Solar Permit in Portland, Maine
Permit required
Yes, a permit is required
Installing any rooftop or ground-mounted solar system.
Quick answer
Portland lists installing solar panels among projects that require a building permit, and solar arrays also take an electrical permit priced by system size. The city publishes no exemption for residential solar.
- Issued by
- City of Portland Permitting and Inspections Department
- Phone
- 207-874-8703
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
Maine's owner-builder rule (32 M.R.S. 1201-A(13); 32 M.R.S. 1102-C(5)(A-1); 32 M.R.S. 1102-D; 32 M.R.S. 3302(1)(C); 30-A M.R.S. 4215) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Portland
- Fee schedule in force
- Official scheduleRead .
- Published in
- Building Permits and Inspections Fee Schedule (Revised 7/2026), General Building Permit Fees:
- "Up to $1,000 worth of work" $25.00, "Each additional $1,000 worth of work" $15.00.
- Starting work without a permit "may be subject to double the permit fee, per Sec 6-92(d)" of the Code of Ordinances.
- Electrical Permit Fees (Revised 7/2026), Solar Array: "up to 25KW" $75.00;
- "26KW up to 50KW" $100.00;
- on top of the $75.00 "Administrative Fee / Minimum Fee (applies to all electrical permits)".
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in Portland
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
City of Portland Permitting and Inspections Department
- 389 Congress St, Room 315, Portland, ME 04101
- Phone: 207-874-8703
- Email: permitting@portlandmaine.gov
Your Solar Permit checklist for Portland
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: portlandmaine.gov: permitting inspections.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Portland permit portal.
- Keep the office details handy. City of Portland Permitting and Inspections Department. Phone: 207-874-8703. Email: permitting@portlandmaine.gov. Address: 389 Congress St, Room 315, Portland, ME 04101.
Compiled from the official sources on this page. Last checked .
What else needs a permit in Portland
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Flooring and paint are exempt; remodels, drywall work and any plumbing or electrical work are not | Building Permits and Inspections Fee Schedule (Revised 7/2026), General Building Permit Fees: "Up to $1,000 worth of work" $25.00; the schedule has the rest |
| Deck Permit | Permit required | Any size | Building Permits and Inspections Fee Schedule (Revised 7/2026), General Building Permit Fees: "Up to $1,000 worth of work" $25.00; the schedule has the rest |
| Electrical Permit | Permit required | Any size | Electrical Permit Fees (Revised 7/2026): "Administrative Fee / Minimum Fee (applies to all electrical permits)" $75.00; the schedule has the rest |
| EV Charger Permit | Permit required | Any size | Electrical Permit Fees (Revised 7/2026): $75.00 administrative/minimum fee |
| Fence Permit | It depends | Fence height; any height in a historic district or on a historic-listed property needs a permit | Building Permits and Inspections Fee Schedule (Revised 7/2026), General Building Permit Fees: "Up to $1,000 worth of work" $25.00; the schedule has the rest |
| HVAC Permit | Permit required | Any size | See schedule |
| Plumbing Permit | Permit required | Any size | Plumbing Permit Fees (Revised 7/2026): "Minimum fee (up to four fixtures)" $40.00, "Each additional fixture" $10.00; the schedule has the rest |
| Pool Permit | Permit required | Any size | Building Permits and Inspections Fee Schedule (Revised 7/2026), General Building Permit Fees: "Up to $1,000 worth of work" $25.00; the schedule has the rest |
| Roof Replacement Permit | It depends | Re-shingling with no structural changes is exempt; structural roof work and historic properties are not | No fee when no permit is needed |
| Shed Permit | Permit required | Any size | Building Permits and Inspections Fee Schedule (Revised 7/2026), General Building Permit Fees: "Up to $1,000 worth of work" $25.00; the schedule has the rest |
| Water Heater Permit | Permit required | Any size | Plumbing Permit Fees (Revised 7/2026): "Minimum fee (up to four fixtures)" $40.00 plus "City surcharge for all plumbing permits" $10.00 |
Frequently asked questions
- Do you need a solar permit in Portland?
- Yes. Installing any rooftop or ground-mounted solar system. If you are unsure how that applies to your project, call the City of Portland Permitting and Inspections Department at 207-874-8703 before you start.
- How much does a solar permit cost in Portland?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 8 Nov 2026. For the figure on your own project, call the City of Portland Permitting and Inspections Department at 207-874-8703.
- How long does a solar permit take in Portland?
- The Permitting FAQ (Rev. 12/1/2025) puts the average turnaround for all permits at about 4 to 6 weeks; Fast Track reviews average 10 business days once the application is complete. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a solar permit in Portland?
- You can apply through the Portland permit portal or contact the City of Portland Permitting and Inspections Department directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Portland?
- Under Maine law (32 M.R.S. 1201-A(13); 32 M.R.S. 1102-C(5)(A-1); 32 M.R.S. 1102-D; 32 M.R.S. 3302(1)(C); 30-A M.R.S. 4215): Because Maine does not license general contractors, nothing in state law stops a homeowner from doing their own carpentry or pulling their own town building permit. For electrical work, since a 2025 amendment, a person may wire an existing single-family home they own and occupy without a license and without a state electrical permit, as long as the work meets the National Electrical Code. A new single-family home the owner will live in can also be wired by the owner, but only with a single-family dwelling certificate and a state or local inspection before the wiring is covered. For plumbing, a license is not needed for work in a single-family residence that is or will be the person's own home, as long as it meets the Plumbers' Examining Board's laws and rules; the plumbing permit itself is still required. Confirm how Portland applies this before you apply.
From the Library
Everything above, sourced
How this solar permit page for Portland was verified. 2 official sources: portlandmaine.gov, content.civicplus.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Portland Permitting and Inspections Department. Rules change; confirm before you build. How we verify.