt carve out published.

Issued by
City of Columbia Planning and Development Services, Building Inspections Division and Development Center
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your South Carolina Contractor's Licensing Board license active, and under which business name? Verify it on verify.llronline.com.

South Carolina's owner-builder rule (S.C. Code Ann. 40-59-260(A), (B), (C), (E), (F); 40-59-265; 40-59-280; 40-59-20(6), (7); 40-59-30(A)) sets what you may do on your own home without hiring anyone. Read the statute.

What a solar permit costs in Columbia

Fee schedule in force
Official scheduleRead .

Both a building permit and an electrical permit are priced under Code of Ordinances Sec. 5-204(a)(2) for one and two family dwellings: $20.00 for total value of $1.00 to $5,000.00, then $4.00 per $1,000.00 or fraction thereof, plus the $25.00 residential plan review fee.

A contract verifying job cost is not required to accept plans for review but is required before the building permit is issued.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Columbia compares in South Carolina

No South Carolina jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
CharlestonPermit requiredSee schedule
Columbiathis pagePermit requiredSee schedule
Greenville CountyPermit requiredSee schedule

How to apply in Columbia

General guide, not specific to this office

What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

City of Columbia Planning and Development Services, Building Inspections Division and Development Center

Permitting activity in Columbia

In 2025, Columbia authorized permits for 1,956 new residential housing units (910 single-family, 1,046 in multi-family buildings), valued at $337M, down from 2,148 the year before. That works out to about 14.9 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 131,530.

What else needs a permit in Columbia

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeSee schedule
Electrical PermitIt dependsBefore a service change, rewiring, new circuits or any standalone electrical work...See schedule
Fence PermitPermit requiredAny sizeSee schedule
HVAC PermitIt dependsBefore a standalone HVAC change out, new system installation or duct work, unless the...See schedule
Patio PermitPermit requiredAny sizeSee schedule
Plumbing PermitIt dependsBefore a repipe, fixture addition, water heater replacement, sewer work or any...See schedule
Pool PermitIt dependspools that are in ground or permanent above groundSee schedule
Roof Replacement PermitPermit requiredAny sizeSee schedule
Shed PermitPermit requiredAny sizeSee schedule

Frequently asked questions

Do you need a solar permit in Columbia?
Yes, before installing rooftop or ground mounted solar panels at a residence in the city limits. If you are unsure how that applies to your project, call the permit office at (803) 545-3420 before you start.
How much does a solar permit cost in Columbia?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the permit office at (803) 545-3420.
How long does a solar permit take in Columbia?
In Columbia, a solar permit typically takes 5-10 business days. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a solar permit in Columbia?
You can apply through the Columbia permit portal or contact the City of Columbia Planning and Development Services, Building Inspections Division and Development Center directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Columbia?
Under South Carolina law (S.C. Code Ann. 40-59-260(A), (B), (C), (E), (F); 40-59-265; 40-59-280; 40-59-20(6), (7); 40-59-30(A)): South Carolina licenses residential builders and residential specialty contractors under S.C. Code Title 40 Chapter 59, and 40-59-260 exempts the owner of record who builds for himself. The exemption applies only if the owner does the work himself, with his own employees, or with licensed contractors or registered entities, if the structure is intended for the owner's sole occupancy or occupancy by the owner's family and is not intended for sale or rent, and if the general public does not have access to it. The owner must personally appear and sign the building permit application, and the local permitting agency must hand over a disclosure statement whose statutory text reads in part: You must supervise the construction yourself. You may build or improve a one-family or two-family residence. The building must be for your own use and occupancy. It may not be built for sale or rent. The sale restriction is two years and is a presumption rather than a flat bar: 40-59-260(B) makes proof of sale or rent, or of offering for sale or rent, within two years after completion or issuance of a certificate of occupancy prima facie evidence that the project was undertaken for sale or rent, which forfeits the exemption and exposes the owner to the chapter's penalties. South Carolina then adds a step no other state in this wave has: 40-59-260(E) requires the owner to promptly record a notice with the register of deeds, indexed under the owner's name in the grantor index, stating that the building was constructed by the owner as an unlicensed builder, and failure to record revokes the statutory exemption. The exemption is from the licensing chapter, not from the permit, and 40-59-280 requires the building official to refuse a permit unless the applicant furnishes evidence of licensure, registration, or exemption. Confirm how Columbia applies this before you apply.

From the Library

Solar Permit in other South Carolina localities

Everything above, sourced

How this solar permit page for Columbia was verified. 2 official sources: planninganddevelopment.columbiasc.gov, planninganddevelopment.columbiasc.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Columbia Planning and Development Services, Building Inspections Division and Development Center. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project