Shed Permit in Cook County, Illinois
It depends
Sometimes, depending on the project
Before building, installing or moving a detached shed, gazebo or detached garage, unless the structure is a prefabricated storage container smaller than 81 square feet.
By Mario Bailey, verified against official sources
Quick answer
Sheds are named explicitly in the Cook County Building Code as structures that cannot be erected without first obtaining a permit. The only size-based carve-out in the code is for prefabricated storage containers less than 81 square feet, so a small prefabricated storage unit can be placed without a permit while a built or larger shed cannot. The county publishes a separate requirements flyer for a detached shed or garage of less than 625 square feet, which requires a plat of survey less than five years old, a site plan, and full construction details.
Typical threshold: prefabricated storage containers.

Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before building, installing or moving a detached shed, gazebo or detached garage, unless the structure is a prefabricated storage container smaller than 81 square feet.
What a shed permit costs in Cook County
How Cook County compares in Illinois
Closest shed permit thresholds outside Illinois
Jurisdictions we cover whose limit sits nearest Cook County's 81 sq ft.
- Charlotte County, Florida, A building permit is not required for plastic or rubber manufactured type sheds 68 square feet or less in area, though they must comply with zoning setbacks and be moved and secured if there is the threat of a tropical storm.
- Sarasota County, Florida, Plastic or rubber storage containers less than 7 feet tall and less than 65 square feet that meet any applicable setback requirements do not need a building permit; all other storage or utility sheds require a permit.
- Arlington, Texas, floor area of a one-story detached tool or storage shed
- Brevard County, Florida, A permit is required for an accessory structure (shed) over 100 square feet.
How to apply in Cook County
A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.
What most shed permit applications include:
- A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
- A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
- Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
- Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
- Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).
General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Cook County Department of Building and Zoning sets the exact checklist for Cook County.
Where to apply in Cook County:
Cook County Department of Building and Zoning
- Cook County Department of Building and Zoning, 69 W. Washington St., Suite 2830, Chicago, IL 60602
- Phone: 312-603-0500
- Email: intake.bnz@cookcountyil.gov
Inspections and closing out your permit
A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.
- Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
- Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
- Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
- For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Cook County permit portal or by phone at 312-603-0500.
Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Shed Permit checklist for Cook County
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: prefabricated storage containers. Usually needed: Before building, installing or moving a detached shed, gazebo or detached garage, unless the structure is a prefabricated storage container smaller than 81 square feet.
- Budget the fee. Cook County Code of Ordinances Sec. 32-1, Building Permit Fee Schedule, item 2-B PRIVATE GARAGES - SHEDS: "Minimum Fee 73.50 or $21.00 each for each 1,000 cubic feet of volume, or fractional part computed from the basement to the highest part of the roof including all projections." A $100.00 residential deposit is payable online and deducted from the final permit fee. Demolition of a shed or private garage is $105.00 under item 4-B. Fee schedule codified through Ord. No. 25-2843, enacted June 12, 2025. Official fee schedule.
- Apply. A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing. Start at the Cook County permit portal.
- Keep the office details handy. Cook County Department of Building and Zoning. Phone: 312-603-0500. Address: Cook County Department of Building and Zoning, 69 W. Washington St., Suite 2830, Chicago, IL 60602.
- Plan for inspections. A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a shed permit in Cook County?
- Sheds are named explicitly in the Cook County Building Code as structures that cannot be erected without first obtaining a permit. The only size-based carve-out in the code is for prefabricated storage containers less than 81 square feet, so a small prefabricated storage unit can be placed without a permit while a built or larger shed cannot. The county publishes a separate requirements flyer for a detached shed or garage of less than 625 square feet, which requires a plat of survey less than five years old, a site plan, and full construction details. Prefabricated storage containers. Always confirm with the office before starting.
- How much does a shed permit cost in Cook County?
- Cook County Code of Ordinances Sec. 32-1, Building Permit Fee Schedule, item 2-B PRIVATE GARAGES - SHEDS: "Minimum Fee 73.50 or $21.00 each for each 1,000 cubic feet of volume, or fractional part computed from the basement to the highest part of the roof including all projections." A $100.00 residential deposit is payable online and deducted from the final permit fee. Demolition of a shed or private garage is $105.00 under item 4-B. Fee schedule codified through Ord. No. 25-2843, enacted June 12, 2025. See the official fee schedule for current amounts.
- Where do you apply for a shed permit in Cook County?
- You can apply through the Cook County permit portal or contact the Cook County Department of Building and Zoning directly. The links are listed on this page.
- Can a homeowner pull a shed permit themselves in Cook County?
- Under Illinois law (225 ILCS 320/3): Whether an owner can pull a building permit is a municipal question in Illinois; there is no state building-permit statute. At the state level, the Plumbing License Law requires that 'all plumbing shall be performed only by plumbers licensed under the provisions of this Act,' but exempts owner-occupants (and lessee-occupants) of single-family residences doing their own plumbing, provided the work meets Illinois State Plumbing Code minimum standards, is submitted for inspection by the Department or local unit, uses no unlicensed helpers ('shall not employ other than a plumber licensed pursuant to this Act to assist'), and the occupant has 'a current intention to live in such premises as his or her bona fide sole and exclusive residence for a period of not less than 6 months after the completion of the plumbing work.' Confirm how Cook County applies this before you apply.
From the Library
What else needs a permit in Cook County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | Cook County Code of Ordinances Sec. |
| Electrical Permit | Permit required | Not specified | Cook County Code of Ordinances Sec. |
| Fence Permit | Permit required | Not specified | Cook County Code of Ordinances Sec. |
| HVAC Permit | Permit required | Not specified | Cook County Code of Ordinances Sec. |
| Patio Permit | Permit required | Not specified | Cook County Code of Ordinances Sec. |
| Plumbing Permit | Permit required | Not specified | Cook County Code of Ordinances Sec. |
| Pool Permit | It depends | prefabricated above-ground pools accessory to detached single-family dwellings | Cook County Code of Ordinances Sec. |
| Roof Replacement Permit | Permit required | Not specified | Cook County Code of Ordinances Sec. |
| Solar Permit | Permit required | Not specified | From the county's Solar Photovoltaic and Thermal System Permit Requirements for... |
Shed Permit in other Illinois localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Cook County documents; the office above sets the local rules.
- IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC
- IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC
Verified by a person against the sources above on , not confirmed with Cook County Department of Building and Zoning. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page